Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
863
(OG)
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1394 1084.65 30 30 15 15 1099.65 279.35 80% 79%
September - 2018
10/14 Km completed, Dargai bypass (3 Km) in progress.
No Image
Package-1
Package-2
Package-3
Package-4
Package-5
863
(OG)
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1394 1084.65 30 30 15 0 1084.65 279.35 80% 78%
July - 2018
10/14 Km completed, Dargai bypass (3 Km) in progress.
No Image
Package-1
Package-2
Package-3
Package-4
Package-5
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
December - 2019
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
November - 2019
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
October - 2019
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 3.75 3.75 113.358 325.392 28% 25%
September - 2019
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 3.75 0 109.608 325.392 28% 24%
August - 2019
Length 10 Km - 4 Km BT completed. Liability Rs.50 m.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
May - 2020
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
April - 2020
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
March - 2020
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
February - 2020
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
140905-Construction, Widening and BT of Usherai Dara and its missing links, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 109.608 15 15 15 15 124.608 325.392 28% 28%
January - 2020
Length 10 Km - 4 Km BT completed.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.424 6 3.904 66.789 5.435 93% 83%
December - 2020
02- Portion Work in progress.
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.424 6 3.904 66.789 5.435 93% 83%
December - 2020
02- Portion Work in progress.
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.424 6 3.904 66.789 5.435 93% 83%
October - 2020
02- Portion Work in progress.
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.424 6 3.904 66.789 5.435 93% 83%
September - 2020
02- Portion Work in progress.
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.424 0 0 62.885 5.435 93% 78%
August - 2020
02- Portion Work in progress.
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 68.32 12.424 0 0 0 68.32 0
July - 2020
No Image
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.415 12.415 3.904 66.789 5.435 93% 83%
May - 2021
02- Portion work stopped due to local dispute
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.415 12.415 3.904 66.789 5.435 93% 83%
April - 2021
02- Portion work stopped due to local dispute
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.415 12.415 3.904 66.789 5.435 93% 83%
March - 2021
02- Portion work stopped due to local dispute
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.415 12.415 3.904 66.789 5.435 93% 83%
February - 2021
02- Portion work stopped due to local dispute
No Image
Non Residential Portion.
Residential portion
863
(OG)
191530-160021 - Completion of Balance Work in Type-D Hospital Jandola, FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 80.744 62.885 12.424 12.424 6 3.904 66.789 5.435 93% 83%
January - 2021
02- Portion Work in progress.
No Image
Non Residential Portion.
Residential portion
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.07 25.6127 26.6127 69.6967 0 100% 70%
December - 2018
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.07 25.6127 14.089 57.173 0 100% 57%
November - 2018
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.07 25.6127 14.089 57.173 0 100% 57%
November - 2018
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.0702 54.0707 54.071 97.155 0 100% 97%
April - 2019
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.0702 54.0707 39.8407 82.9247 0 100% 83%
March - 2019
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.0702 54.0707 39.8407 82.9247 0 100% 83%
March - 2019
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.0702 54.0707 39.8407 82.9247 0 100% 83%
February - 2019
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
863
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.084 56.916 54.07 39.85 39.05 82.134 0 100% 82%
January - 2019
Length 6.5 Km - RW, drain completed.
No Image
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft
Pages : 1