Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, February - 2019, February - 2020, February - 2021, March - 2019, March - 2020, March - 2021, April - 2019, April - 2020, April - 2021, May - 2020, May - 2021, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2018, November - 2019, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 9.3625 9.3625 0 178.923 66.445 74% 70%
December - 2019
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 2.5 0 178.923 66.445 74% 70%
November - 2019
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 2.5 0 178.923 66.445 74% 70%
October - 2019
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 2.5 0 178.923 66.445 74% 70%
September - 2019
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress.
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 2.5 0 178.923 66.445 74% 70%
August - 2019
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress.
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 10 0 178.923 66.445 74% 70%
May - 2020
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 10 0 178.923 66.445 74% 70%
April - 2020
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 10 0 178.923 66.445 74% 70%
March - 2020
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 10 10 0 178.923 66.445 74% 70%
February - 2020
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 178.923 10 9.3625 9.3625 0 178.923 66.445 74% 70%
January - 2020
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. Overlapping With KITE
No Image
PK-92 Dir Upper (Km-1 to 10)
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 170.545 15 9.377 67.429 16.166 93% 28%
December - 2020
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 170.545 15 9.377 67.429 16.166 93% 28%
December - 2020
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 170.545 15 9.377 67.429 16.166 93% 28%
October - 2020
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 170.545 15 9.377 67.429 16.166 93% 28%
September - 2020
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 170.545 0 0 58.052 16.166 93% 24%
August - 2020
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 0 0 0 58.052 16.166 93% 24%
July - 2020
Work in progress, Revised DCE submitted to Director Health Services for amounting to Rs.555.621(M).
No Image
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 42.786 42.786 42.786 100.838 16.166 93% 41%
May - 2021
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 42.786 42.786 42.786 100.838 16.166 93% 41%
April - 2021
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 72.759 72.759 33.33 91.382 16.166 93% 37%
March - 2021
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 72.759 72.759 9.377 67.429 16.166 93% 28%
February - 2021
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
860
(OG)
191535-160440 - Establishment of Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 244.763 58.052 170.545 15 15 9.377 67.429 16.166 93% 28%
January - 2021
Work in progress, Scheme being revised for want of cost of land. (Court Case)
No Image
Type-D Hospital at Tirah Bagh Maidan, Khyber Agency. [MA]
860
(OG)
180163-Improvement and Rehabilitation of Road from Karappa to Shakardara (35 Km), District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 2266.33 0 20 20 10 10 10 0 - -
September - 2018
Electronically submitted bid opened for 3 packages on 07/09/2018. Evaluation under process.
No Image
Kohat
860
(OG)
180163-Improvement and Rehabilitation of Road from Karappa to Shakardara (35 Km), District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 2266.33 0 20 20 10 0 0 0 - -
July - 2018
Summary approved (token grant Rs.50 m). PC-II for Rs.60.760 m approved in DDWP-I on 07/05/2018.
No Image
Kohat
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 3.625 1.135 17.825 10.84 67% 55%
December - 2018
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 3.625 1.135 17.825 10.84 67% 55%
November - 2018
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 3.625 1.135 17.825 10.84 67% 55%
November - 2018
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 4.875 4.875 21.565 10.84 67% 66%
April - 2019
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 4.875 4.875 21.565 10.84 67% 66%
March - 2019
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 4.875 4.875 21.565 10.84 67% 66%
March - 2019
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 4.875 3.625 20.315 10.84 67% 62%
February - 2019
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)
860
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 32.53 16.69 5 4.875 3.625 3.625 20.315 10.84 67% 62%
January - 2019
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress.
No Image
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each)