Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2019, February - 2020, February - 2021, February - 2019, March - 2020, March - 2021, March - 2019, April - 2020, April - 2021, April - 2019, May - 2020, May - 2021, July - 2020, July - 2018, August - 2019, August - 2020, September - 2019, September - 2020, September - 2018, October - 2019, October - 2020, November - 2019, November - 2018, December - 2019, December - 2020, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
783
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 597.77 150.289 20 20 20 10 160.289 427.481 28% 27%
September - 2018
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed, launching in progress (Kotkay bridge).
No Image
1) PK-91, Dir Upper (17.75 Km road)
2) RCC bridge Kotkay
783
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 597.77 150.289 20 20 10 0 150.289 427.481 28% 25%
July - 2018
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed, launching in progress (Kotkay bridge).
No Image
1) PK-91, Dir Upper (17.75 Km road)
2) RCC bridge Kotkay
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 7.25 7.25 58.972 88.278 41% 39%
December - 2018
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed.
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 7.25 5 56.722 88.278 41% 38%
November - 2018
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed.
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 7.25 5 56.722 88.278 41% 38%
November - 2018
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed.
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 9.75 9.75 61.472 88.278 41% 41%
April - 2019
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed. (b) earth work in progress.
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 8.5 8.5 60.222 88.278 41% 40%
March - 2019
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed. (b) earth work in progress.
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 8.5 8.5 60.222 88.278 41% 40%
March - 2019
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed. (b) earth work in progress.
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 8.5 7.25 58.972 88.278 41% 39%
February - 2019
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed. B) earth work in progress
No Image
Karak
783
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 150 51.722 10 9.75 7.25 7.25 58.972 88.278 41% 39%
January - 2019
Length 10 Km (width 20 ft) - WBM completed, BT 3 Km completed.
No Image
Karak
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 5 5 5 239.768 39.783 86% 81%
December - 2019
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units.
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 15 5 5 239.768 39.783 86% 81%
November - 2019
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units.
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 20 5 5 239.768 39.783 86% 81%
October - 2019
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units.
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 20 5 5 239.768 39.783 86% 81%
September - 2019
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units.
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 20 5 0 234.768 39.783 86% 80%
August - 2019
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units.
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 5 5 5 239.768 39.783 86% 81%
May - 2020
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units. Encroachments to be removed by District Admin
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 5 5 5 239.768 39.783 86% 81%
April - 2020
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units. Encroachments to be removed by District Admin
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 5 5 5 239.768 39.783 86% 81%
March - 2020
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units. Encroachments to be removed by District Admin
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 5 5 5 239.768 39.783 86% 81%
February - 2020
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units. Encroachments to be removed by District Admin
No Image
Nowshera
783
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads a) G.T Road to Said Akbar Koroona b) Ayub Abad to Essori Bala c) Jehangira Kati Maina d) Pitao Payan to Dargai village e) G. T Road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 294.551 234.768 20 5 5 5 239.768 39.783 86% 81%
January - 2020
Original scope - completed (12 Km). Revised scope (5 Km ) -WBM in progress on all units. Encroachments to be removed by District Admin
No Image
Nowshera
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
December - 2020
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
December - 2020
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
October - 2020
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
September - 2020
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
August - 2020
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
July - 2020
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
May - 2021
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
April - 2021
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
March - 2021
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
February - 2021
Revenue componenet only
No Image
783
(New)
200196-Up-gradation of SINOR, Swat.
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 491 0 0 0 0 0 0 0 - -
January - 2021
Revenue componenet only
No Image
Pages : 1