Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
- | - | - | - | Line Deptt | 250 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. Demarcation on new site awaited. Feasibility study will be redone. |
No Image |
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
- | - | - | - | Line Deptt | 250 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. |
No Image |
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
- | - | - | - | Line Deptt | 250 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. |
No Image |
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
- | - | - | - | Line Deptt | 250 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. |
No Image |
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. New site not yet demarcated. |
No Image |
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. New site not yet demarcated. |
No Image |
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 338.43 | 0 | 50 | 50 | 30.9 | 30.9 | 30.9 | 288.43 | 15% |
9% June - 2018 |
MAK consultant for Phase-I. Work order issued. Land payment made. |
No Image |
KDA, Kohat | |||||||||||||||||||
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 338.43 | 0 | 50 | 50 | 37.5 | 13.393 | 13.393 | 288.43 | 15% |
4% May - 2018 |
MAK consultant for Phase-I. Work order issued. Land payment made. |
No Image |
KDA, Kohat | |||||||||||||||||||
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 338.43 | 0 | 50 | 50 | 37.5 | 0 | 0 | 288.43 | 15% |
- April - 2018 |
MAK consultant for Phase-I. Technical bid received on 27/04/2018. |
No Image |
KDA, Kohat | |||||||||||||||||||
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 338.43 | 0 | 50 | 50 | 25 | 0 | 0 | 288.43 | 15% |
- March - 2018 |
(MAK consultant for Phase -I )
RFP Flaoted for Phase II. NiT invited. |
No Image |
KDA, Kohat | |||||||||||||||||||
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 350 | 0 | 50 | 50 | 25 | 0 | 0 | 300 | 14% |
- February - 2018 |
(MAK consultant ) Scheme approved in PDWP held on 8/3/2018. |
No Image |
KDA, Kohat | |||||||||||||||||||
797 (OG) |
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 50 | 50 | 25 | 0 | 0 | 0 | - |
- January - 2018 |
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. Demarcation on new site awaited. Feasibility study will be redone. |
No Image |
Kohat | |||||||||||||||||||
797 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 30 | 0 | 0 | 197.71 | 94.824 | 71% |
61% September - 2018 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
797 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 197.71 | 30 | 30 | 0 | 0 | 197.71 | 94.824 | 71% |
61% July - 2018 |
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 100 | 50 | 1.521 | 1303.507 | 463.014 | 75% |
70% December - 2020 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Nowshera | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 100 | 50 | 1.521 | 1303.507 | 463.014 | 75% |
70% December - 2020 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Nowshera | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 100 | 25 | 0 | 1301.986 | 463.014 | 75% |
70% October - 2020 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Nowshera | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 100 | 25 | 0 | 1301.986 | 463.014 | 75% |
70% September - 2020 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Nowshera | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 100 | 25 | 0 | 1301.986 | 463.014 | 75% |
70% August - 2020 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Nowshera | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 1401.987 | 100 | 0 | 0 | 0 | 1401.987 | 0 | 100% |
100% July - 2020 |
Main building (3 blocks) - Structure work complete |
No Image |
Nowshera | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2569.253 | 1301.986 | 100 | 578.189 | 578.189 | 96.4 | 1398.386 | 1167.267 | 55% |
54% May - 2021 |
01- Unit
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
Summary submitted fro Enhancement.
(Executed by FWO) |
No Image |
Establishment of Nowshera Medical College (Phase-I)
Scope of work:
| |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2569.253 | 1301.986 | 100 | 95 | 95 | 95 | 1396.986 | 1167.267 | 55% |
54% April - 2021 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
Summary submitted fro Enhancement.
(Executed by FWO) |
No Image |
Establishment of Nowshera Medical College (Phase-I) | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2569.253 | 1301.986 | 100 | 50 | 50 | 50 | 1351.986 | 1167.267 | 55% |
53% March - 2021 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Establishment of Nowshera Medical College (Phase-I) | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 50 | 50 | 50 | 1351.986 | 463.014 | 75% |
72% February - 2021 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Establishment of Nowshera Medical College (Phase-I) | |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1865 | 1301.986 | 100 | 50 | 50 | 2.923 | 1304.909 | 463.014 | 75% |
70% January - 2021 |
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. |
No Image |
Establishment of Nowshera Medical College (Phase-I) | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 9.501 | 4.5 | 72.05 | 79.764 | 49% |
46% December - 2018 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 4.501 | 4.5 | 72.05 | 79.764 | 49% |
46% November - 2018 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 4.501 | 4.5 | 72.05 | 79.764 | 49% |
46% November - 2018 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 9.5005 | 9.5 | 77.05 | 79.764 | 49% |
49% April - 2019 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. Work stopped due to non-abailability of fund. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 9.5005 | 9.5 | 77.05 | 79.764 | 49% |
49% March - 2019 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. Work stopped due to non-abailability of fund. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 9.5005 | 9.5 | 77.05 | 79.764 | 49% |
49% March - 2019 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. Work stopped due to non-abailability of fund. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 9.5005 | 9.5 | 77.05 | 79.764 | 49% |
49% February - 2019 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.314 | 67.55 | 10 | 9.5 | 9.501 | 9.5 | 77.05 | 79.764 | 49% |
49% January - 2019 |
Length 13 Km - 10 Km asphalt completed.
Court case/contractor liability of Rs.70 m. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 45.595 | 45.595 | 42.594162 | 209.147162 | 93.447 | 69% |
70% December - 2019 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. Can be completed. |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 42.595 | 42.595 | 42.595 | 209.148 | 93.447 | 69% |
70% November - 2019 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 42.595 | 42.595 | 42.595 | 209.148 | 93.447 | 69% |
70% October - 2019 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 40 | 10 | 10 | 176.553 | 93.447 | 69% |
59% September - 2019 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 40 | 10 | 0 | 166.553 | 93.447 | 69% |
56% August - 2019 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 45.595 | 45.595 | 45.595 | 212.148 | 93.447 | 69% |
71% May - 2020 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
P-II (Rs. 94 M ) |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 45.595 | 45.595 | 45.595 | 212.148 | 93.447 | 69% |
71% April - 2020 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
P-II (Rs. 94 M ) |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 45.595 | 45.595 | 45.595 | 212.148 | 93.447 | 69% |
71% March - 2020 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
P-II (Rs. 94 M ) |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 45.595 | 45.595 | 45.595 | 212.148 | 93.447 | 69% |
71% February - 2020 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
P-II (Rs. 94 M ) |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
797 (OG) |
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 166.553 | 40 | 45.595 | 45.595 | 42.594162 | 209.147162 | 93.447 | 69% |
70% January - 2020 |
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
P-II (Rs. 94 M ) |
No Image |
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km) | |||||||||||||||||||
Pages : 1 |