Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2018, September - 2019, October - 2020, October - 2017, October - 2019, November - 2019, November - 2017, November - 2018, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
805
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 0.75 0.001 0.001 0.0005 0 0.75 334.552 0% 0%
September - 2018
Earth work in progress.
No Image
Battagram
805
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 0.75 0.001 0.001 0.0005 0 0.75 334.552 0% 0%
July - 2018
Work order issued.
No Image
Battagram
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
December - 2020
PC-II submitted to health. Pre PDWP held.
No Image
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
December - 2020
PC-II submitted to health. Pre PDWP held.
No Image
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
October - 2020
PC-II submitted to health. Pre PDWP held.
No Image
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
September - 2020
PC-II submitted to health. Pre PDWP held.
No Image
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
August - 2020
PC-II submitted to health. Pre PDWP held.
No Image
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 0 0 0 0 0 - -
July - 2020
PC-II submitted to health. Pre PDWP held.
No Image
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
May - 2021
PC-II submitted Aug 2021 to health. Pre PDWP held.
No Image
Medical College Dist: charssadda
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
April - 2021
PC-II submitted Aug 2021 to health. Pre PDWP held.
No Image
Medical College Dist: charssadda
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
March - 2021
PC-II submitted Aug 2021 to health. Pre PDWP held.
No Image
Medical College Dist: charssadda
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
February - 2021
PC-II submitted Aug 2021 to health. Pre PDWP held.
No Image
Medical College Dist: charssadda
805
(New)
190067-Establishment of Charsadda Medical College, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 1300 0 50 50 0 0 0 0 - -
January - 2021
PC-II submitted Aug 2021 to health. Pre PDWP held.
No Image
Medical College Dist: charssadda
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
10-03-16 - - 04-12-13 - 930.934 166.95 50 55 55 55 221.95 713.984 23% 24%
December - 2017
Main building - GF roof laid, block work in FF in progress. High court - roof laid, block work in progress. Lodges - FF BW in progress (Consultant AA Associates). Demand Rs.35 m.
No Image
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
10-03-16 - - 04-12-13 - 930.934 166.95 50 55 55 25.355 192.305 713.984 23% 21%
September - 2017
Main building - GF roof laid, block work in FF in progress. High court - roof laid, block work in progress. Lodges - FF BW in progress (Consultant AA Associates).
No Image
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
10-03-16 - - 04-12-13 - 930.934 166.95 50 50 25.355 25.355 192.305 713.984 23% 21%
August - 2017
Main building - SS in progess. Highcourt - roof laid. Lodges - DPC level, BW in progress (Consultant AA Associates).
No Image
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
10-03-16 - - 04-12-13 - 930.934 166.95 50 50 0 0 166.95 713.984 23% 18%
July - 2017
Main building - SS in progess. Highcourt - roof laid. Lodges - DPC level, BW in progress (Consultant AA Associates).
No Image
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 166.95 50 55 55 55 221.95 713.984 23% 24%
November - 2017
Main building - GF roof laid, block work in FF in progress. High court - roof laid, block work in progress. Lodges - FF BW in progress (Consultant AA Associates). Demand Rs.55 m.
No Image
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 166.95 50 55 55 26.6 193.55 713.984 23% 21%
October - 2017
Main building - GF roof laid, block work in FF in progress. High court - roof laid, block work in progress. Lodges - FF BW in progress (Consultant AA Associates).
No Image
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 126.45 50 65 65 65 191.45 754.484 19% 21%
June - 2018
Consultant AA Associates. Main building, high court, judicial lodge - foundation in progress.
No Image
Judicial Complex, Chitral.
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 126.45 50 55 55 55 181.45 754.484 19% 19%
May - 2018
(Consultant AA Associates) Main building + High Court + Judicial Lodge - Foundation in progress Staff Accom: + Judicial Lock - Work started BW in progress Demand Rs.55 m.
No Image
Judicial Complex, Chitral.
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 126.45 50 55 55 55 181.45 754.484 19% 19%
April - 2018
(Consultant AA Associates) Main building + High Court + Judicial Lodge - Foundation in progress Staff Accom: + Judicial Lock - Work started BW in progress Demand Rs.55 m.
No Image
Judicial Complex, Chitral.
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 126.45 50 55 55 55 181.45 754.484 19% 19%
March - 2018
(Consultant AA Associates) Main building + High Court + Judicial Lodge - Foundation in progress Staff Accom: + Judicial Lock - Work started BW in progress Demand Rs.55 m.
No Image
Judicial Complex, Chitral.
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 126.45 50 55 55 55 181.45 754.484 19% 19%
February - 2018
Main building - GF roof laid, block work in FF in progress. High court - roof laid, block work in progress. Lodges - FF BW in progress (Consultant AA Associates). Demand Rs.55 m.
No Image
Chitral
805
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 166.95 50 55 55 55 221.95 713.984 23% 24%
January - 2018
Main building - GF roof laid, block work in FF in progress. High court - roof laid, block work in progress. Lodges - FF BW in progress (Consultant AA Associates). Demand Rs.35 m.
No Image
Chitral
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.848 25.677 16.5069 179.8249 0 100% 90%
December - 2018
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road. Can be completed for Rs.36.682 m.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.848 16.5069 16.5069 179.8249 0 100% 90%
November - 2018
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road. Can be completed for Rs.36.682 m.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.848 16.5069 16.5069 179.8249 0 100% 90%
November - 2018
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road. Can be completed for Rs.36.682 m.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.8479 34.8479 34.847 198.165 0 100% 99%
April - 2019
Length 20 Km - 20 Km asphalt completed, shoulder in progress.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.8479 34.8479 30.262 193.58 0 100% 97%
March - 2019
Length 20 Km - 20 Km asphalt completed, shoulder in progress.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.8479 34.8479 30.262 193.58 0 100% 97%
March - 2019
Length 20 Km - 20 Km asphalt completed, shoulder in progress.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.8479 30.2624 25.677 188.995 0 100% 94%
February - 2019
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road.
No Image
805
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 163.318 36.682 34.848 25.677 25.677 188.995 0 100% 94%
January - 2019
Length 17 Km - 13 Km asphalt completed and only 3 Km premix remaining in balance portion of service road.
No Image
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 30 30 20 37 63.03 37% 37%
December - 2019
Length 6 Km - earth work 80% completed. Demand 20 M
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 20 20 20 37 63.03 37% 37%
November - 2019
Length 6 Km - earth work 80% completed.
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 20 20 20 37 63.03 37% 37%
October - 2019
Length 6 Km - earth work 80% completed.
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 20 5 5 22 63.03 37% 22%
September - 2019
Length 6 Km - earth work 80% completed.
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 20 5 0 17 63.03 37% 17%
August - 2019
Length 6 Km - earth work 80% completed.
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 30 30 30 47 63.03 37% 47%
May - 2020
Length 6 Km - earth work 80% completed. S/B 20 % completed. Demand 20 M
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 30 30 30 47 63.03 37% 47%
April - 2020
Length 6 Km - earth work 80% completed. S/B 20 % completed. Demand 20 M
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 30 30 30 47 63.03 37% 47%
March - 2020
Length 6 Km - earth work 80% completed. S/B 20 % completed. Demand 20 M
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 30 30 30 47 63.03 37% 47%
February - 2020
Length 6 Km - earth work 80% completed. S/B 20 % completed. Demand 20 M
No Image
Tordher District Swabi 6 Km
805
(OG)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 17 20 30 30 30 47 63.03 37% 47%
January - 2020
Length 6 Km - earth work 80% completed. S/B 20 % completed. Demand 20 M
No Image
Tordher District Swabi 6 Km
Pages : 1