799 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 62.694 | 20 | 20 | 20 | 10 | 72.694 | 117.306 | 41% |
36% September - 2018 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
799 (OG) |
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 62.694 | 20 | 20 | 10 | 0 | 62.694 | 117.306 | 41% |
31% July - 2018 |
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started. |
No Image |
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr) | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.528 | 49.442 | 35.356 | 174.907 | 0 | 100% |
85% December - 2018 |
Length 20 Km - 16 Km asphalt completed, on remaining base course, structure work in progress. Can be completed for Rs.89.354 m. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.528 | 35.356 | 10 | 149.551 | 0 | 100% |
73% November - 2018 |
Length 20 Km - 16 Km asphalt completed, on remaining base course, structure work in progress. Can be completed for Rs.89.354 m. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.528 | 35.356 | 10 | 149.551 | 0 | 100% |
73% November - 2018 |
Length 20 Km - 16 Km asphalt completed, on remaining base course, structure work in progress. Can be completed for Rs.89.354 m. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.5277 | 63.5277 | 60.355 | 199.906 | 0 | 100% |
97% April - 2019 |
Length 20 Km - 18 Km asphalt completed, on remaining base course, structure work in progress. Reveised PC-I/DCE for Rs.233.909 m submitted. Rs.29.833 m needed to complete. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.5277 | 63.5277 | 60.355 | 199.906 | 0 | 100% |
97% March - 2019 |
Length 20 Km - 18 Km asphalt completed, on remaining base course, structure work in progress. Reveised PC-I/DCE for Rs.233.909 m submitted. Rs.29.833 m needed to complete. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.5277 | 63.5277 | 60.355 | 199.906 | 0 | 100% |
97% March - 2019 |
Length 20 Km - 18 Km asphalt completed, on remaining base course, structure work in progress. Reveised PC-I/DCE for Rs.233.909 m submitted. Rs.29.833 m needed to complete. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.5277 | 63.5277 | 49.441 | 188.992 | 0 | 100% |
92% February - 2019 |
Length 20 Km - 16 Km asphalt completed, on remaining base course, structure work in progress. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 205.896 | 139.551 | 66.345 | 63.528 | 49.442 | 49.441 | 188.992 | 0 | 100% |
92% January - 2019 |
Length 20 Km - 16 Km asphalt completed, on remaining base course, structure work in progress. Can be completed for Rs.89.354 m. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
12-08-13 | - | - | 12-05-16 | - | 552.653 | 511.851 | 6.25 | 6.25 | 6.25 | 6.25 | 518.101 | 34.552 | 94% |
94% December - 2017 |
Completed. |
No Image |
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 6.25 | 6.25 | 6.25 | 6.25 | 518.101 | 34.552 | 94% |
94% November - 2017 |
Completed. |
No Image |
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 5 | 5 | 2 | 1.842 | 513.693 | 35.802 | 94% |
93% October - 2017 |
Completed. |
No Image |
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
12-08-13 | - | - | 12-05-16 | - | 552.653 | 511.851 | 5 | 5 | 2 | 1.591 | 513.442 | 35.802 | 94% |
93% September - 2017 |
Completed. |
No Image |
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
12-08-13 | - | - | 12-05-16 | - | 552.653 | 511.851 | 5 | 5 | 0 | 0 | 511.851 | 35.802 | 94% |
93% August - 2017 |
Completed. |
No Image |
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
12-08-13 | - | - | 12-05-16 | - | 552.653 | 511.851 | 5 | 5 | 0 | 0 | 511.851 | 35.802 | 94% |
93% July - 2017 |
HVAC completed. 4 generators installed and operational , fire fighting installled. 2 elevators installed. |
No Image |
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 7.5 | 7.5 | 7.5 | 7.5 | 519.351 | 33.302 | 94% |
94% June - 2018 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 7.5 | 7.5 | 7.5 | 7.5 | 519.351 | 33.302 | 94% |
94% May - 2018 |
Completed. Demand Rs.2 m for maintenance. |
No Image |
Peshawar | |||||||||||||||||||
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 7.5 | 7.5 | 7.5 | 7.5 | 519.351 | 33.302 | 94% |
94% April - 2018 |
Completed. Demand Rs.2 m for maintenance. |
No Image |
Peshawar | |||||||||||||||||||
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 7.5 | 7.5 | 7.5 | 7.5 | 519.351 | 33.302 | 94% |
94% March - 2018 |
Completed. Demand Rs. 2 M for Maintence |
No Image |
Peshawar | |||||||||||||||||||
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 7.5 | 7.5 | 7.5 | 7.5 | 519.351 | 33.302 | 94% |
94% February - 2018 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
799 (OG) |
120898-Replacement of AC Plant, Lifts and Installation of Heavy Duty Generator in Peshawar High Court, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 552.653 | 511.851 | 7.5 | 7.5 | 7.5 | 7.5 | 519.351 | 33.302 | 94% |
94% January - 2018 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 264.215 | 30 | 43 | 43 | 42.999285 | 307.214285 | 505.785 | 37% |
38% December - 2019 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Damand 100 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 |
December - 2020 |
Land paymnet made to DC Swabi Rs.170 M
DCSC for consultant selection held on 03/11/20.
Consultant Selected.
Palnning initated . Site Issues identifed in 136 Kanal Land Identifed (7 Kanal Dispute) |
No Image | |
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 |
December - 2020 |
Land paymnet made to DC Swabi Rs.170 M
DCSC for consultant selection held on 03/11/20.
Consultant Selected.
Palnning initated . Site Issues identifed in 136 Kanal Land Identifed (7 Kanal Dispute) |
No Image | |
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 550.296 | 264.215 | 30 | 38 | 38 | 37.672 | 301.887 | 256.081 | 53% |
55% November - 2019 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 550.296 | 264.215 | 30 | 38 | 38 | 38 | 302.215 | 256.081 | 53% |
55% October - 2019 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
Land paymnet made to DC Swabi Rs.170 M
DCSC for consultant selection held on 03/11/20 |
No Image |
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 550.296 | 264.215 | 30 | 30 | 7.5 | 7.5 | 271.715 | 256.081 | 53% |
49% September - 2019 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
Land paymnet made to DC Swabi Rs.170 M |
No Image |
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 550.296 | 264.215 | 30 | 30 | 7.5 | 0 | 264.215 | 256.081 | 53% |
48% August - 2019 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
Pc-II Submitted for design and supersvision for |
No Image |
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
Pc-II Submitted for design and supersvision for |
No Image |
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 264.215 | 30 | 43 | 43 | 43 | 307.215 | 505.785 | 37% |
38% May - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Damand 100 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
May - 2021 |
Land paymnet made to DC Swabi Rs.170 M
PC-I under preppartion by the Consultants |
No Image | |
Construction of Purpose Built Building for Gajju Khan Medical College Swabi | |||||||||||||||||||
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 264.215 | 30 | 43 | 43 | 43 | 307.215 | 505.785 | 37% |
38% April - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Damand 100 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
April - 2021 |
Land paymnet made to DC Swabi Rs.170 M
PC-I under preppartion by the Consultants |
No Image | |
Construction of Purpose Built Building for Gajju Khan Medical College Swabi | |||||||||||||||||||
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 264.215 | 30 | 43 | 43 | 43 | 307.215 | 505.785 | 37% |
38% March - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Damand 100 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 |
March - 2021 |
Land paymnet made to DC Swabi Rs.170 M
DCSC for consultant selection held on 03/11/20.
Consultant Selected.
Palnning initated . Site Issues identifed in 136 Kanal Land Identifed (7 Kanal Dispute) |
No Image | |
Construction of Purpose Built Building for Gajju Khan Medical College Swabi | |||||||||||||||||||
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 264.215 | 30 | 43 | 43 | 43 | 307.215 | 505.785 | 37% |
38% February - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Damand 100 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 |
February - 2021 |
Land paymnet made to DC Swabi Rs.170 M
DCSC for consultant selection held on 03/11/20.
Consultant Selected.
Palnning initated . Site Issues identifed in 136 Kanal Land Identifed (7 Kanal Dispute) |
No Image | |
Construction of Purpose Built Building for Gajju Khan Medical College Swabi | |||||||||||||||||||
799 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 264.215 | 30 | 43 | 43 | 43 | 307.215 | 505.785 | 37% |
38% January - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Damand 100 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 1 | 0 | 0 | 0 | 0 |
January - 2021 |
Land paymnet made to DC Swabi Rs.170 M
DCSC for consultant selection held on 03/11/20.
Consultant Selected.
Palnning initated . Site Issues identifed in 136 Kanal Land Identifed (7 Kanal Dispute) |
No Image | |
Construction of Purpose Built Building for Gajju Khan Medical College Swabi | |||||||||||||||||||