Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 20 | 20 | 9.999967 | 284.455967 | 926.114 | 23% |
23% December - 2019 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Demand 40 M |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 10 | 10 | 8.453 | 282.909 | 926.114 | 23% |
23% November - 2019 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 10 | 10 | 6.19 | 280.646 | 926.114 | 23% |
23% October - 2019 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 10 | 2.5 | 2.5 | 276.956 | 926.114 | 23% |
23% September - 2019 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 10 | 2.5 | 0 | 274.456 | 926.114 | 23% |
23% August - 2019 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Liability 60 m. Revised DCE submitted for reduced scope (component a proposed for dropping). |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 20 | 20 | 20 | 294.456 | 926.114 | 23% |
24% May - 2020 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Demand 50 M |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 20 | 20 | 20 | 294.456 | 926.114 | 23% |
24% April - 2020 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Demand 50 M |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 20 | 20 | 20 | 294.456 | 926.114 | 23% |
24% March - 2020 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Demand 50 M |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 20 | 20 | 20 | 294.456 | 926.114 | 23% |
24% February - 2020 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Demand 50 M |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 274.456 | 10 | 20 | 20 | 20 | 294.456 | 926.114 | 23% |
24% January - 2020 |
Length 43 Km ) (7 units) - (b) Work in progress in 21 Km. BT 4 Km completed. Demand 60 M |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
845 (OG) |
150868-Construction of Road from Kala-Khtha to Thalikot road, Khair Bara to Dhok Road, Karplia to Hassan Bai road and Soha to Koktri road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 79.788 | 0.001 | 0.001 | 0.0005 | 0 | 79.788 | 120.211 | 40% |
40% September - 2018 |
Length 7 Km (width 12 ft) - out of 4 units, all in progress. |
No Image |
1) Kala - Khtha to Thalikot road
2) Khair Bara to Dhoke road
3) Kariplia to Hassan Bai road
4) Soha to Kakortri road | |||||||||||||||||||
845 (OG) |
150868-Construction of Road from Kala-Khtha to Thalikot road, Khair Bara to Dhok Road, Karplia to Hassan Bai road and Soha to Koktri road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 79.788 | 0.001 | 0.001 | 0.0005 | 0 | 79.788 | 120.211 | 40% |
40% July - 2018 |
Length 7 Km (width 12 ft) - out of 4 units, all in progress. |
No Image |
1) Kala - Khtha to Thalikot road
2) Khair Bara to Dhoke road
3) Kariplia to Hassan Bai road
4) Soha to Kakortri road | |||||||||||||||||||
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- December - 2020 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- December - 2020 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- October - 2020 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- September - 2020 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- August - 2020 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
July - 2020 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- May - 2021 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- April - 2021 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- March - 2021 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- February - 2021 |
No Image | |
845 (OG) |
191529-140180 - Facilitation of Health Setup in FRs (MA) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 432.398 | 255.703 | 0 | 0 | 0 | 0 | 255.703 | 0 | - |
- January - 2021 |
No Image | |
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 4.5005 | 4.5 | 120.915 | 203.585 | 38% |
37% December - 2018 |
Length 13 Km - sub base, WBM, structure work in progress. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 4.501 | 4.5 | 120.915 | 203.585 | 38% |
37% November - 2018 |
Length 13 Km - sub base, WBM, structure work in progress. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 4.501 | 4.5 | 120.915 | 203.585 | 38% |
37% November - 2018 |
Length 13 Km - sub base, WBM, structure work in progress. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 9.4995 | 9.4995 | 125.9145 | 203.585 | 38% |
38% April - 2019 |
Length 18 Km (22 units) - sub base, WBM, structure work in progress on all units. Rs.70 m required for completion of work. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 9.4995 | 9.4995 | 125.9145 | 203.585 | 38% |
38% March - 2019 |
Length 18 Km (22 units) - sub base, WBM, structure work in progress on all units. Rs.70 m required for completion of work. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 9.4995 | 9.4995 | 125.9145 | 203.585 | 38% |
38% March - 2019 |
Length 18 Km (22 units) - sub base, WBM, structure work in progress on all units. Rs.70 m required for completion of work. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 9.4995 | 9.4995 | 125.9145 | 203.585 | 38% |
38% February - 2019 |
Length 18 Km (22 units) - sub base, WBM, structure work in progress opn all units . |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
845 (OG) |
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sher Afzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 330 | 116.415 | 10 | 9.5 | 4.5005 | 4.5 | 120.915 | 203.585 | 38% |
37% January - 2019 |
Length 13 Km - sub base, WBM, structure work in progress. |
No Image |
1) Beka Lar Tordher road (0.50 Km)
2) Zakaria Saleh road (1 Km)
3) Haryan Salah road (1 Km)
4) Jalbai Mian Dhand road (1 Km)
5) Farooq Banda road Jehangira (0.80 Km)
6) Balo Haryan road (3 Km)
7) Swabi Interchange Service road to Sher Afzak Banda Balo road (1 Km)
8) Swabi University road Ambar (2 Km)
9) Jalsai Tordher road (1 Km)
10) Lahor Zara Janazgah road (0.50 Km)
11) Beka Shakh Nabi road (1.50 Km)
12) Beka Lar Tordher road
13) Zakria Salah road
14) Haryan Salah road
15) Jalbai Main Dhand road
16) Farooq Banda Jehangira road Jehangira
17) Balo Haryan road
18) Swabi Interchange Service to Sher Afzal Shah Banda Balo road
19) Swabi University Ambar road
20) Jalsai Tordher road
21) Lahore Zara Janazgah road
22) Beka Shakh Nabi road | |||||||||||||||||||
Pages : 1 |