Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2019, February - 2020, February - 2021, February - 2019, March - 2020, March - 2021, March - 2019, April - 2019, April - 2020, April - 2021, May - 2020, May - 2021, July - 2020, July - 2018, August - 2019, August - 2020, September - 2019, September - 2020, September - 2018, October - 2019, October - 2020, November - 2019, November - 2018, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 37.45 37.45 35.100599 173.150599 21.95 89% 87%
December - 2019
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 40 10 10 148.05 21.95 89% 74%
November - 2019
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 40 10 10 148.05 21.95 89% 74%
October - 2019
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 40 10 10 148.05 21.95 89% 74%
September - 2019
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 40 10 0 138.05 21.95 89% 69%
August - 2019
Length 13 Km - earth work completed. Work stopped due to snow bound area. Liability Rs.48.6 m.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 30 30 30 168.05 21.95 89% 84%
May - 2020
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 30 30 30 168.05 21.95 89% 84%
April - 2020
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 30 30 30 168.05 21.95 89% 84%
March - 2020
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 30 30 30 168.05 21.95 89% 84%
February - 2020
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 138.05 40 37.45 37.45 35.100599 173.150599 21.95 89% 87%
January - 2020
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 85.842 14.158 13.804 10.265 5.512 91.354 0 100% 91%
December - 2018
Length 3 Km - structure work in progress. Revised DCE for Rs.138 m submitted to P&D. Pre-PDWP on 15/11/2018.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 85.842 14.158 13.804 10.265 3.512 89.354 0 100% 89%
November - 2018
Length 3 Km - structure work in progress. Revised DCE for Rs.138 m submitted to P&D. Pre-PDWP on 15/11/2018.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 85.842 14.158 13.804 10.265 3.512 89.354 0 100% 89%
November - 2018
Length 3 Km - structure work in progress. Revised DCE for Rs.138 m submitted to P&D. Pre-PDWP on 15/11/2018.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 113.31 85.842 14.158 13.804 13.804 13.804 99.646 13.31 88% 88%
April - 2019
Length 3 Km - structure work in progress.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 113.31 85.842 14.158 13.804 13.804 10.265 96.107 13.31 88% 85%
March - 2019
Length 3 Km - structure work in progress.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 113.31 85.842 14.158 13.804 13.804 10.265 96.107 13.31 88% 85%
March - 2019
Length 3 Km - structure work in progress.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 113.31 85.842 14.158 13.804 13.804 8.57 94.412 13.31 88% 83%
February - 2019
Length 3 Km - structure work in progress.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 113.31 85.842 14.158 13.804 10.265 8.57 94.412 13.31 88% 83%
January - 2019
Length 3 Km - structure work in progress.
No Image
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft)
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
December - 2020
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
December - 2020
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
October - 2020
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
September - 2020
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
August - 2020
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 -
July - 2020
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
May - 2021
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
April - 2021
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
March - 2021
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
February - 2021
No Image
870
(OG)
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 256.52 154.628 0 0 0 0 154.628 0 - -
January - 2021
No Image
870
(OG)
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1198.1 0 0.001 0.001 0.0005 0 0 1198.099 0% -
September - 2018
Tender has been called on 03/10/2018 for flyover at Mingora bypass (Phase-I).
No Image
870
(OG)
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1198.1 0 0.001 0.001 0.0005 0 0 1198.099 0% -
July - 2018
PC-II for Rs.30 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Option finalized, detail design in progress. PC-I/DCE submitted. ACS meeting decision - Mingora Flyover will be taken up only. DCE approved.
No Image
Pages : 1