Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
867 (OG) |
140620-Re-construction of Bridge at Tor Warsak Daggar & widening / improvement & BT of 18 Km leftover portion of Swarai Pir Qilla Puran Road, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1017.223 | 123.029 | 20 | 20 | 10 | 10 | 133.029 | 874.194 | 14% |
13% September - 2018 |
Bridge - completed. Road - earth work, structure in progress. PC-II for Rs.43.750 m approved in DDWP on 19/06/2017 for construction supervision. |
No Image |
Package-1 (Bridge at Tor Warsak Daggar)
Package-2 (Swarai Pir Qilla Puran Road) | |||||||||||||||||||
867 (OG) |
140620-Re-construction of Bridge at Tor Warsak Daggar & widening / improvement & BT of 18 Km leftover portion of Swarai Pir Qilla Puran Road, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1017.223 | 98.029 | 20 | 20 | 10 | 0 | 98.029 | 899.194 | 12% |
10% July - 2018 |
Bridge - completed. Road - earth work, structure in progress. PC-II for Rs.43.750 m approved in DDWP on 19/06/2017 for construction supervision. |
No Image |
Package-1 (Bridge at Tor Warsak Daggar)
Package-2 (Swarai Pir Qilla Puran Road) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 9.3625 | 9.3625 | 2.5 | 108.218 | 209.782 | 36% |
33% December - 2019 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 10 | 2.5 | 0 | 105.718 | 209.782 | 36% |
32% November - 2019 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 10 | 2.5 | 0 | 105.718 | 209.782 | 36% |
32% October - 2019 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 10 | 2.5 | 0 | 105.718 | 209.782 | 36% |
32% September - 2019 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 10 | 2.5 | 0 | 105.718 | 209.782 | 36% |
32% August - 2019 |
6 units (34.5 Km) - all in progress. Work stopped due to snow bound area. Liability Rs.24.39 m. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 7.5 | 7.5 | 7.5 | 113.218 | 209.782 | 36% |
35% May - 2020 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 7.5 | 7.5 | 7.5 | 113.218 | 209.782 | 36% |
35% April - 2020 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 7.5 | 7.5 | 7.5 | 113.218 | 209.782 | 36% |
35% March - 2020 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 7.5 | 7.5 | 7.5 | 113.218 | 209.782 | 36% |
35% February - 2020 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150829-Rehabilitation/ Reconstruction of a) RCC roads Kumrat, Badgoai & Jandrai Road b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325.5 | 105.718 | 10 | 9.3625 | 9.3625 | 5 | 110.718 | 209.782 | 36% |
34% January - 2020 |
6 units (34.5 Km) - all in progress. |
No Image |
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km) | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 19.5 | 19.5 | 75 | 0 | 100% |
100% December - 2018 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 9.75 | 9.75 | 65.25 | 0 | 100% |
87% November - 2018 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 9.75 | 9.75 | 65.25 | 0 | 100% |
87% November - 2018 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 19.5 | 19.5 | 75 | 0 | 100% |
100% April - 2019 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 19.5 | 19.5 | 75 | 0 | 100% |
100% March - 2019 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 19.5 | 19.5 | 75 | 0 | 100% |
100% March - 2019 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 19.5 | 19.5 | 75 | 0 | 100% |
100% February - 2019 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 55.5 | 19.5 | 19.5 | 19.5 | 19.5 | 75 | 0 | 100% |
100% January - 2019 |
2/2 units in progress. |
No Image |
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft | |||||||||||||||||||
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
02-06-16 | 30-06-18 | - | 07-12-15 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% December - 2017 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% November - 2017 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% October - 2017 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
02-06-16 | 30-06-18 | - | 07-12-15 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% September - 2017 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
02-06-16 | 30-06-18 | - | 07-12-15 | - | 18.6 | 13.608 | 0 | 0 | 0 | 0 | 13.608 | 4.992 | - |
73% August - 2017 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
02-06-16 | 30-06-18 | - | 07-12-15 | - | 18.6 | 13.608 | 0 | 0 | 0 | 0 | 13.608 | 4.992 | - |
73% July - 2017 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 0.604 | 0.604 | 0 | 13.608 | 2.692 | 86% |
73% June - 2018 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
Peshawar | |||||||||||||||||||
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% May - 2018 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
Peshawar | |||||||||||||||||||
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% April - 2018 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
Peshawar | |||||||||||||||||||
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% March - 2018 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
Peshawar | |||||||||||||||||||
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% February - 2018 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
Peshawar | |||||||||||||||||||
867 (OG) |
150639-Renovation of Mines & Minerals Directorate Building. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.6 | 13.608 | 2.3 | 2.3 | 2.3 | 0 | 13.608 | 2.692 | 86% |
73% January - 2018 |
Flooring and roof treatment completed, eletrification and paint work, plumbing work in progress. |
No Image |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- December - 2020 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- December - 2020 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- October - 2020 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- September - 2020 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- August - 2020 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
July - 2020 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- May - 2021 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- April - 2021 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- March - 2021 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- February - 2021 |
No Image | |
867 (OG) |
191563-180285 - Strengthening of National Program for Family Planning and Primary Health Care in all Tribal Districts/Sub-Divisions. [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 452.672 | 49.997 | 0 | 0 | 0 | 0 | 49.997 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |