Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
11-06-05 | 30-06-18 | - | 08-01-14 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 33.791 | 201.716 | 7.5 | 97% |
78% December - 2017 |
Finishing in progress. |
No Image |
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
11-06-05 | 30-06-18 | - | 08-01-14 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 0 | 167.925 | 7.5 | 97% |
65% September - 2017 |
Finishing in progress. |
No Image |
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
11-06-05 | 30-06-18 | - | 08-01-14 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 0 | 167.925 | 7.5 | 97% |
65% August - 2017 |
Finishing in progress. |
No Image |
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
11-06-05 | 30-06-18 | - | 08-01-14 | - | 258 | 167.925 | 82.575 | 82.575 | 0 | 0 | 167.925 | 7.5 | 97% |
65% July - 2017 |
Finishing in progress. |
No Image |
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 33.79 | 201.715 | 7.5 | 97% |
78% November - 2017 |
Finishing in progress. |
No Image |
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 16.995 | 184.92 | 7.5 | 97% |
72% October - 2017 |
Finishing in progress. |
No Image |
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 86.366 | 86.366 | 81.395 | 249.32 | 7.5 | 97% |
97% June - 2018 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 106.366 | 106.366 | 81.395 | 249.32 | 7.5 | 97% |
97% May - 2018 |
Finishing in progress. Demand Rs.40 m. |
No Image |
Bannu | |||||||||||||||||||
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 82.575 | 65.722 | 65.722 | 233.647 | 7.5 | 97% |
91% April - 2018 |
Finishing in progress. Demand Rs.40 m. |
No Image |
Bannu | |||||||||||||||||||
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 82.575 | 61.931 | 35.404 | 203.329 | 7.5 | 97% |
79% March - 2018 |
Finishing in progress. Demand Rs.40 m. |
No Image |
Bannu | |||||||||||||||||||
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 35.404 | 203.329 | 7.5 | 97% |
79% February - 2018 |
Finishing in progress. |
ADP's Images |
Bannu | |||||||||||||||||||
795 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 167.925 | 82.575 | 82.575 | 50 | 50 | 217.925 | 7.5 | 97% |
84% January - 2018 |
Finishing in progress. |
No Image |
795 (OG) |
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 550 | 314.057 | 0.001 | 0.001 | 0.0005 | 0 | 314.057 | 235.942 | 57% |
57% September - 2018 |
9/9 roads completed. 2/9 bridges completed. 6/9 bridges in progress. 1 retendering (Osiak) 5th time. |
No Image |
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni | |||||||||||||||||||
795 (OG) |
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 550 | 314.057 | 0.001 | 0.001 | 0.0005 | 0 | 314.057 | 235.942 | 57% |
57% July - 2018 |
9/9 roads completed. 2/9 bridges completed. 6/9 bridges in progress. 1 retendering (Osiak) 5th time. |
No Image |
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.35 | 17.1 | 25 | 25 | 25 | 20.5 | 37.6 | 153.25 | 22% |
19% December - 2018 |
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work, WBM in progress. Bid of 2 bridges opening on 17/12/2018. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.35 | 17.1 | 25 | 25 | 25 | 12.5 | 29.6 | 153.25 | 22% |
15% November - 2018 |
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work in progress. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.35 | 17.1 | 25 | 25 | 25 | 12.5 | 29.6 | 153.25 | 22% |
15% November - 2018 |
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work in progress. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 17.1 | 25 | 25 | 25 | 25 | 42.1 | 152.97 | 22% |
22% April - 2019 |
Length 10.5 Km - 3 Km asphaltic base/wearing completed. Structure work, WBM in progress. 2 bridges - work order issued. Work stopped due to non-abailability of fund. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 17.1 | 25 | 25 | 25 | 25 | 42.1 | 152.97 | 22% |
22% March - 2019 |
Length 10.5 Km - 3 Km asphaltic base/wearing completed. Structure work, WBM in progress. 2 bridges - work order issued. Work stopped due to non-abailability of fund. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 17.1 | 25 | 25 | 25 | 25 | 42.1 | 152.97 | 22% |
22% March - 2019 |
Length 10.5 Km - 3 Km asphaltic base/wearing completed. Structure work, WBM in progress. 2 bridges - work order issued. Work stopped due to non-abailability of fund. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 17.1 | 25 | 25 | 25 | 25 | 42.1 | 152.97 | 22% |
22% February - 2019 |
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work, WBM in progress. Bid of 2 bridges opening on 17/12/2018. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 17.1 | 25 | 25 | 25 | 25 | 42.1 | 152.97 | 22% |
22% January - 2019 |
Length 10.5 Km - 2 Km asphalt wearing completed. Structure work, WBM in progress. Bid of 2 bridges opening on 17/12/2018. |
No Image |
Peshawar | |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.926 | 40 | 123 | 123 | 123 | 484.926 | 178.508 | 69% |
84% May - 2021 |
Girls Hostel completed
Block A & B Completed
Tube well over head tank completed
VRF const: work started
Demand Rs: ? |
No Image |
Scope of work:
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 0 | 40 | 123 | 123 | 123 | 0 | 0 |
April - 2021 |
Girls Hostel completed
Block A & B Completed
Tube well over head tank completed
VRF const: work started
Demand Rs: ? |
No Image | |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 40 | 40 | 40 | 401.925 | 178.509 | 69% |
69% December - 2020 |
Main building Civil work in completed & occupied.
Installation of VRF in progress.
P-II : Can be complted provided balance funds relresed
Revised TS submitted |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 40 | 40 | 40 | 401.925 | 178.509 | 69% |
69% December - 2020 |
Main building Civil work in completed & occupied.
Installation of VRF in progress.
P-II : Can be complted provided balance funds relresed
Revised TS submitted |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 40 | 10 | 10 | 371.925 | 178.509 | 69% |
64% October - 2020 |
Main building Civil work in completed & occupied.
Installation of VRF in progress.
P-II : Can be complted provided balance funds relresed |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 40 | 10 | 10 | 371.925 | 178.509 | 69% |
64% September - 2020 |
Main building Civil work in completed.
Installation of VRF in progress.
P-II : Can be complted provided balance funds relresed |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 40 | 10 | 0 | 361.925 | 178.509 | 69% |
62% August - 2020 |
Main building Civil work in completed.
Installation of VRF in progress. |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 0 | 0 | 0 | 361.925 | 178.509 | 69% |
62% July - 2020 |
Main building Civil work in completed.
Installation of VRF in progress. |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 0 | 40 | 90 | 90 | 90 | 0 | 0 |
March - 2021 |
Girls Hostel completed
Block A & B Completed
Tube well over head tank completed
VRF const: work started |
No Image | |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 0 | 40 | 90 | 90 | 90 | 0 | 0 |
February - 2021 |
Girls Hostel completed
Block A & B Completed
Tube well over head tank completed
VRF const: work started |
No Image | |
Peshawar
| |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.925 | 40 | 40 | 40 | 40 | 401.925 | 178.509 | 69% |
69% January - 2021 |
Main building Civil work in completed & occupied.
Installation of VRF in progress.
Demand Rs: 50 M
P-II : Can be complted provided balance funds relresed
Revised TS submitted |
No Image |
Peshawar
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 11.63663 | 11.63663 | 0 | 331.321 | 0 | 100% |
96% December - 2019 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Drain in the bazar (revised scope) disputed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 12.429 | 3.107 | 0 | 331.321 | 0 | 100% |
96% November - 2019 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Cannot be completed - Drain in the bazar (revised scope) disputed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 12.429 | 3.107 | 0 | 331.321 | 0 | 100% |
96% October - 2019 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Cannot be completed - Drain in the bazar (revised scope) disputed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 12.429 | 3.107 | 3.107 | 334.428 | 0 | 100% |
97% September - 2019 |
Length 12 Km - 12 Km asphalt completed, structure work in progress. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 12.429 | 3.107 | 0 | 331.321 | 0 | 100% |
96% August - 2019 |
Length 12 Km - 12 Km asphalt completed, structure work in progress. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 11.63663 | 11.637 | 11.637 | 342.958 | 0 | 100% |
100% May - 2020 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Drain in the bazar (revised scope) disputed.
Can be completed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 11.63663 | 11.637 | 11.637 | 342.958 | 0 | 100% |
100% April - 2020 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Drain in the bazar (revised scope) disputed.
Can be completed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 11.63663 | 11.637 | 11.637 | 342.958 | 0 | 100% |
100% March - 2020 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Drain in the bazar (revised scope) disputed.
Can be completed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 11.63663 | 11.637 | 11.637 | 342.958 | 0 | 100% |
100% February - 2020 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Drain in the bazar (revised scope) disputed.
Can be completed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
795 (OG) |
141002-F/S, Design and Construction/Rehabilitation of Roads and street pavements a) Kunda Topi b) Gar Mergoz c) Zarobi Topi, d) Zaida Kaddi, e) Marghuz Yousafi Swabi. (21 KM). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 343.75 | 331.321 | 12.429 | 11.63663 | 11.637 | 11.637 | 342.958 | 0 | 100% |
100% January - 2020 |
Length 12 Km - 12 Km asphalt completed, structure work in progress.
Drain in the bazar (revised scope) disputed.
Can be completed. |
No Image |
1) Kunda Topi Road length 12 km width 24 ft
2) Zaroobi Topi road 2 Km width 18 ft
3) Zaida Kaddi road 4 Km width 18ft
4) Marghuz Yousafai road 3 Km width 18ft
| |||||||||||||||||||
Pages : 1 |