Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2020, February - 2021, February - 2019, March - 2020, March - 2021, March - 2019, April - 2020, April - 2021, April - 2019, May - 2020, May - 2021, July - 2020, July - 2018, August - 2020, August - 2019, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
784
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 124.81 5 5 2.5 2.5 127.31 263.927 33% 32%
September - 2018
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
784
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 124.81 5 5 2.5 0 124.81 263.927 33% 32%
July - 2018
5 units - work in progress.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 137.689 12.312 12.312 6.156 0.308 137.997 0 100% 92%
December - 2018
Length 12 Km (width 12 ft) - 7 Km WBM completed. Tender for balance work re-called on 14/1/2019. Revised DCE approved . AA Awaited.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 137.689 12.312 12.312 6.156 0 137.689 0 100% 92%
November - 2018
Length 12 Km (width 12 ft) - 7 Km WBM completed. Rationalized DCE for Rs.318.5 m re-submitted to P&D after recommendations of M&E. Tender for balance work called on 03/12/2018. Tech evaluation in progress.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 137.689 12.312 12.312 6.156 0 137.689 0 100% 92%
November - 2018
Length 12 Km (width 12 ft) - 7 Km WBM completed. Rationalized DCE for Rs.318.5 m re-submitted to P&D after recommendations of M&E. Tender for balance work called on 03/12/2018. Tech evaluation in progress.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 315.636 137.689 12.312 12.317 12.317 12.317 150.006 165.635 48% 48%
April - 2019
Length 12 Km (width 12 ft) - 7 Km WBM completed. 9 Km BT completed.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 315.636 137.689 12.312 12.312 12.312 12 149.689 165.635 48% 47%
March - 2019
Length 12 Km (width 12 ft) - 7 Km WBM completed. 9 Km BT completed.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 315.636 137.689 12.312 12.312 12.312 12 149.689 165.635 48% 47%
March - 2019
Length 12 Km (width 12 ft) - 7 Km WBM completed. 9 Km BT completed.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 315.636 137.689 12.312 12.312 12.312 3.046 140.735 165.635 48% 45%
February - 2019
Length 12 Km (width 12 ft) - 7 Km WBM completed. Financial Bid of contractor opened.
No Image
Karak
784
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 315.636 137.689 12.312 12.312 6.161 0.308 137.997 165.635 48% 44%
January - 2019
Length 12 Km (width 12 ft) - 7 Km WBM completed. Tech evaluation of balance work in progress.
No Image
Karak
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 20 20 251.966 32.034 89% 89%
December - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 10 10 241.966 32.034 89% 85%
November - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 5 5 236.966 32.034 89% 83%
October - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 5 5 236.966 32.034 89% 83%
September - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 5 5 236.966 32.034 89% 83%
August - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 20 20 251.966 32.034 89% 89%
May - 2020
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 20 20 251.966 32.034 89% 89%
April - 2020
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 20 20 251.966 32.034 89% 89%
March - 2020
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 20 20 251.966 32.034 89% 89%
February - 2020
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads a) Khair Abad to Mandoo Khel Village b) Camp Koroona Yousaf Abad Akora c) Adamzai to Momond Garhi d) Jehangira Chowk to Railway Station, District Nowshera. (10 Kms)
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 231.966 20 20 20 20 251.966 32.034 89% 89%
January - 2020
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
December - 2020
PC-II submitted
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
December - 2020
PC-II submitted
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 1 1 0 0 0 0 - -
October - 2020
PC-II submitted to Client Deptt
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 1 1 0 0 0 0 - -
September - 2020
PC-II submitted to Client Deptt
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 1 1 0 0 0 0 - -
August - 2020
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 1 0 0 0 0 0 -
July - 2020
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
May - 2021
PC-II submitted
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
April - 2021
PC-II submitted
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
March - 2021
PC-II submitted
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
February - 2021
PC-II submitted
No Image
784
(New)
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 200 200 0 0 0 0
January - 2021
PC-II submitted
No Image