Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2020, February - 2021, February - 2019, March - 2020, March - 2021, March - 2019, April - 2020, April - 2021, April - 2019, May - 2020, May - 2021, July - 2020, July - 2018, August - 2020, August - 2019, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 35 35 35 174.56 239.177 39% 44%
December - 2019
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 15 15 15 154.56 239.177 39% 39%
November - 2019
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 15 15 15 154.56 239.177 39% 39%
October - 2019
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 15 3.75 3.75 143.31 239.177 39% 36%
September - 2019
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 15 3.75 0 139.56 239.177 39% 35%
August - 2019
5 units - work in progress. Work stopped due to snow bound area. Liability Rs.44.45 m.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 35 35 35 174.56 239.177 39% 44%
May - 2020
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 35 35 35 174.56 239.177 39% 44%
April - 2020
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 35 35 35 174.56 239.177 39% 44%
March - 2020
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 35 35 35 174.56 239.177 39% 44%
February - 2020
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150827-a) Rehabilitaiton/ Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora sharamkand & b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 139.56 15 35 35 35 174.56 239.177 39% 44%
January - 2020
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95 95 95 947.06 145.408 87% 87%
December - 2018
Length 39.45 Km (23 units) - 20 Km completed.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95 95 95 947.06 145.408 87% 87%
November - 2018
Length 39.45 Km (23 units) - 20 Km completed.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95 95 95 947.06 145.408 87% 87%
November - 2018
Length 39.45 Km (23 units) - 20 Km completed.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95.846 95.846 95.846 947.906 145.408 87% 87%
April - 2019
Length 39.45 Km (23 units) - 20 Km completed.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95.846 95.846 95.846 947.906 145.408 87% 87%
March - 2019
Length 39.45 Km (23 units) - 20 Km completed. PC-I/DCE for Rs.1169.485 m submitted to CE North on 11/03/2019 with the request to take appropriate action in light o P&D Deptt.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95.846 95.846 95.846 947.906 145.408 87% 87%
March - 2019
Length 39.45 Km (23 units) - 20 Km completed. PC-I/DCE for Rs.1169.485 m submitted to CE North on 11/03/2019 with the request to take appropriate action in light o P&D Deptt.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95.846 95.846 95.846 947.906 145.408 87% 87%
February - 2019
Length 39.45 Km (23 units) - 20 Km completed. PC-I/DCE for Rs.1169.485 m submitted to CE North on 11/03/2019 with the request to take appropriate action in light o P&D Deptt.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
150848-Impt/Reconst of various roads in UC Fatima, UC Bakhshali and Bala Garhi, UC Elaym UC Mardan rural, UC Garyala, UC Gujrat, UC Babinay, UC Kass Koroona, UC Par Hoti, UC Kot Daulatzai, UC Katakhat & UC Sikandri in PK-30 Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 852.06 95 95 95 95 947.06 145.408 87% 87%
January - 2019
Length 39.45 Km (23 units) - 20 Km completed.
No Image
1) Dalasa Stop to Fatima road 1.5 Km UC Fatima (construction/widening)
2) Hamza Khan to Chagharzo 1 Km UC Fatima (construction/improvement/widening)
3) Gujar Abad to Seri 0.7 Km UC Baala Garhi (construction/improvement/widening)
4) Chamdheri road 1.1 Km UC Bala Garhi (construction/improvement/widening)
5) Bakhshali to Seri 1.5 Km UC Bakhshali (construction/improvement/widening)
6) Charsadda raod Airab to Seri Koroona 1.8 Km UC Mardan Rural (construction/improvement/widening)
7) Karham, Bar Killi and Gila Ther Abad 3 Km UC Galyar (construction/improvement/widening)
8) Chamdheri to Gujar Abad road 1.7 Km UC Bala Garhi (construction/BT)
9) Main Swabi road Sikandari Mashinan Bilal Masjid road 2.3 Km UC Sikandari PK-30 (rehabilitation/improvement)
10) Khan Sher Killi road 2 Km UC Babanay PK-30 (rehabilitation/improvement)
11) Fatima village to Hamza Khan road UC Fatima 1.800 Km (construction/improvement/widening)
12) Akbar Abad road link road Said Abad 1.500 Km UC Garyala (construction/BT)
13) Bakhshali to Chamdheri School road 1.500 Km UC Bakhshali (construction/BT)
14) Par Hoti bridge Mashinian road to Purdil Abad 1.300 Km PK-30 UC Sikandari (rehabilitation/improvement)
15) Main Bakhshali - Charguli road to Gahraib Abad via Kata Khat UC Kata Khat 3 Km (rehabilitation/improvement)
16) Construction/BT of Kot Daulatzai Arbano rado Dheri (1.2 Km UC Kot Daulatzai
17) Rehabilitation/improvement of Dubai Ada to Akbar Abad 1.2 Km
18) Construction/Btof Amjad Abad to Kotar Pan road 1 Km UC Kata Khat Mardan
19) Rehabilitation/improvement of Katlang road to Landay Shah 1.850 Km UC Mardan Rural
20) Construction/BT of Majeed Abad road UC Par Hoti 1 Km PK-30
21) Rehabilitation/improvement of Dangdang village road UC Mardan Rural-I 1 Km
22) Rehabilitation/widening/improvement of Bakhshali to Charguly road 7.5 Km UC Kata Khat Mardan
23) Improvement of road from Swat Expressway to Bakhshali Bazar 2.5 Km
866
(OG)
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera.
Nowshera
PKHA
30-11--1 30-11--1 - 30-11--1 - 1726.703 1783.7 10 10 5 5 1788.7 0 100% 100%
September - 2018
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress.
No Image
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel)
866
(OG)
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera.
Nowshera
PKHA
30-11--1 30-11--1 - 30-11--1 - 1726.703 1353.7 10 10 5 0 1353.7 363.003 79% 78%
July - 2018
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress.
No Image
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel)
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
December - 2020
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
December - 2020
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
October - 2020
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
September - 2020
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
August - 2020
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 -
July - 2020
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
May - 2021
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
April - 2021
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
March - 2021
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
February - 2021
No Image
866
(OG)
191562-140181 - Health Nutrition Program in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 882.249 217.617 0 0 0 0 217.617 0 - -
January - 2021
No Image
Pages : 1