Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
841
(OG)
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 48.291 43.262 6.737 6.737 3.369 0 43.262 0 100% 90%
September - 2018
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt.
No Image
2 Km, Haripur
841
(OG)
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 48.291 43.262 6.737 6.737 3.369 0 43.262 0 100% 90%
July - 2018
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt.
No Image
2 Km, Haripur
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
December - 2020
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
December - 2020
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
October - 2020
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
September - 2020
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
August - 2020
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 -
July - 2020
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
May - 2021
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
April - 2021
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
March - 2021
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
February - 2021
No Image
841
(OG)
191504-100180 - Physical Rehabilitation Centers in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 386.372 295.97 0 0 0 0 295.97 0 - -
January - 2021
No Image
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.764 0.3618 0 118.507 0 100% 100%
December - 2018
Revised PC-I/DCE for Rs.137.782 m submitted (for inclusion of additional bridge Janglo Pul) to Chief Infra P&D on 25/09/2017. Summary for change of nomenclature is under process. CMD awaited.
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.764 0.362 0 118.507 0 100% 100%
November - 2018
Revised PC-I/DCE for Rs.137.782 m submitted (for inclusion of additional bridge Janglo Pul) to Chief Infra P&D on 25/09/2017. Summary for change of nomenclature is under process. CMD awaited.
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.764 0.362 0 118.507 0 100% 100%
November - 2018
Revised PC-I/DCE for Rs.137.782 m submitted (for inclusion of additional bridge Janglo Pul) to Chief Infra P&D on 25/09/2017. Summary for change of nomenclature is under process. CMD awaited.
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.403 0.403 0 118.507 0 100% 100%
April - 2019
Test pile, pier, pile work, transum completed.
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.3618 0.3618 0 118.507 0 100% 100%
March - 2019
Test pile, pier, pile work, transum completed. Revised PC-I/DCE for Rs.137.782 m submitted. Denied in PDWP.
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.3618 0.3618 0 118.507 0 100% 100%
March - 2019
Test pile, pier, pile work, transum completed. Revised PC-I/DCE for Rs.137.782 m submitted. Denied in PDWP.
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.7638 0.7638 0 118.507 0 100% 100%
February - 2019
Revised PC-I/DCE for Rs.137.782 m submitted . Denied in PDWP
No Image
Swabi
841
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 97.804 118.507 0.804 0.764 0.3618 0 118.507 0 100% 100%
January - 2019
Revised PC-I/DCE for Rs.137.782 m submitted (for inclusion of additional bridge Janglo Pul) to Chief Infra P&D on 25/09/2017. Summary for change of nomenclature is under process. CMD awaited.
No Image
Swabi
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 45 7.5 27.597 129.799 35% 14%
December - 2019
Land acquisiton in progress. Section -17 announed.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 7.5 3.4 23.497 129.799 35% 12%
November - 2019
work started.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 7.5 3.4 23.497 129.799 35% 12%
October - 2019
work started.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 50 12.5 2.85 22.947 129.799 35% 11%
September - 2019
work started.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 50 12.5 2.85 22.947 129.799 35% 11%
August - 2019
work started.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 51.251 51.251 51.251 51.251 71.348 128.548 36% 36%
May - 2020
Test Pile in progress. Section -17 announed.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 45 32.582 52.679 129.799 35% 26%
April - 2020
Test Pile in progress. Section -17 announed.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 45 32.582 52.679 129.799 35% 26%
March - 2020
Test Pile in progress. Section -17 announed.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 45 32.582 52.679 129.799 35% 26%
February - 2020
Test Pile in progress. Section -17 announed.
No Image
PK-82, Swat
841
(OG)
170568-Construction of 2 Km Bypass Road in Barikot District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.896 20.097 50 45 45 7.5 27.597 129.799 35% 14%
January - 2020
Test Pile in progress. Section -17 announed.
No Image
PK-82, Swat