Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2018, March - 2019, March - 2020, March - 2021, April - 2018, April - 2019, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2018, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
78
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 7.847 0 0 0 0 0 0 7.847 - -
September - 2018
Work order issued.
No Image
1) Construction of Mosque in Khyber Pakhtunkhwa House Abbottabad (CS Directive) 2) Parda Wall of Inspection Hut C&W Deptt Abbottabad 3) Rehabilitation and renovation of Govt Guest House Shimla Hill road Abbottabad 4) Renovation of C&W Rest House Kakool Abbottabad 5) Rehabilitation / Renovtion of Kala Pani Rest House Abbottabad 6) Construction of Lavatory Block and Record Room in C&W Division Office Abbottabad
78
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 7.847 0 0 0 0 0 0 7.847 - -
July - 2018
Procurement completed.
No Image
1) Construction of Mosque in Khyber Pakhtunkhwa House Abbottabad (CS Directive) 2) Parda Wall of Inspection Hut C&W Deptt Abbottabad 3) Rehabilitation and renovation of Govt Guest House Shimla Hill road Abbottabad 4) Renovation of C&W Rest House Kakool Abbottabad 5) Rehabilitation / Renovtion of Kala Pani Rest House Abbottabad 6) Construction of Lavatory Block and Record Room in C&W Division Office Abbottabad
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 10.001 9.8 72.228 0 100% 100%
December - 2019
RW in GI wire 60% completed. Back filling in progress. Balance work tendered.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 2.5 2.5 64.928 0 100% 90%
November - 2019
RW in GI wire 60% completed. Back filling in progress. Balance work tendered.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 2.5 2.5 64.928 0 100% 90%
October - 2019
RW in GI wire 60% completed. Back filling in progress. Balance work tendered.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 2.5 2.5 64.928 0 100% 90%
September - 2019
RW in GI wire 60% completed. Back filling in progress. Balance work tendered.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 2.5 0 62.428 0 100% 86%
August - 2019
RW in GI wire 60% completed. Back filling in progress. Balance work tendered.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 10.001 9.86 72.288 0 100% 100%
May - 2020
RW in GI wire 80% completed. Back filling in progress. Balance work tendered. Cannot be completed.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 10.001 9.86 72.288 0 100% 100%
April - 2020
RW in GI wire 80% completed. Back filling in progress. Balance work tendered. Cannot be completed.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 10.001 9.86 72.288 0 100% 100%
March - 2020
RW in GI wire 80% completed. Back filling in progress. Balance work tendered. Cannot be completed.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 10.001 9.86 72.288 0 100% 100%
February - 2020
RW in GI wire 80% completed. Back filling in progress. Balance work tendered. Cannot be completed.
No Image
District Secretariat PK-79 Buner
78
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 62.428 10.001 10.001 10.001 9.86 72.288 0 100% 100%
January - 2020
RW in GI wire 80% completed. Back filling in progress. Balance work tendered. Cannot be completed.
No Image
District Secretariat PK-79 Buner
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
20-05-16 30-06-18 - 18-11-15 - 25 22.828 11.672 11.672 5.252 3.409 26.237 0 100% 100%
December - 2017
Finishing in progress.
No Image
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
20-05-16 30-06-18 - 18-11-15 - 25 22.828 11.672 11.672 5.252 1.552 24.38 0 100% 98%
September - 2017
Finishing in progress.
No Image
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
20-05-16 30-06-18 - 18-11-15 - 25 22.828 11.672 11.672 5.252 1.552 24.38 0 100% 98%
August - 2017
Finishing in progress.
No Image
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
20-05-16 30-06-18 - 18-11-15 - 25 22.828 11.672 11.672 5.252 0 22.828 0 100% 91%
July - 2017
Finishing in progress.
No Image
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 5.252 3.409 26.237 0 100% 100%
November - 2017
Finishing in progress.
No Image
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 5.252 1.552 24.38 0 100% 98%
October - 2017
Finishing in progress.
No Image
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 4.755 4.755 4.755 27.583 0 100% 100%
June - 2018
Completed.
No Image
Haripur
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 11.672 4.755 27.583 0 100% 100%
May - 2018
Completed.
No Image
Haripur
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 5.252 4.284 27.112 0 100% 100%
April - 2018
GF/FF - finishing in progress.
No Image
Haripur
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 5.252 4.284 27.112 0 100% 100%
March - 2018
GF/FF - finishing in progress.
No Image
Haripur
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 5.252 4.284 27.112 0 100% 100%
February - 2018
Finishing in progress.
No Image
Haripur
78
(OG)
150212-Re-construction of Office of Deputy Commissioner, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 25 22.828 11.672 11.672 5.252 3.409 26.237 0 100% 100%
January - 2018
Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 27.165 24.165 24.165 21.459 30.662 1.866 95% 80%
December - 2020
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 27.165 24.165 24.165 21.459 30.662 1.866 95% 80%
December - 2020
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 9 9 9 9 18.203 20.031 48% 48%
October - 2020
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 9 9 9 9 18.203 20.031 48% 48%
September - 2020
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 0 0 0 0 9.203 29.031 - 24%
August - 2020
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 14.669 27.165 0 0 0 14.669 0 100% 38%
July - 2020
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 4.564 27.165 24.165 24.165 24.165 28.729 6.505 83% 75%
May - 2021
04- Units 1. Finishing 2. Completed 3. Competed 4. AA. Not issued
No Image
1 CVD Pewar UK
2 CVD Mahoora LK
3. AD Office
4. LK W&S
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 27.165 24.165 24.165 21.164 30.367 1.866 95% 79%
April - 2021
6 - Units all in Finishing stage
No Image
1 CVD Pewar UK
2 CVD Mahoora LK
3 CVD Zawaki CK
4 CVD Said Ali Mela CK
5 CVD Donga CK
6 AD Office
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 27.165 24.165 24.165 23.407 32.61 1.866 95% 85%
March - 2021
6 - Units all in Finishing stage
No Image
1 CVD Pewar UK
2 CVD Mahoora LK
3 CVD Zawaki CK
4 CVD Said Ali Mela CK
5 CVD Donga CK
6 AD Office
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 27.165 24.165 24.165 23.407 32.61 1.866 95% 85%
February - 2021
6 - Units all in Finishing stage
No Image
1 CVD Pewar UK
2 CVD Mahoora LK
3 CVD Zawaki CK
4 CVD Said Ali Mela CK
5 CVD Donga CK
6 AD Office
78
(OG)
191065-180067 - Construction of building for Existing Vety: facilities and Solarization of AD Office in District Kurram. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 38.234 9.203 27.165 24.165 24.165 21.459 30.662 1.866 95% 80%
January - 2021
6 - Units 1- Roof level in progress. 2- S/S in progress. 3- Finishing in progress. 4- Roofing in progress. 5- S/S + Compound Wall in progress. 6- Finishing in progress.
No Image
1 CVD Pewar UK
2 CVD Mahoora LK
3 CVD Zawaki CK
4 CVD Said Ali Mela CK
5 CVD Donga CK
6 AD Office
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
December - 2018
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
November - 2018
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
November - 2018
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
April - 2019
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
March - 2019
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
March - 2019
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
February - 2019
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira Nowshera and Besham Shangla.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
January - 2019
LOA issued to consultants. Site not yet H/O.
No Image
Sub Divisional Complex at Jehangira Nowshera
78
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 316.89 120.37 0.0005 0.0005 0.0005 0 120.37 196.52 38% 38%
September - 2018
Bore, OHT completed. Work in CM Sectt and house in progress. Demand Rs. 20 M
No Image
1) Boring of Tube Well and construction of overhead tank 2 SAQ residence and the Minister's residences Peshawar
2) Construction of Office for the SE Provincial Building (Construction) Peshawar
3) Rehabilitation / Renovation of Res # 511 Hayatabad Peshawar
4) Rehabilitation / Renovation and Construction of 02 Nos Additional Room in Res # 518 at Hayatabad Peshawar
5) Construction of offices and 2 Nos Barracks, Watch Tower, Security Wall Dhobi Gath, Barber Ship etc for security staff in Chief Minister House at Peshawar, construction of BW in Chief Minister House / Secretariat (Additional Work of Tile in CM House)
6) Additional Alteration of P&D bloch in Civil Secretariat Peshawar
7) Residence of Additional Secretary P&D Deptt
8) Construction of Tube Well / OHWT at Gunner Lane Peshawar
9) Repair/renovaton and revamping of Annex/Secretariat of CM House Peshawar
10) Construction of OHWT at Gulshan Rehman Colony Kohat road Peshawar
11) Construction of Covered Walk Way in Civil Secretariat Peshawar
12) Renovation of Commissioner's Office Peshawar
13) Rehabilitation/renovation of XEN PBCC-1 building C&W Deptt Peshawar
78
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 316.89 120.37 0 0 0 0 120.37 196.52 - 38%
July - 2018
Bore, OHT completed. Work in CM Sectt and house in progress.
No Image
1) Boring of Tube Well and construction of overhead tank 2 SAQ residence and the Minister's residences Peshawar
2) Construction of Office for the SE Provincial Building (Construction) Peshawar
3) Rehabilitation / Renovation of Res # 511 Hayatabad Peshawar
4) Rehabilitation / Renovation and Construction of 02 Nos Additional Room in Res # 518 at Hayatabad Peshawar
5) Construction of offices and 2 Nos Barracks, Watch Tower, Security Wall Dhobi Gath, Barber Ship etc for security staff in Chief Minister House at Peshawar, construction of BW in Chief Minister House / Secretariat (Additional Work of Tile in CM House)
6) Additional Alteration of P&D bloch in Civil Secretariat Peshawar
7) Residence of Additional Secretary P&D Deptt
8) Construction of Tube Well / OHWT at Gunner Lane Peshawar
9) Repair/renovaton and revamping of Annex/Secretariat of CM House Peshawar
10) Construction of OHWT at Gulshan Rehman Colony Kohat road Peshawar
11) Construction of Covered Walk Way in Civil Secretariat Peshawar
12) Renovation of Commissioner's Office Peshawar
13) Rehabilitation/renovation of XEN PBCC-1 building C&W Deptt Peshawar
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira, Nowshera and Besham, Shangla.
Provincial
30-11--1 30-11--1 - 30-11--1 - 200 24.818 10 10 10 0 24.818 0 - -
December - 2018
No Image
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira, Nowshera and Besham, Shangla.
Provincial
30-11--1 30-11--1 - 30-11--1 - 200 24.818 10 10 10 0 24.818 0 - -
November - 2018
No Image
78
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira, Nowshera and Besham, Shangla.
Provincial
30-11--1 30-11--1 - 30-11--1 - 200 24.818 10 10 10 0 24.818 0 - -
November - 2018
No Image
78
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Provincial
30-11--1 30-11--1 - 30-11--1 - 334.737 103.604 0.001 0.001 0.0005 0 103.604 0 - -
September - 2018
Work in progress.
No Image
78
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Provincial
30-11--1 30-11--1 - 30-11--1 - 334.737 103.604 0.001 0.001 0.0005 0 103.604 0 - -
July - 2018
Work in progress.
No Image
Pages : 1 2