Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2018, September - 2019, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
828
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 44.12 0.001 0.001 0.0005 0 44.12 155.879 22% 22%
September - 2018
Length 13 Km - out of 5 units, all earth work in progress.
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
828
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 44.12 0.001 0.001 0.0005 0 44.12 155.879 22% 22%
July - 2018
Length 13 Km - out of 5 units, all earth work in progress.
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
December - 2018
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
November - 2018
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
November - 2018
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10.92 10.92 10.92 334.131 416.533 44% 45%
April - 2019
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
March - 2019
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
March - 2019
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
February - 2019
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 749.744 323.211 10 10 10 10 333.211 416.533 44% 44%
January - 2019
Length 23 Km - completed (original scope). Revised scope - in progress.
No Image
Nowshera
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 9.3625 9.3625 2.5 93.471 87.169 54% 50%
December - 2019
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 10 2.5 2.5 93.471 87.169 54% 50%
November - 2019
Length 12 Km (4 units) - earth work, SW in progress. P-II
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 10 2.5 2.5 93.471 87.169 54% 50%
October - 2019
Length 12 Km (4 units) - earth work, SW in progress. P-II
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 10 2.5 0 90.971 87.169 54% 48%
September - 2019
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 10 2.5 0 90.971 87.169 54% 48%
August - 2019
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 13.28 13.28 6.292 97.263 87.169 54% 52%
May - 2020
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 9.3625 9.3625 2.5 93.471 87.169 54% 50%
April - 2020
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 9.3625 9.3625 2.5 93.471 87.169 54% 50%
March - 2020
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 9.3625 9.3625 2.5 93.471 87.169 54% 50%
February - 2020
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
141004-F/S, Design and Rehabilitation of Roads a) Martung to Dedal b) Shikolai to Anawar (3 Km) c) Awarai to Kandona (2Km) & d) Fiza to Alagram (1Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 90.971 10 9.3625 9.3625 2.5 93.471 87.169 54% 50%
January - 2020
Length 12 Km (4 units) - earth work, SW in progress. Deamnd Rs.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 2.792 4.677 5.727 45% 45%
December - 2020
08- Units completed =02 In progress =06
No Image
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 2.792 4.677 5.727 45% 45%
December - 2020
08- Units completed =02 In progress =06
No Image
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
October - 2020
08- Units completed =02 In progress =06
No Image
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
September - 2020
08- Units completed =02 In progress =06
No Image
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
August - 2020
08- Units completed =02 In progress =06
No Image
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
May - 2021
08- Units All Completed
No Image
1 Model CHC Ladha
2 BHU Kanigurram
3 BHU Umar Raghzai
4 CHC Baloch
5 CHC Abdul Baqi
6 CHC Gulsa Khan
7 CD Karam
8 CD Dray Dakai
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
April - 2021
08- Units all completed
No Image
1 Model CHC Ladha
2 BHU Kanigurram
3 BHU Umar Raghzai
4 CHC Baloch
5 CHC Abdul Baqi
6 CHC Gulsa Khan
7 CD Karam
8 CD Dray Dakai
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
March - 2021
08- Units completed =02 In progress =06
No Image
1 Model CHC Ladha
2 BHU Kanigurram
3 BHU Umar Raghzai
4 CHC Baloch
5 CHC Abdul Baqi
6 CHC Gulsa Khan
7 CD Karam
8 CD Dray Dakai
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 0 1.885 5.727 45% 18%
February - 2021
08- Units completed =02 In progress =06
No Image
1 Model CHC Ladha
2 BHU Kanigurram
3 BHU Umar Raghzai
4 CHC Baloch
5 CHC Abdul Baqi
6 CHC Gulsa Khan
7 CD Karam
8 CD Dray Dakai
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 10.404 1.885 2.792 2.792 2.792 2.792 4.677 5.727 45% 45%
January - 2021
08- Units completed =02 In progress =06
No Image
1 Model CHC Ladha
2 BHU Kanigurram
3 BHU Umar Raghzai
4 CHC Baloch
5 CHC Abdul Baqi
6 CHC Gulsa Khan
7 CD Karam
8 CD Dray Dakai
828
(OG)
191540-140250 - Solarization of 08 Existing Health Facilities in Close Area, SWA. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 10.196 7.404 2.792 0 0 0 7.404 0
July - 2020
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
01-08-15 - - 06-03-15 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
December - 2017
Leveling/dressing in progress. Cafetaria work started. Scheme frozen. Rev DCE submitted since 6 months, no decision.
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
- - - 06-03-15 - 82.464 80.926 50 50 0 0 80.926 0 100% 98%
September - 2017
Leveling/dressing in progress. Cafetaria work started. Revised DCE for Rs.199.964 m submitted.
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
- - - 06-03-15 - 82.464 80.926 50 50 0 0 80.926 0 100% 98%
August - 2017
Leveling/dressing in progress. Cafetaria work started. Revised DCE for Rs.199.964 m submitted.
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
- - - 06-03-15 - 82.464 80.926 50 50 0 0 80.926 0 100% 98%
July - 2017
Leveling/dressing in progress. Cafetaria work started. Revised DCE for Rs.199.964 m submitted.
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
November - 2017
Leveling/dressing in progress. Cafetaria work started. Revised DCE for Rs.199.964 m submitted.
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
October - 2017
Leveling/dressing in progress. Cafetaria work started. Revised DCE for Rs.199.964 m submitted.
No Image
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 0 0 80.926 0 100% 98%
June - 2018
Leveling/dressing in progress. Cafetaria plastering in progress. Admin block - BW in progress. Scheme frozen. Revised DCE submitted since 6 months, no decision.
No Image
Swabi
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
May - 2018
Leveling/dressing in progress. Cafetaria plastering in progress. Admin block - BW in progress. Scheme frozen. Revised DCE submitted since 6 months, no decision.
No Image
Swabi
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
April - 2018
Leveling/dressing in progress. Cafetaria plastering in progress. Admin block - BW in progress. Scheme frozen. Revised DCE submitted since 6 months, no decision.
No Image
Swabi
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
March - 2018
Leveling/dressing in progress. Cafetaria work started. Scheme frozen. Rev DCE submitted since 6 months, no decision.
No Image
Swabi
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
February - 2018
Leveling/dressing in progress. Cafetaria work started. Scheme frozen. Rev DCE submitted since 6 months, no decision.
No Image
Swabi
828
(OG)
130610-Construction of Public Park at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 82.464 80.926 50 50 25 0 80.926 0 100% 98%
January - 2018
Leveling/dressing in progress. Cafetaria work started. Scheme frozen. Rev DCE submitted since 6 months, no decision.
No Image
Pages : 1