Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2019, February - 2020, February - 2021, February - 2019, March - 2020, March - 2021, March - 2019, April - 2020, April - 2021, April - 2019, May - 2020, May - 2021, July - 2020, July - 2018, August - 2020, August - 2019, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2019, November - 2018, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
791
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
30-11--1 30-11--1 - 30-11--1 - 115.656 34.988 0 0 0 0 34.988 80.668 - 30%
September - 2018
RCC bridge (1 span) in progress, 2 Km road work in progress.
No Image
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition)
791
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
30-11--1 30-11--1 - 30-11--1 - 115.656 34.988 0 0 0 0 34.988 80.668 - 30%
July - 2018
RCC bridge (1 span) in progress, 2 Km road work in progress
No Image
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition)
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 56.58 21.908 2553.421 0 100% 100%
December - 2020
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 56.58 21.908 2553.421 0 100% 100%
December - 2020
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 28 12.21 2543.723 0 100% 100%
October - 2020
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 28 12.21 2543.723 0 100% 100%
September - 2020
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 0 0 0 2531.513 0 100% 100%
July - 2020
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 74.319 74.319 45.818 2577.331 0 100% 100%
May - 2021
Pack-1 & 2 - Completed. Pack-3 & 4 - Completed & H/O Rs: 40 M surrendered surplus to requriement
No Image
Scope of work:
Package-I
  • Admin block
  • Anatomy Department
  • Community Medicine & Forensic Medicine
  • Lecture Theatre & Exam Hall
  • Boys Hostel
Package-II
  • Pharmacology Depart: & Majid & Anima House
  • Pathology Deptt
  • Physiology & Bio Chemistry
  • Girls Hostel
  • Auditorium & Mortuary
  • Package III & IV
  • Type C Residence (10- Marlas) 15 Nos
  • Type D Residence (07- Marlas) 21 Nos
  • Boys Hostel
  • Type A Residence (18- Marlas) 05 Nos
  • Type B Residence (13- Marlas) 05 Nos
  • Cafeteria/Guest House
  • Type E Residence (05- Marlas) 20 Nos
  • Type F Residence (03- Marlas) 20 Nos
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 114.319 45.818 2577.331 0 100% 100%
April - 2021
Pack-1 & 2 - completed. Pack-3 & 4 - Completed & H/O Rs: 40 M surrendered surplus to requriement
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 114.319 38.542 2570.055 0 100% 100%
March - 2021
Pack-1 & 2 - completed. Pack-3 & 4 - Completed & H/O
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 114.319 38.542 2570.055 0 100% 100%
February - 2021
Pack-1 & 2 - completed. Pack-3 & 4 - Completed & H/O
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 56.58 21.908 2553.421 0 100% 100%
January - 2021
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II.
DI.Khan
30-11--1 30-11--1 - 30-11--1 - 2502.052 2531.513 114.319 114.319 28 0 2531.513 0 100% 100%
August - 2020
Pack-1 & 2 - completed. Pack-3 & 4 - in progress
No Image
DI.Khan
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.15 12.65 3.668 84.092 0 100% 84%
December - 2018
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.15 12.65 3.668 84.092 0 100% 84%
November - 2018
Length 6 Km - 4 Km BT completed. 500 mtr WBM completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.15 12.65 3.668 84.092 0 100% 84%
November - 2018
Length 6 Km - 4 Km BT completed. 500 mtr WBM completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.15 21.15 1.087 81.511 0 100% 82%
April - 2019
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.1 21.1 1.087 81.511 0 100% 82%
March - 2019
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.1 21.1 1.087 81.511 0 100% 82%
March - 2019
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.15 21.15 3.668 84.092 0 100% 84%
February - 2019
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
Hangu
791
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 80.424 22 21.15 12.65 3.668 84.092 0 100% 84%
January - 2019
Length 6 Km - 6 Km BT completed. Structure work in progress.
No Image
Hangu
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 15 15 108.812 91.188 54% 54%
December - 2019
3/11 Km asphalt completed. WBM, AWC in progress
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 7.5 7.5 101.312 91.188 54% 51%
November - 2019
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued.
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 3.75 3.75 97.562 91.188 54% 49%
October - 2019
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued.
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 3.75 3.75 97.562 91.188 54% 49%
September - 2019
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued.
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 3.75 3.75 97.562 91.188 54% 49%
August - 2019
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued.
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 15 15 108.812 91.188 54% 54%
May - 2020
3/11 Km asphalt completed. WBM, AWC in progress
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 15 15 108.812 91.188 54% 54%
April - 2020
3/11 Km asphalt completed. WBM, AWC in progress
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 15 15 108.812 91.188 54% 54%
March - 2020
3/11 Km asphalt completed. WBM, AWC in progress
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 15 15 108.812 91.188 54% 54%
February - 2020
3/11 Km asphalt completed. WBM, AWC in progress
No Image
Nowshera
791
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 93.812 15 15 15 15 108.812 91.188 54% 54%
January - 2020
3/11 Km asphalt completed. WBM, AWC in progress
No Image
Nowshera
791
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.406 20.183 0.001 0.001 0.0005 0 20.183 0 - -
September - 2018
No Image
791
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.406 20.183 0.001 0.001 0.0005 0 20.183 0 - -
July - 2018
No Image
791
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 69.75 60.161 0 0 0 0 60.161 9.589 - 86%
September - 2018
Length 4.5 Km - 3 Km BT completed.
No Image
Chamtalai to Toroghai road (4.50 Km)
791
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 69.75 60.161 0 0 0 0 60.161 9.589 - 86%
July - 2018
Length 4.5 Km - 3 Km BT completed.
No Image
Chamtalai to Toroghai road (4.50 Km)