Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2019, January - 2020, January - 2021, February - 2018, February - 2019, February - 2020, February - 2021, March - 2018, March - 2019, March - 2020, March - 2021, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2018, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
11-06-05 30-06-18 - 08-01-14 - 258 167.925 82.575 82.575 50 33.791 201.716 7.5 97% 78%
December - 2017
Finishing in progress.
No Image
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
11-06-05 30-06-18 - 08-01-14 - 258 167.925 82.575 82.575 50 0 167.925 7.5 97% 65%
September - 2017
Finishing in progress.
No Image
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
11-06-05 30-06-18 - 08-01-14 - 258 167.925 82.575 82.575 50 0 167.925 7.5 97% 65%
August - 2017
Finishing in progress.
No Image
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
11-06-05 30-06-18 - 08-01-14 - 258 167.925 82.575 82.575 0 0 167.925 7.5 97% 65%
July - 2017
Finishing in progress.
No Image
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 82.575 50 33.79 201.715 7.5 97% 78%
November - 2017
Finishing in progress.
No Image
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 82.575 50 16.995 184.92 7.5 97% 72%
October - 2017
Finishing in progress.
No Image
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 86.366 86.366 81.395 249.32 7.5 97% 97%
June - 2018
Finishing in progress.
No Image
Bannu
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 106.366 106.366 81.395 249.32 7.5 97% 97%
May - 2018
Finishing in progress. Demand Rs.40 m.
No Image
Bannu
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 82.575 65.722 65.722 233.647 7.5 97% 91%
April - 2018
Finishing in progress. Demand Rs.40 m.
No Image
Bannu
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 82.575 61.931 35.404 203.329 7.5 97% 79%
March - 2018
Finishing in progress. Demand Rs.40 m.
No Image
Bannu
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 82.575 50 35.404 203.329 7.5 97% 79%
February - 2018
Finishing in progress.
ADP's Images
Bannu
795
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 167.925 82.575 82.575 50 50 217.925 7.5 97% 84%
January - 2018
Finishing in progress.
No Image
795
(OG)
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 550 314.057 0.001 0.001 0.0005 0 314.057 235.942 57% 57%
September - 2018
9/9 roads completed. 2/9 bridges completed. 6/9 bridges in progress. 1 retendering (Osiak) 5th time.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
795
(OG)
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 550 314.057 0.001 0.001 0.0005 0 314.057 235.942 57% 57%
July - 2018
9/9 roads completed. 2/9 bridges completed. 6/9 bridges in progress. 1 retendering (Osiak) 5th time.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.35 17.1 25 25 25 20.5 37.6 153.25 22% 19%
December - 2018
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work, WBM in progress. Bid of 2 bridges opening on 17/12/2018.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.35 17.1 25 25 25 12.5 29.6 153.25 22% 15%
November - 2018
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work in progress.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.35 17.1 25 25 25 12.5 29.6 153.25 22% 15%
November - 2018
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work in progress.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.07 17.1 25 25 25 25 42.1 152.97 22% 22%
April - 2019
Length 10.5 Km - 3 Km asphaltic base/wearing completed. Structure work, WBM in progress. 2 bridges - work order issued. Work stopped due to non-abailability of fund.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.07 17.1 25 25 25 25 42.1 152.97 22% 22%
March - 2019
Length 10.5 Km - 3 Km asphaltic base/wearing completed. Structure work, WBM in progress. 2 bridges - work order issued. Work stopped due to non-abailability of fund.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.07 17.1 25 25 25 25 42.1 152.97 22% 22%
March - 2019
Length 10.5 Km - 3 Km asphaltic base/wearing completed. Structure work, WBM in progress. 2 bridges - work order issued. Work stopped due to non-abailability of fund.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.07 17.1 25 25 25 25 42.1 152.97 22% 22%
February - 2019
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work, WBM in progress. Bid of 2 bridges opening on 17/12/2018.
No Image
Peshawar
795
(OG)
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 195.07 17.1 25 25 25 25 42.1 152.97 22% 22%
January - 2019
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work, WBM in progress. Bid of 2 bridges opening on 17/12/2018.
No Image
Peshawar
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
MPD-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.926 40 123 123 123 484.926 178.508 69% 84%
May - 2021
Girls Hostel completed Block A & B Completed Tube well over head tank completed VRF const: work started Demand Rs: ?
No Image
Scope of work:
  • Block-I
  • Basement + Gournd + 3rd Floor
  • Block-II
  • Basement + Ground + 5th Floor
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
MPD-2
30-11--1 30-11--1 - 30-11--1 - 580.434 0 40 123 123 123 0 0
April - 2021
Girls Hostel completed Block A & B Completed Tube well over head tank completed VRF const: work started Demand Rs: ?
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 40 40 40 401.925 178.509 69% 69%
December - 2020
Main building Civil work in completed & occupied. Installation of VRF in progress. P-II : Can be complted provided balance funds relresed Revised TS submitted
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 40 40 40 401.925 178.509 69% 69%
December - 2020
Main building Civil work in completed & occupied. Installation of VRF in progress. P-II : Can be complted provided balance funds relresed Revised TS submitted
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 40 10 10 371.925 178.509 69% 64%
October - 2020
Main building Civil work in completed & occupied. Installation of VRF in progress. P-II : Can be complted provided balance funds relresed
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 40 10 10 371.925 178.509 69% 64%
September - 2020
Main building Civil work in completed. Installation of VRF in progress. P-II : Can be complted provided balance funds relresed
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 40 10 0 361.925 178.509 69% 62%
August - 2020
Main building Civil work in completed. Installation of VRF in progress.
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 0 0 0 361.925 178.509 69% 62%
July - 2020
Main building Civil work in completed. Installation of VRF in progress.
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 0 40 90 90 90 0 0
March - 2021
Girls Hostel completed Block A & B Completed Tube well over head tank completed VRF const: work started
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 0 40 90 90 90 0 0
February - 2021
Girls Hostel completed Block A & B Completed Tube well over head tank completed VRF const: work started
No Image
Peshawar
 
795
(OG)
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 580.434 361.925 40 40 40 40 401.925 178.509 69% 69%
January - 2021
Main building Civil work in completed & occupied. Installation of VRF in progress. Demand Rs: 50 M P-II : Can be complted provided balance funds relresed Revised TS submitted
No Image
Peshawar
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 11.63663 11.63663 0 331.321 0 100% 96%
December - 2019
Length 12 Km - 12 Km asphalt completed, structure work in progress. Drain in the bazar (revised scope) disputed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 12.429 3.107 0 331.321 0 100% 96%
November - 2019
Length 12 Km - 12 Km asphalt completed, structure work in progress. Cannot be completed - Drain in the bazar (revised scope) disputed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 12.429 3.107 0 331.321 0 100% 96%
October - 2019
Length 12 Km - 12 Km asphalt completed, structure work in progress. Cannot be completed - Drain in the bazar (revised scope) disputed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 12.429 3.107 3.107 334.428 0 100% 97%
September - 2019
Length 12 Km - 12 Km asphalt completed, structure work in progress.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 12.429 3.107 0 331.321 0 100% 96%
August - 2019
Length 12 Km - 12 Km asphalt completed, structure work in progress.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 11.63663 11.637 11.637 342.958 0 100% 100%
May - 2020
Length 12 Km - 12 Km asphalt completed, structure work in progress. Drain in the bazar (revised scope) disputed. Can be completed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 11.63663 11.637 11.637 342.958 0 100% 100%
April - 2020
Length 12 Km - 12 Km asphalt completed, structure work in progress. Drain in the bazar (revised scope) disputed. Can be completed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 11.63663 11.637 11.637 342.958 0 100% 100%
March - 2020
Length 12 Km - 12 Km asphalt completed, structure work in progress. Drain in the bazar (revised scope) disputed. Can be completed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 11.63663 11.637 11.637 342.958 0 100% 100%
February - 2020
Length 12 Km - 12 Km asphalt completed, structure work in progress. Drain in the bazar (revised scope) disputed. Can be completed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
795
(OG)
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM).
Swabi
30-11--1 30-11--1 - 30-11--1 - 343.75 331.321 12.429 11.63663 11.637 11.637 342.958 0 100% 100%
January - 2020
Length 12 Km - 12 Km asphalt completed, structure work in progress. Drain in the bazar (revised scope) disputed. Can be completed.
No Image
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
 
Pages : 1