Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, September - 2018, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 1.168 56.168 24.647 76% 54%
December - 2019
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 1 56 24.647 76% 54%
November - 2019
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 0 55 24.647 76% 53%
October - 2019
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 0 55 24.647 76% 53%
September - 2019
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 0 55 24.647 76% 53%
August - 2019
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 14.201 14.201 8.171 63.171 24.647 76% 61%
May - 2020
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 3.668 58.668 24.647 76% 56%
April - 2020
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 3.668 58.668 24.647 76% 56%
March - 2020
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 3.668 58.668 24.647 76% 56%
February - 2020
GF - roof laid, plastering in progress. FF - roofing in progress. Mosque - Roof Level
No Image
Battagram
80
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 55 24.735 24.735 6.184 3.168 58.168 24.647 76% 56%
January - 2020
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
December - 2020
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
December - 2020
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
October - 2020
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
September - 2020
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
August - 2020
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 -
July - 2020
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
May - 2021
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
April - 2021
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
March - 2021
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
February - 2021
No Image
80
(OG)
191061-180088 - Promotion of Broiler Farming through Establishment of Broiler Farms and Enhancement of Meat production (small ruminants) on public private partnership in District Orakzai. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 19.7 13.384 0 0 0 0 13.384 0 - -
January - 2021
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
25-12-12 30-06-18 - 20-11-12 - 99.695 83.753 19.2 19.2 8.64 6.103 89.856 0 100% 90%
December - 2017
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 8.64 2.348 86.101 0 100% 86%
November - 2017
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 8.64 2.348 86.101 0 100% 86%
October - 2017
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
25-12-12 30-06-18 - 20-11-12 - 99.695 83.753 19.2 19.2 8.64 2.348 86.101 0 100% 86%
September - 2017
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
25-12-12 30-06-18 - 20-11-12 - 99.695 83.753 19.2 19.2 8.64 2.348 86.101 0 100% 86%
August - 2017
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
25-12-12 30-06-18 - 20-11-12 - 99.695 83.753 19.2 19.2 8.64 0 83.753 0 100% 84%
July - 2017
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 15.928 15.928 15.928 99.681 0 100% 100%
June - 2018
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
Islamabad (4 Nos Suits)
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 19.2 14.4 98.153 0 100% 98%
May - 2018
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
Islamabad (4 Nos Suits)
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 14.4 8.64 92.393 0 100% 93%
April - 2018
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
Islamabad (4 Nos Suits)
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 14.4 8.64 92.393 0 100% 93%
March - 2018
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
Islamabad (4 Nos Suits)
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 8.64 8.64 92.393 0 100% 93%
February - 2018
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
Islamabad (4 Nos Suits)
80
(OG)
120351-Construction of Mosque and Conversion of basement in S-I and S-II Blocks to Staff Accommodation in KPK House, Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 99.695 83.753 19.2 19.2 8.64 6.103 89.856 0 100% 90%
January - 2018
Mosque, S-I, S-II basement - completed. Staff suits, information block - finishing in progress.
No Image
4 Nos Suits
80
(OG)
120842-Establishment of Project Unit for PaRRSA/PDMA for USAID Projects in C&W Department.
Provincial
30-11--1 30-11--1 - 30-11--1 - 166.6 192.898 5 5 2.5 0 192.898 0 100% 100%
September - 2018
Work in progress.
No Image
80
(OG)
120842-Establishment of Project Unit for PaRRSA/PDMA for USAID Projects in C&W Department.
Provincial
30-11--1 30-11--1 - 30-11--1 - 166.6 192.898 5 5 2.5 0 192.898 0 100% 100%
July - 2018
Work in progress.
No Image
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
December - 2018
Plan view drawing submitted to Principal Architect, CDO on 31/12/2018.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
November - 2018
DCE under preparation.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
November - 2018
DCE under preparation.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 0 5 5 0 0 0 61.604 8% -
April - 2019
Tender under process.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
March - 2019
PC-I/DCE submitted. DDWP held. AA Awaited.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
March - 2019
PC-I/DCE submitted. DDWP held. AA Awaited.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
February - 2019
PC-I/DCE submitted to SE on 12/2/2019.
No Image
Tank
80
(New)
180590-Construction of Bachelor Hostel for C&W Staff at Tank.
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 75 0 5 5 0 0 0 0 - -
January - 2019
Plan view drawing submitted to Principal Architect, CDO on 31/12/2018.
No Image
Tank
Pages : 1