Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, September - 2018, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2019, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
- - - - Line Deptt 250 0 50 50 0 0 0 0 - -
December - 2017
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. Demarcation on new site awaited. Feasibility study will be redone.
No Image
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
- - - - Line Deptt 250 0 50 50 0 0 0 0 - -
September - 2017
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt.
No Image
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
- - - - Line Deptt 250 0 50 50 0 0 0 0 - -
August - 2017
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt.
No Image
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
- - - - Line Deptt 250 0 50 50 0 0 0 0 - -
July - 2017
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt.
No Image
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 250 0 50 50 0 0 0 0 - -
November - 2017
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. New site not yet demarcated.
No Image
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 250 0 50 50 0 0 0 0 - -
October - 2017
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. New site not yet demarcated.
No Image
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 338.43 0 50 50 30.9 30.9 30.9 288.43 15% 9%
June - 2018
MAK consultant for Phase-I. Work order issued. Land payment made.
No Image
KDA, Kohat
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 338.43 0 50 50 37.5 13.393 13.393 288.43 15% 4%
May - 2018
MAK consultant for Phase-I. Work order issued. Land payment made.
No Image
KDA, Kohat
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 338.43 0 50 50 37.5 0 0 288.43 15% -
April - 2018
MAK consultant for Phase-I. Technical bid received on 27/04/2018.
No Image
KDA, Kohat
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 338.43 0 50 50 25 0 0 288.43 15% -
March - 2018
(MAK consultant for Phase -I ) RFP Flaoted for Phase II. NiT invited.
No Image
KDA, Kohat
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 350 0 50 50 25 0 0 300 14% -
February - 2018
(MAK consultant ) Scheme approved in PDWP held on 8/3/2018.
No Image
KDA, Kohat
797
(OG)
160445-Reconstruction and Renovation of Judicial Complex Kohat (PC-II approved).
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 250 0 50 50 25 0 0 0 - -
January - 2018
PC-II approved for Rs.12.500 m. AA awaited. LOA issued to MAK ESA with SAAB Peshawar on 27/02/2017. PC-I for Rs.285.550 m submitted to client deptt. Site changed. Demarcation on new site awaited. Feasibility study will be redone.
No Image
Kohat
797
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 197.71 30 30 0 0 197.71 94.824 71% 61%
September - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
797
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 197.71 30 30 0 0 197.71 94.824 71% 61%
July - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 100 50 1.521 1303.507 463.014 75% 70%
December - 2020
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Nowshera
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 100 50 1.521 1303.507 463.014 75% 70%
December - 2020
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Nowshera
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 100 25 0 1301.986 463.014 75% 70%
October - 2020
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Nowshera
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 100 25 0 1301.986 463.014 75% 70%
September - 2020
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Nowshera
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 100 25 0 1301.986 463.014 75% 70%
August - 2020
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Nowshera
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1336.811 1401.987 100 0 0 0 1401.987 0 100% 100%
July - 2020
Main building (3 blocks) - Structure work complete
No Image
Nowshera
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 2569.253 1301.986 100 578.189 578.189 96.4 1398.386 1167.267 55% 54%
May - 2021
01- Unit Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. Summary submitted fro Enhancement. (Executed by FWO)
No Image
Establishment of Nowshera Medical College (Phase-I)
 
Scope of work:
  • College Nowshera
  • Main Building
  • Auditorium/ Gymnasium
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 2569.253 1301.986 100 95 95 95 1396.986 1167.267 55% 54%
April - 2021
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed. Summary submitted fro Enhancement. (Executed by FWO)
No Image
Establishment of Nowshera Medical College (Phase-I)
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 2569.253 1301.986 100 50 50 50 1351.986 1167.267 55% 53%
March - 2021
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Establishment of Nowshera Medical College (Phase-I)
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 50 50 50 1351.986 463.014 75% 72%
February - 2021
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Establishment of Nowshera Medical College (Phase-I)
797
(OG)
150522-Establishment of Nowshera Medical College (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 1865 1301.986 100 50 50 2.923 1304.909 463.014 75% 70%
January - 2021
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
No Image
Establishment of Nowshera Medical College (Phase-I)
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 9.501 4.5 72.05 79.764 49% 46%
December - 2018
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 4.501 4.5 72.05 79.764 49% 46%
November - 2018
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 4.501 4.5 72.05 79.764 49% 46%
November - 2018
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 9.5005 9.5 77.05 79.764 49% 49%
April - 2019
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m. Work stopped due to non-abailability of fund.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 9.5005 9.5 77.05 79.764 49% 49%
March - 2019
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m. Work stopped due to non-abailability of fund.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 9.5005 9.5 77.05 79.764 49% 49%
March - 2019
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m. Work stopped due to non-abailability of fund.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 9.5005 9.5 77.05 79.764 49% 49%
February - 2019
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 157.314 67.55 10 9.5 9.501 9.5 77.05 79.764 49% 49%
January - 2019
Length 13 Km - 10 Km asphalt completed. Court case/contractor liability of Rs.70 m.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 45.595 45.595 42.594162 209.147162 93.447 69% 70%
December - 2019
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. Can be completed.
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 42.595 42.595 42.595 209.148 93.447 69% 70%
November - 2019
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 42.595 42.595 42.595 209.148 93.447 69% 70%
October - 2019
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 40 10 10 176.553 93.447 69% 59%
September - 2019
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 40 10 0 166.553 93.447 69% 56%
August - 2019
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work.
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 45.595 45.595 45.595 212.148 93.447 69% 71%
May - 2020
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. P-II (Rs. 94 M )
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 45.595 45.595 45.595 212.148 93.447 69% 71%
April - 2020
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. P-II (Rs. 94 M )
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 45.595 45.595 45.595 212.148 93.447 69% 71%
March - 2020
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. P-II (Rs. 94 M )
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 45.595 45.595 45.595 212.148 93.447 69% 71%
February - 2020
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. P-II (Rs. 94 M )
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
797
(OG)
150851-Constn/BT of roads a)Karizi-Urmar Sadri,b)Palosai Khairabad,c)Rohani Bazargay,d)BakyanoKili-Kharif,e)Drangono,f)Mastilar,g)Sard China Tarkha,h)Artono,i)KhoroDulat,j)KhoroHaryan, k)Ghazikot-Dagai,l)Shahedan Bridge-Zardad Koty, m)Dr.HamidulHaq, Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 300 166.553 40 45.595 45.595 42.594162 209.147162 93.447 69% 70%
January - 2020
Length 8 Km - sub base, embankment, drain in progress. Rehabilitation nature work. P-II (Rs. 94 M )
No Image
1) Karizoo to Urmar Sadri road (3 Km)
2) Palosai Khair Abad road (2.50 Km)
3) Rohani Bazargi road (3.170 Km)
4) Construction of road from Bakyano Killi to Kharif Khan Killi UC Yaqoobi (2 Km)
5) Construction of Drangono road Yar Hussain UC Yar Hussain West (1.50 Km)
6) Construction of Masti Lar road Yar Hussain UC Yar Hussain West (0.843 Km)
7) Construction of Sard Cheena Tarkha road (1.50 Km) UC Sar Cheena
8) Construction of Aratoono road UC Yar Hussain Eat (1.50 Km)
9) Construction of Khoro Daulat road UC Daulat (1.62 Km)
10) Construction of Khoro Haryan road (2 Km) UC Dobian
11) Construction of Ghazi Kot Chowk to Dagai UC Yar Hussain East (1 Km)
12) Construction of road from Shaheedan Bridge to Zardad Kotte UC Yaqoobi (0.60 Km)
13) Construction of Dr.Hamid ul Haq road UC Dobian (1 Km)
Pages : 1