Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
22-03-13 | - | - | 29-11-12 | - | 839.897 | 481.644 | 210.8 | 210.8 | 100 | 76.44 | 558.084 | 147.453 | 82% |
66% December - 2017 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
22-03-13 | - | - | 29-11-12 | - | 839.897 | 481.644 | 210.8 | 210.8 | 100 | 6.176 | 487.82 | 147.453 | 82% |
58% September - 2017 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
22-03-13 | - | - | 29-11-12 | - | 839.897 | 481.644 | 210.8 | 210.8 | 100 | 0 | 481.644 | 147.453 | 82% |
57% August - 2017 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
22-03-13 | - | - | 29-11-12 | - | 839.897 | 481.644 | 210.8 | 210.8 | 0 | 0 | 481.644 | 147.453 | 82% |
57% July - 2017 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 839.897 | 481.644 | 210.8 | 210.8 | 100 | 75.432 | 557.076 | 147.453 | 82% |
66% November - 2017 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 839.897 | 481.644 | 210.8 | 210.8 | 100 | 6.285 | 487.929 | 147.453 | 82% |
58% October - 2017 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 950 | 481.644 | 210.8 | 151.64 | 151.64 | 129.598 | 611.242 | 257.556 | 73% |
64% June - 2018 |
Main building, residences - finishing in progress. |
No Image |
1) Additional works
2) VRF (Variable Regregitor Flow) | |||||||||||||||||||
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 950 | 481.644 | 210.8 | 210.8 | 171.642 | 128.716 | 610.36 | 257.556 | 73% |
64% May - 2018 |
Main building, residences - finishing in progress. Demand Rs.50 m. |
No Image |
1) Additional works
2) VRF (Variable Regregitor Flow) | |||||||||||||||||||
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 950 | 481.644 | 210.8 | 210.8 | 125.6 | 125.6 | 607.244 | 257.556 | 73% |
64% April - 2018 |
Main building, residences - finishing in progress. Demand Rs.50 m. |
No Image |
1) Additional works
2) VRF (Variable Regregitor Flow) | |||||||||||||||||||
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 950 | 481.644 | 210.8 | 210.8 | 105.6 | 104.819 | 586.463 | 257.556 | 73% |
62% March - 2018 |
Main building, residences - finishing in progress. Demand Rs.50 m. |
No Image |
1) Additional works
2) VRF (Variable Regregitor Flow) | |||||||||||||||||||
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 950 | 481.644 | 210.8 | 210.8 | 83 | 83 | 564.644 | 257.556 | 73% |
59% February - 2018 |
Main building, residences - finishing in progress. |
ADP's Images |
1) Additional works
2) VRF (Variable Regregitor Flow) | |||||||||||||||||||
794 (OG) |
120003-Construction of Peshawar High Court Bannu Bench. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 839.897 | 481.644 | 210.8 | 210.8 | 83 | 83 | 564.644 | 147.453 | 82% |
67% January - 2018 |
Main building, residences - finishing in progress. |
No Image |
794 (OG) |
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 82.95 | 20 | 11.877 | 1.877 | 1.877 | 84.827 | 320.156 | 24% |
20% September - 2018 |
3 units:
S# 1: Finishing in progress
S# 2 # 3: Cutting in progress |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
794 (OG) |
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 82.95 | 20 | 20 | 10 | 0 | 82.95 | 320.156 | 24% |
20% July - 2018 |
3 units:
S# 1: Finishing in progress
S# 2 # 3: Cutting in progress |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 4.5005 | 0 | 1.221 | 172.901 | 6% |
1% December - 2018 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 4.501 | 0 | 1.221 | 172.901 | 6% |
1% November - 2018 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 4.501 | 0 | 1.221 | 172.901 | 6% |
1% November - 2018 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 9.5 | 7 | 8.221 | 172.901 | 6% |
4% April - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 7.0005 | 4.508 | 5.729 | 172.901 | 6% |
3% March - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 7.0005 | 4.508 | 5.729 | 172.901 | 6% |
3% March - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 7.0005 | 4.5005 | 5.7215 | 172.901 | 6% |
3% February - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
170578-F/S, Design & Construction / Improvement of Hangu Samana Main Road (7 Km) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 1.221 | 10 | 9.5 | 4.5005 | 4.501 | 5.722 | 172.901 | 6% |
3% January - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 155.85 | 1507.612 | 645.238 | 71% |
69% December - 2020 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 155.85 | 1507.612 | 645.238 | 71% |
69% December - 2020 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 57.653 | 1409.415 | 645.238 | 71% |
64% October - 2020 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 50 | 50 | 1401.762 | 645.238 | 71% |
64% September - 2020 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 50 | 0 | 1351.762 | 645.238 | 71% |
62% August - 2020 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 0 | 0 | 0 | 1351.762 | 645.238 | 71% |
62% July - 2020 |
Pack-1 - BB work in progress. Pack-2 - SS roof sla |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 199.999 | 1551.761 | 645.238 | 71% |
71% May - 2021 |
03- Packages
Pac - 1:
Basement, G+3 Strcutre competed, G/Floor 50%, BB Work Completed & Flooring 60% Completed, F/F 50%, BB work Completed & Flooring 60% Completed
2nd Floor: 50% BB work completed & Flooring 60% completed
3rd Floor BB work completed & Flooring 60% Completed
Pac - 2 :
Basement Slab Completed, P. Beam Completed, G.F Roof Slab laid, BB Work & Flooring Completed
1st Floor Laid BB & Flooring Completed
2nd Floor BB work & Flooring Completed
3rd Floor Completed
4th Floor BB work completed
Pac - 3 :
C/Wall 90% Completed
Girls Hostel G+5 roof slab completed and BB work is 100% completed, Flooring Completed watch Tower 2/4 Completed drain completed
Common Facility Block: G/F Plaster in Progress, F/F BB work in progress, 2nd Floor roof laid, 3rd floor roof laid
4th Floor steel work in progress |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 199.999 | 1551.761 | 645.238 | 71% |
71% April - 2021 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 199.999 | 1551.761 | 645.238 | 71% |
71% March - 2021 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 199.999 | 1551.761 | 645.238 | 71% |
71% February - 2021 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 173.664 | 1525.426 | 645.238 | 71% |
69% January - 2021 |
Pack-1 - G+4 Slab pad BB work completed. 2/4 story flooring completed. Joinery in progress.
Dental block Pack-2
G+4 Structure completed & flooring in progress Base slab completed.
Ist Floor roof laid.
2nd Floor 100 slab completed.
3rd floor 100%completed.
Package-III, C/Wall 90% completed. Girls Hostel G+5 roof slab, BB work completed. |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% December - 2019 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% November - 2019 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% October - 2019 |
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress.
P-II |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 5 | 5 | 132.866 | 32.134 | 82% |
74% September - 2019 |
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 5 | 5 | 132.866 | 32.134 | 82% |
74% August - 2019 |
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% May - 2020 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% April - 2020 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% March - 2020 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% February - 2020 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
794 (OG) |
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park- Alla Dher Road, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180 | 127.866 | 20 | 20 | 20 | 20 | 147.866 | 32.134 | 82% |
82% January - 2020 |
11- Km completed.
3.25 Km 70% completed. |
No Image |
1) Tordher Alladher road (width 18 ft)
2) Nawan Nehar Kund Park Alladher Road (width 18 ft) | |||||||||||||||||||
Pages : 1 |