Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2018, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
- - - - - 0 0 0 0 0 0 0 0 - -
December - 2017
E-bid re-invited on 08/01/2018.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2017
Tender floated on 16/11/2017.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2017
Tender floated on 16/11/2017.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 9.983 0 7.949 7.949 7.949 7.949 7.949 2.034 80% 80%
June - 2018
Work in progress.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 9.983 0 8 8 8 5.901 5.901 1.983 80% 59%
May - 2018
Work in progress.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 9.983 0 8 8 8 5.151 5.151 1.983 80% 52%
April - 2018
Work in progress.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 9.983 0 8 8 8 5.151 5.151 1.983 80% 52%
March - 2018
Work in progress.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 9.983 0 8 8 8 2.554 2.554 1.983 80% 26%
February - 2018
Work in progress.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 9.983 0 0 0 0 0 0 9.983 - -
January - 2018
Tender approval under process.
No Image
1) Construction of Street Pavement/Culverts/Drains/RW at UC Hassanzai and UC Hajizai PK-22
2) Construction of Street Pavement/Culverts/Drains/RW at UC Panjpao and UC MC-III Shabqadar PK-22
3) Construction of 0.5 Km road from Kotak Mirzai road to Haji Wasal Khan Qilla Shabqadar PK-22 (CM directive against 2% shares of PFC)
839
(OG)
140656-F/S, Design & Construction of road from (i) Sulam Khand to Sira road (6.50 Km), (ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and (iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km).
Haripur
30-11--1 30-11--1 - 30-11--1 - 399.486 272.592 0.001 0.001 0.0005 0 272.592 126.893 68% 68%
September - 2018
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus.
No Image
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km
839
(OG)
140656-F/S, Design & Construction of road from (i) Sulam Khand to Sira road (6.50 Km), (ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and (iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km).
Haripur
30-11--1 30-11--1 - 30-11--1 - 399.486 272.592 0.001 0.001 0.0005 0 272.592 126.893 68% 68%
July - 2018
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus.
No Image
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 8.06 4 2.805 13.813 0.004 100% 72%
December - 2020
04- Units Work in progress on all units.
No Image
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 8.06 4 2.805 13.813 0.004 100% 72%
December - 2020
04- Units Work in progress on all units.
No Image
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 47.251 11.008 8.06 8.06 4 0.019 11.027 28.183 40% 23%
October - 2020
04- Units Work in progress on all units.
No Image
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 47.251 11.008 8.06 8.06 4 0 11.008 28.183 40% 23%
September - 2020
04- Units Work in progress on all units.
No Image
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 47.251 11.008 8.06 8.06 4 0 11.008 28.183 40% 23%
August - 2020
04- Units Work in progress on all units.
No Image
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 47.251 30.66 8.06 0 0 0 30.66 0
July - 2020
No Image
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 10.062 10.062 2.805 13.813 0.004 100% 72%
May - 2021
04- Units 1. Finishing 2. M/Block Finished & Flooring in progress 3. Completed 4. Completed
No Image
1 CHC Dag Tamanzai Pindiai
2 CD Bara Ghundai Prang Ghar
3 BHU Baro Khel  (TS 6.689)
4 BHU Lagham Ghundai PIndiali
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 10.062 10.062 2.805 13.813 0.004 100% 72%
April - 2021
04- Units Work in progress on all units.
No Image
1 CHC Dag Tamanzai Pindiai
2 CD Bara Ghundai Prang Ghar
3 BHU Baro Khel  (TS 6.689)
4 BHU Lagham Ghundai PIndiali
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 10.062 10.062 2.805 13.813 0.004 100% 72%
March - 2021
04- Units Work in progress on all units.
No Image
1 CHC Dag Tamanzai Pindiai
2 CD Bara Ghundai Prang Ghar
3 BHU Baro Khel  (TS 6.689)
4 BHU Lagham Ghundai PIndiali
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 6.002 6.002 2.805 13.813 0.004 100% 72%
February - 2021
04- Units Work in progress on all units.
No Image
1 CHC Dag Tamanzai Pindiai
2 CD Bara Ghundai Prang Ghar
3 BHU Baro Khel  (TS 6.689)
4 BHU Lagham Ghundai PIndiali
839
(OG)
191521-170040 - Removal of Deficiencies in Existing Health Facilities & Provision of Medicines, Diagnostic/Laboratory Investigation Materials and Instruments on Need Basis in Existing Health Facilities in Mohmand Agency. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.072 11.008 8.06 4 4 2.805 13.813 0.004 100% 72%
January - 2021
04- Units Work in progress on all units.
No Image
1 CHC Dag Tamanzai Pindiai
2 CD Bara Ghundai Prang Ghar
3 BHU Baro Khel
4 BHU Lagham Ghundai PIndiali
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
- - - - - 700 0 170 170 0 0 0 0 - -
December - 2017
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
November - 2017
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
October - 2017
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
June - 2018
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
May - 2018
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
April - 2018
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
March - 2018
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
February - 2018
No Image
839
(OG)
130382-Improvment of Water Supply, Sewerage / Drainage System in Selected Districts of KP.
Provincial
30-11--1 30-11--1 - 30-11--1 - 700 0 170 170 0 0 0 0 - -
January - 2018
No Image
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.833 67.833 49.073 227.808 0 100% 91%
December - 2018
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.833 67.833 36.244 214.979 0 100% 86%
November - 2018
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.833 67.833 36.244 214.979 0 100% 86%
November - 2018
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.8329 67.8329 60.18 238.915 0 100% 96%
April - 2019
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed. Rs.9.424 m required for completion of work.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.8329 67.8329 60.18 238.915 0 100% 96%
March - 2019
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed. Rs.9.424 m required for completion of work.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.8329 67.8329 60.18 238.915 0 100% 96%
March - 2019
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed. Rs.9.424 m required for completion of work.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.8329 67.8329 60.18 238.915 0 100% 96%
February - 2019
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km) in District Swabi. SH: (i) Tarkha Chowk-Shaeedan (2.6 Km), (ii) Nazar Chowk-Ismaila (7 Km), (iii) Mardan Swabi MR-Ismaila (4-Km).
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 178.735 74.561 67.833 67.833 60.18 238.915 0 100% 96%
January - 2019
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
No Image
1) Construcion of road Dobian to Nazar and Tarkha (8 Km) PK-33 width 18 ft
2) Construction of road from Mardan Swabi main road to Ismaila (3 Km) PK-33 width 18ft
3) Construction of road from Tarkha Chowk to Shaheedan (2.60 Km) PK-33 width 18ft
4) Construction of road from Nazar Chowk to Ismaila (6 Km) PK-33  width 18ft
 
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 20 0 20.087 249.254 14% 7%
December - 2019
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 5 0 20.087 249.254 14% 7%
November - 2019
Work in progress.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 5 0 20.087 249.254 14% 7%
October - 2019
Work in progress. Funds will be utilized soon
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 5 0 20.087 249.254 14% 7%
September - 2019
Work in progress.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 5 0 20.087 249.254 14% 7%
August - 2019
Civil work in progress.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 20 15.969 36.056 249.254 14% 12%
May - 2020
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 20 13.534 33.621 249.254 14% 12%
April - 2020
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 20 13.534 33.621 249.254 14% 12%
March - 2020
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 20 13.534 33.621 249.254 14% 12%
February - 2020
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
839
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 20.087 20 20 20 0 20.087 249.254 14% 7%
January - 2020
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
Pages : 1