Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
836 (OG) |
170572-Construction of Qalandarabad Bypass Road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 239.642 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 239.641 | 0% |
- September - 2018 |
Excavation in progress. |
No Image |
Abbottabad | |||||||||||||||||||
836 (OG) |
170572-Construction of Qalandarabad Bypass Road, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 239.642 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 239.641 | 0% |
- July - 2018 |
Work order issued. |
No Image |
Abbottabad | |||||||||||||||||||
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 21 | 21 | 15 | 45 | 15 | 82% |
53% December - 2020 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 21 | 21 | 15 | 45 | 15 | 82% |
53% December - 2020 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 39.481 | 12 | 12 | 42 | 15 | 82% |
50% October - 2020 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 39.481 | 12 | 12 | 42 | 15 | 82% |
50% September - 2020 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 39.481 | 0 | 0 | 30 | 15 | 82% |
36% August - 2020 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 45 | 39.481 | 0 | 0 | 0 | 45 | 0 | 100% |
53% July - 2020 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 30.374 | 30.374 | 29.525 | 59.525 | 15 | 82% |
70% May - 2021 |
3- Units
1 FInishing
2 F/F roof in progress
3 90% Completed |
No Image |
1 Const: of Docotors Hostel (06 Nos)
2 Nurisng Hostel (20 Nos)
3 Repair/Reahb: Old Existing Building | |||||||||||||||||||
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 30.374 | 30.374 | 29.525 | 59.525 | 15 | 82% |
70% April - 2021 |
3- Units
1 FInishing
2 F/F roof in progress
3 90% Completed |
No Image |
1 Const: of Docotors Hostel (06 Nos)
2 Nurisng Hostel (20 Nos)
3 Repair/Reahb: Old Existing Building | |||||||||||||||||||
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 30.374 | 30.374 | 28.569 | 58.569 | 15 | 82% |
69% March - 2021 |
3- Units
1 FInishing
2 F/F roof in progress
3 90% Completed |
No Image |
1 Const: of Docotors Hostel (06 Nos)
2 Nurisng Hostel (20 Nos)
3 Repair/Reahb: Old Existing Building | |||||||||||||||||||
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 30.374 | 30.374 | 21.266 | 51.266 | 15 | 82% |
61% February - 2021 |
3- Units
1 FInishing
2 F/F roof in progress
3 90% Completed |
No Image |
1 Const: of Docotors Hostel (06 Nos)
2 Nurisng Hostel (20 Nos)
3 Repair/Reahb: Old Existing Building | |||||||||||||||||||
836 (OG) |
191522-170071 - Establishment of Residential Flat for Doctors and Reconstruction of Nursing Hostel in AHQ Hospital Landi Kotal District Khyber. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 84.481 | 30 | 39.481 | 21.266 | 21.266 | 15.204 | 45.204 | 15 | 82% |
54% January - 2021 |
3- Units
2 units work in progress, and S.No 3 work order issued but progress of scheme slow due to non release of fund. |
No Image |
1 Const: of Docotors Hostel (06 Nos)
2 Nurisng Hostel (20 Nos)
3 Repair/Reahb: Old Existing Building | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 5.0005 | 5 | 65 | 80 | 47% |
43% December - 2018 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 5.001 | 5 | 65 | 80 | 47% |
43% November - 2018 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 5.001 | 5 | 65 | 80 | 47% |
43% November - 2018 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 10 | 10 | 70 | 80 | 47% |
47% April - 2019 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 8.7505 | 8.75 | 68.75 | 80 | 47% |
46% March - 2019 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 8.7505 | 8.75 | 68.75 | 80 | 47% |
46% March - 2019 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 8.7505 | 8.75 | 68.75 | 80 | 47% |
46% February - 2019 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 Km) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 60 | 10 | 10 | 5.0005 | 5 | 65 | 80 | 47% |
43% January - 2019 |
7 Km - work in progress. |
No Image |
Nowshera | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 47.5 | 47.5 | 37.5 | 141.502 | 55.998 | 73% |
67% December - 2019 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. Damand 50 M P-II |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 50 | 12.5 | 12.5 | 116.502 | 55.998 | 73% |
55% November - 2019 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 50 | 12.5 | 12.5 | 116.502 | 55.998 | 73% |
55% October - 2019 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 50 | 12.5 | 5 | 109.002 | 55.998 | 73% |
52% September - 2019 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 50 | 12.5 | 5 | 109.002 | 55.998 | 73% |
52% August - 2019 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 47.5 | 47.5 | 47.5 | 151.502 | 55.998 | 73% |
72% May - 2020 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. Damand 50 M P-II |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 47.5 | 47.5 | 47.5 | 151.502 | 55.998 | 73% |
72% April - 2020 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. Damand 50 M P-II |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 47.5 | 47.5 | 47.5 | 151.502 | 55.998 | 73% |
72% March - 2020 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. Damand 50 M P-II |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 47.5 | 47.5 | 47.5 | 151.502 | 55.998 | 73% |
72% February - 2020 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. Damand 50 M P-II |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
836 (OG) |
150812-Construction of road from Nusrat chowk to Langarr chowk, shamozai jabbagai road district Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210 | 104.002 | 50 | 47.5 | 47.5 | 47.5 | 151.502 | 55.998 | 73% |
72% January - 2020 |
Length 9 Km - 7 Km BT completed. WBM, structure work in progress in remaining road. Damand 50 M P-II |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||