Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2019, March - 2020, March - 2021, March - 2018, April - 2019, April - 2020, April - 2021, April - 2018, May - 2018, May - 2020, May - 2021, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2018, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
22-03-13 - - 29-11-12 - 839.897 481.644 210.8 210.8 100 76.44 558.084 147.453 82% 66%
December - 2017
Main building, residences - finishing in progress.
No Image
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
22-03-13 - - 29-11-12 - 839.897 481.644 210.8 210.8 100 6.176 487.82 147.453 82% 58%
September - 2017
Main building, residences - finishing in progress.
No Image
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
22-03-13 - - 29-11-12 - 839.897 481.644 210.8 210.8 100 0 481.644 147.453 82% 57%
August - 2017
Main building, residences - finishing in progress.
No Image
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
22-03-13 - - 29-11-12 - 839.897 481.644 210.8 210.8 0 0 481.644 147.453 82% 57%
July - 2017
Main building, residences - finishing in progress.
No Image
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 839.897 481.644 210.8 210.8 100 75.432 557.076 147.453 82% 66%
November - 2017
Main building, residences - finishing in progress.
No Image
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 839.897 481.644 210.8 210.8 100 6.285 487.929 147.453 82% 58%
October - 2017
Main building, residences - finishing in progress.
No Image
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 481.644 210.8 151.64 151.64 129.598 611.242 257.556 73% 64%
June - 2018
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 481.644 210.8 210.8 171.642 128.716 610.36 257.556 73% 64%
May - 2018
Main building, residences - finishing in progress. Demand Rs.50 m.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 481.644 210.8 210.8 125.6 125.6 607.244 257.556 73% 64%
April - 2018
Main building, residences - finishing in progress. Demand Rs.50 m.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 481.644 210.8 210.8 105.6 104.819 586.463 257.556 73% 62%
March - 2018
Main building, residences - finishing in progress. Demand Rs.50 m.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 481.644 210.8 210.8 83 83 564.644 257.556 73% 59%
February - 2018
Main building, residences - finishing in progress.
ADP's Images
1) Additional works
2) VRF (Variable Regregitor Flow)
794
(OG)
120003-Construction of Peshawar High Court Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 839.897 481.644 210.8 210.8 83 83 564.644 147.453 82% 67%
January - 2018
Main building, residences - finishing in progress.
No Image
794
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 423.106 82.95 20 11.877 1.877 1.877 84.827 320.156 24% 20%
September - 2018
3 units: S# 1: Finishing in progress S# 2 # 3: Cutting in progress
No Image
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads
794
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 423.106 82.95 20 20 10 0 82.95 320.156 24% 20%
July - 2018
3 units: S# 1: Finishing in progress S# 2 # 3: Cutting in progress
No Image
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 4.5005 0 1.221 172.901 6% 1%
December - 2018
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 4.501 0 1.221 172.901 6% 1%
November - 2018
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 4.501 0 1.221 172.901 6% 1%
November - 2018
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 9.5 7 8.221 172.901 6% 4%
April - 2019
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 7.0005 4.508 5.729 172.901 6% 3%
March - 2019
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 7.0005 4.508 5.729 172.901 6% 3%
March - 2019
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 7.0005 4.5005 5.7215 172.901 6% 3%
February - 2019
Earth work, structure in progress.
No Image
Hangu
794
(OG)
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 1.221 10 9.5 4.5005 4.501 5.722 172.901 6% 3%
January - 2019
Earth work, structure in progress.
No Image
Hangu
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 155.85 1507.612 645.238 71% 69%
December - 2020
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 155.85 1507.612 645.238 71% 69%
December - 2020
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 57.653 1409.415 645.238 71% 64%
October - 2020
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 50 50 1401.762 645.238 71% 64%
September - 2020
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 50 0 1351.762 645.238 71% 62%
August - 2020
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 0 0 0 1351.762 645.238 71% 62%
July - 2020
Pack-1 - BB work in progress. Pack-2 - SS roof sla
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 199.999 1551.761 645.238 71% 71%
May - 2021
03- Packages Pac - 1: Basement, G+3 Strcutre competed, G/Floor 50%, BB Work Completed & Flooring 60% Completed, F/F 50%, BB work Completed & Flooring 60% Completed 2nd Floor: 50% BB work completed & Flooring 60% completed 3rd Floor BB work completed & Flooring 60% Completed Pac - 2 : Basement Slab Completed, P. Beam Completed, G.F Roof Slab laid, BB Work & Flooring Completed 1st Floor Laid BB & Flooring Completed 2nd Floor BB work & Flooring Completed 3rd Floor Completed 4th Floor BB work completed Pac - 3 : C/Wall 90% Completed Girls Hostel G+5 roof slab completed and BB work is 100% completed, Flooring Completed watch Tower 2/4 Completed drain completed Common Facility Block: G/F Plaster in Progress, F/F BB work in progress, 2nd Floor roof laid, 3rd floor roof laid 4th Floor steel work in progress
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 199.999 1551.761 645.238 71% 71%
April - 2021
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 199.999 1551.761 645.238 71% 71%
March - 2021
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 199.999 1551.761 645.238 71% 71%
February - 2021
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
130618-Establishment of Kohat Institute of Medical Sciences (KIMS)
Kohat
30-11--1 30-11--1 - 30-11--1 - 2197 1351.762 200 200 200 173.664 1525.426 645.238 71% 69%
January - 2021
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress. Dental block Pack-2 G+4 Structure completed & flooring in progress Base slab completed. Ist Floor roof laid. 2nd Floor 100 slab completed. 3rd floor 100%completed. Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed.
No Image
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
December - 2019
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
November - 2019
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
October - 2019
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress. P-II
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 5 5 132.866 32.134 82% 74%
September - 2019
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 5 5 132.866 32.134 82% 74%
August - 2019
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
May - 2020
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
April - 2020
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
March - 2020
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
February - 2020
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
794
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 180 127.866 20 20 20 20 147.866 32.134 82% 82%
January - 2020
11- Km completed. 3.25 Km 70% completed.
No Image
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft)
Pages : 1