Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 1.168 | 56.168 | 24.647 | 76% |
54% December - 2019 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 1 | 56 | 24.647 | 76% |
54% November - 2019 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 0 | 55 | 24.647 | 76% |
53% October - 2019 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 0 | 55 | 24.647 | 76% |
53% September - 2019 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 0 | 55 | 24.647 | 76% |
53% August - 2019 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 14.201 | 14.201 | 8.171 | 63.171 | 24.647 | 76% |
61% May - 2020 |
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 3.668 | 58.668 | 24.647 | 76% |
56% April - 2020 |
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 3.668 | 58.668 | 24.647 | 76% |
56% March - 2020 |
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 3.668 | 58.668 | 24.647 | 76% |
56% February - 2020 |
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 55 | 24.735 | 24.735 | 6.184 | 3.168 | 58.168 | 24.647 | 76% |
56% January - 2020 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- December - 2020 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- December - 2020 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- October - 2020 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- September - 2020 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- August - 2020 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
July - 2020 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- May - 2021 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- April - 2021 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- March - 2021 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- February - 2021 |
No Image | |
80 (OG) |
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.7 | 13.384 | 0 | 0 | 0 | 0 | 13.384 | 0 | - |
- January - 2021 |
No Image | |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
25-12-12 | 30-06-18 | - | 20-11-12 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 6.103 | 89.856 | 0 | 100% |
90% December - 2017 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 2.348 | 86.101 | 0 | 100% |
86% November - 2017 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 2.348 | 86.101 | 0 | 100% |
86% October - 2017 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
25-12-12 | 30-06-18 | - | 20-11-12 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 2.348 | 86.101 | 0 | 100% |
86% September - 2017 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
25-12-12 | 30-06-18 | - | 20-11-12 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 2.348 | 86.101 | 0 | 100% |
86% August - 2017 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
25-12-12 | 30-06-18 | - | 20-11-12 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 0 | 83.753 | 0 | 100% |
84% July - 2017 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 15.928 | 15.928 | 15.928 | 99.681 | 0 | 100% |
100% June - 2018 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
Islamabad (4 Nos Suits) | |||||||||||||||||||
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 19.2 | 14.4 | 98.153 | 0 | 100% |
98% May - 2018 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
Islamabad (4 Nos Suits) | |||||||||||||||||||
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 14.4 | 8.64 | 92.393 | 0 | 100% |
93% April - 2018 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
Islamabad (4 Nos Suits) | |||||||||||||||||||
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 14.4 | 8.64 | 92.393 | 0 | 100% |
93% March - 2018 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
Islamabad (4 Nos Suits) | |||||||||||||||||||
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 8.64 | 92.393 | 0 | 100% |
93% February - 2018 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
Islamabad (4 Nos Suits) | |||||||||||||||||||
80 (OG) |
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.695 | 83.753 | 19.2 | 19.2 | 8.64 | 6.103 | 89.856 | 0 | 100% |
90% January - 2018 |
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress. |
No Image |
4 Nos Suits | |||||||||||||||||||
80 (OG) |
120842-Establishment of Project Unit for PaRRSA/PDMA for USAID Projects in C&W Department. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 166.6 | 192.898 | 5 | 5 | 2.5 | 0 | 192.898 | 0 | 100% |
100% September - 2018 |
Work in progress. |
No Image |
80 (OG) |
120842-Establishment of Project Unit for PaRRSA/PDMA for USAID Projects in C&W Department. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 166.6 | 192.898 | 5 | 5 | 2.5 | 0 | 192.898 | 0 | 100% |
100% July - 2018 |
Work in progress. |
No Image |
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
Plan view drawing submitted to Principal Architect, CDO on 31/12/2018. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
DCE under preparation. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
DCE under preparation. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 5 | 5 | 0 | 0 | 0 | 61.604 | 8% |
- April - 2019 |
Tender under process. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-I/DCE submitted. DDWP held. AA Awaited. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-I/DCE submitted. DDWP held. AA Awaited. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
PC-I/DCE submitted to SE on 12/2/2019. |
No Image |
Tank | |||||||||||||||||||
80 (New) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 75 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
Plan view drawing submitted to Principal Architect, CDO on 31/12/2018. |
No Image |
Tank | |||||||||||||||||||
Pages : 1 |