Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% December - 2018 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% November - 2018 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% November - 2018 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% April - 2019 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% March - 2019 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% March - 2019 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% February - 2019 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 436.034 | 25.351 | 25 | 25 | 25 | 25 | 50.351 | 385.683 | 12% |
12% January - 2019 |
Earth work, structure work in progress (approved 10 Km) (width - 12ft). |
No Image |
Existing road
- Baran Dam to Jani Khel 0+0 to 2-825 and 4+400 to 10+600 (length 9 Km)
New road
- Baran Dam to Jani Khel (from 16+600 length 6 Km)
- Baran Dam to jani Khel (from 0+000 to 2+00 length 2 Km)
- Police Station Miryan to Haved road (0+000 to 2+00 length 2 Km) | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 15.73517 | 58.57917 | 42.749 | 60% |
55% December - 2019 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress. |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 5 | 47.844 | 42.749 | 60% |
45% November - 2019 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress. |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 5 | 5 | 47.844 | 42.749 | 60% |
45% October - 2019 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress. |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 5 | 4.606 | 47.45 | 42.749 | 60% |
45% September - 2019 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress. |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 5 | 0 | 42.844 | 42.749 | 60% |
41% August - 2019 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress. |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 20 | 62.844 | 42.749 | 60% |
60% May - 2020 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress.
Demand Rs. 10 m |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 20 | 62.844 | 42.749 | 60% |
60% April - 2020 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress.
Demand Rs. 10 m |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 20 | 62.844 | 42.749 | 60% |
60% March - 2020 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress.
Demand Rs. 10 m |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 20 | 62.844 | 42.749 | 60% |
60% February - 2020 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress.
Demand Rs. 10 m |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 42.844 | 20 | 20 | 20 | 20 | 62.844 | 42.749 | 60% |
60% January - 2020 |
3 units - Length 7.5 Km - width 24 ft. Earth work in progress.
Demand Rs. 10 m |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
774 (OG) |
150965-Construction / Black Topping of roads Raindalay & Kakas road UC Miskini, Union Council Mayar road, Union Council Samar Bagh and UC Kambat Road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 275.308 | 65.193 | 0.001 | 0.001 | 0.0005 | 0 | 65.193 | 210.114 | 24% |
24% September - 2018 |
Length 22 Km - 3 Km BT completed. |
No Image |
1) Construction/BT of Raindlay road UC Miskini
2) Construction/BT of Kakass road UC Miskini
3) BT of Zardar Banda raod UC Mayar
4) BT of Markhano to Nasir road UC Mayar
5) BT of Adam Shah and Juni Kalay road UC Mayar
6) BT of Khwar to Inzaro (Chaghrabs) road UC Mayar
7) BT of Pattan to Batoro raod UC Mayar
8) BT of Jabagai to Batoro road UC Mayar
9) Construction of PCC road Khara UC Kambat
10) Construction of PCC road Gatano UC Kambat
11) BT of Mandizo Damtal Malkano road UC Kambat
12) BT of Damtal Nekhan Bandaroad UC Kambat
13) BT of Asharkore Bala road UC Samarbagh
14) Construction of PCC road Shontala UC Samarbagh
15) BT of Gular road UC Samarbagh
16) BT of Qashodali road UC Samarbagh
17) BT of Dandono road UC Samarbagh
18) BT of Tatar Bala and Gul Dherai road UC Samarbagh | |||||||||||||||||||
774 (OG) |
150965-Construction / Black Topping of roads Raindalay & Kakas road UC Miskini, Union Council Mayar road, Union Council Samar Bagh and UC Kambat Road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 275.308 | 65.193 | 0.001 | 0.001 | 0.0005 | 0 | 65.193 | 210.114 | 24% |
24% July - 2018 |
Length 22 Km - 3 Km BT completed. |
No Image |
1) Construction/BT of Raindlay road UC Miskini
2) Construction/BT of Kakass road UC Miskini
3) BT of Zardar Banda raod UC Mayar
4) BT of Markhano to Nasir road UC Mayar
5) BT of Adam Shah and Juni Kalay road UC Mayar
6) BT of Khwar to Inzaro (Chaghrabs) road UC Mayar
7) BT of Pattan to Batoro raod UC Mayar
8) BT of Jabagai to Batoro road UC Mayar
9) Construction of PCC road Khara UC Kambat
10) Construction of PCC road Gatano UC Kambat
11) BT of Mandizo Damtal Malkano road UC Kambat
12) BT of Damtal Nekhan Bandaroad UC Kambat
13) BT of Asharkore Bala road UC Samarbagh
14) Construction of PCC road Shontala UC Samarbagh
15) BT of Gular road UC Samarbagh
16) BT of Qashodali road UC Samarbagh
17) BT of Dandono road UC Samarbagh
18) BT of Tatar Bala and Gul Dherai road UC Samarbagh | |||||||||||||||||||
774 (New) |
190286-F/S for Up-Gradation of existing DHQ Hospital into 500 bedded Category-A Teaching Hospital in Lakki Marwat |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-II submitted to P&D. Observations Attended?
Un approved. |
No Image |
774 (New) |
190286-F/S for Up-Gradation of existing DHQ Hospital into 500 bedded Category-A Teaching Hospital in Lakki Marwat |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-II submitted to P&D. Observations Attended?
Un approved. |
No Image |
774 (New) |
190286-F/S for Up-Gradation of existing DHQ Hospital into 500 bedded Category-A Teaching Hospital in Lakki Marwat |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-II submitted to P&D. Observations Attended. |
No Image |
774 (New) |
190286-F/S for Up-Gradation of existing DHQ Hospital into 500 bedded Category-A Teaching Hospital in Lakki Marwat |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
PC-II submitted to P&D. Observations Attended. |
No Image | |
Pages : 1 |