Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 37.45 | 37.45 | 35.100599 | 173.150599 | 21.95 | 89% |
87% December - 2019 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 40 | 10 | 10 | 148.05 | 21.95 | 89% |
74% November - 2019 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 40 | 10 | 10 | 148.05 | 21.95 | 89% |
74% October - 2019 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 40 | 10 | 10 | 148.05 | 21.95 | 89% |
74% September - 2019 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 40 | 10 | 0 | 138.05 | 21.95 | 89% |
69% August - 2019 |
Length 13 Km - earth work completed. Work stopped due to snow bound area. Liability Rs.48.6 m. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 30 | 30 | 30 | 168.05 | 21.95 | 89% |
84% May - 2020 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 30 | 30 | 30 | 168.05 | 21.95 | 89% |
84% April - 2020 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 30 | 30 | 30 | 168.05 | 21.95 | 89% |
84% March - 2020 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 30 | 30 | 30 | 168.05 | 21.95 | 89% |
84% February - 2020 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 138.05 | 40 | 37.45 | 37.45 | 35.100599 | 173.150599 | 21.95 | 89% |
87% January - 2020 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 85.842 | 14.158 | 13.804 | 10.265 | 5.512 | 91.354 | 0 | 100% |
91% December - 2018 |
Length 3 Km - structure work in progress. Revised DCE for Rs.138 m submitted to P&D. Pre-PDWP on 15/11/2018. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 85.842 | 14.158 | 13.804 | 10.265 | 3.512 | 89.354 | 0 | 100% |
89% November - 2018 |
Length 3 Km - structure work in progress. Revised DCE for Rs.138 m submitted to P&D. Pre-PDWP on 15/11/2018. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 85.842 | 14.158 | 13.804 | 10.265 | 3.512 | 89.354 | 0 | 100% |
89% November - 2018 |
Length 3 Km - structure work in progress. Revised DCE for Rs.138 m submitted to P&D. Pre-PDWP on 15/11/2018. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.31 | 85.842 | 14.158 | 13.804 | 13.804 | 13.804 | 99.646 | 13.31 | 88% |
88% April - 2019 |
Length 3 Km - structure work in progress. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.31 | 85.842 | 14.158 | 13.804 | 13.804 | 10.265 | 96.107 | 13.31 | 88% |
85% March - 2019 |
Length 3 Km - structure work in progress. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.31 | 85.842 | 14.158 | 13.804 | 13.804 | 10.265 | 96.107 | 13.31 | 88% |
85% March - 2019 |
Length 3 Km - structure work in progress. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.31 | 85.842 | 14.158 | 13.804 | 13.804 | 8.57 | 94.412 | 13.31 | 88% |
83% February - 2019 |
Length 3 Km - structure work in progress. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.31 | 85.842 | 14.158 | 13.804 | 10.265 | 8.57 | 94.412 | 13.31 | 88% |
83% January - 2019 |
Length 3 Km - structure work in progress. |
No Image |
1) Palo Dheri to village Jalil road and improvement/rehabilitation of Dubai Adda to village Chargah road PK-29
2) Reconstruction of bridge at Dubai Adda to Charagah (road length 1.6 Km width 12 ft) | |||||||||||||||||||
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- December - 2020 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- December - 2020 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- October - 2020 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- September - 2020 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- August - 2020 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
July - 2020 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- May - 2021 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- April - 2021 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- March - 2021 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- February - 2021 |
No Image | |
870 (OG) |
191566-170328 - Hepatitis Control Program in FATA (phase-III) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 256.52 | 154.628 | 0 | 0 | 0 | 0 | 154.628 | 0 | - |
- January - 2021 |
No Image | |
870 (OG) |
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1198.1 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 1198.099 | 0% |
- September - 2018 |
Tender has been called on 03/10/2018 for flyover at Mingora bypass (Phase-I). |
No Image |
870 (OG) |
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1198.1 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 1198.099 | 0% |
- July - 2018 |
PC-II for Rs.30 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Option finalized, detail design in progress. PC-I/DCE submitted. ACS meeting decision - Mingora Flyover will be taken up only. DCE approved. |
No Image |