Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
787 (OG) |
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.708 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 157.707 | 0% |
- September - 2018 |
Work in progress. |
No Image |
1) Swauser Kasai
2) Gulbagh
3) Sromanzai | |||||||||||||||||||
787 (OG) |
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.708 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 157.707 | 0% |
- July - 2018 |
Work in progress. |
No Image |
1) Swauser Kasai
2) Gulbagh
3) Sromanzai | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.393 | 41.859 | 40.266 | 24.337 | 5.838 | 51.231 | 12.748 | 87% |
51% December - 2018 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.393 | 41.859 | 40.266 | 24.337 | 0.085 | 45.478 | 12.748 | 87% |
45% November - 2018 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.393 | 41.859 | 40.266 | 24.337 | 0.085 | 45.478 | 12.748 | 87% |
45% November - 2018 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.394 | 41.859 | 40.266 | 40.266 | 15.429 | 60.823 | 12.747 | 87% |
61% April - 2019 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.394 | 41.859 | 40.266 | 40.266 | 9.453 | 54.847 | 12.747 | 87% |
55% March - 2019 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.394 | 41.859 | 40.266 | 40.266 | 9.453 | 54.847 | 12.747 | 87% |
55% March - 2019 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.394 | 41.859 | 40.266 | 40.266 | 5.838 | 51.232 | 12.747 | 87% |
51% February - 2019 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.394 | 41.859 | 40.266 | 24.337 | 5.838 | 51.232 | 12.747 | 87% |
51% January - 2019 |
Length 12 Km (width 18 ft) - 3 Km TST completed. |
No Image |
1) BT Road of Bahadar Kot (2 Km) ( W- 14 ft)
2) BT Road of Bazid Khel (3 Km) (w - 18ft )
3) BT Road of Paracha Town (1 Km) (width 12 Ft)
4) BT Road of UC Kharmato (2 Km) (width 18 ft )
5) BT Road of UC Chorlaki (2 Km) (width 18 ft )
6) BT Road of UC KhushalGarh (2 Km) (width 18 ft) | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 20 | 20 | 19.999689 | 307.302689 | 242.274 | 56% |
56% December - 2019 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 20 | 10 | 10 | 297.303 | 242.274 | 56% |
54% November - 2019 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 20 | 5 | 5 | 292.303 | 242.274 | 56% |
53% October - 2019 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 20 | 5 | 5 | 292.303 | 242.274 | 56% |
53% September - 2019 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 20 | 5 | 5 | 292.303 | 242.274 | 56% |
53% August - 2019 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 50 | 50 | 48.155 | 335.458 | 242.274 | 56% |
61% May - 2020 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 40 | 40 | 20 | 307.303 | 242.274 | 56% |
56% April - 2020 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 40 | 40 | 20 | 307.303 | 242.274 | 56% |
56% March - 2020 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 40 | 40 | 20 | 307.303 | 242.274 | 56% |
56% February - 2020 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (OG) |
150810-Construction/ pavement of roads/streets in UC?s Kheshgi Bala,Kheshgi Payan, Aman Garh and Gandheri, Nowshera |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 287.303 | 20 | 20 | 20 | 19.999689 | 307.302689 | 242.274 | 56% |
56% January - 2020 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |