Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 4.5005 | 3.5 | 26.666 | 26.934 | 73% |
27% December - 2018 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 4.501 | 0 | 23.166 | 26.934 | 73% |
23% November - 2018 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 4.501 | 0 | 23.166 | 26.934 | 73% |
23% November - 2018 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 9.5 | 7.02 | 30.186 | 26.934 | 73% |
30% April - 2019 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 7.0005 | 7 | 30.166 | 26.934 | 73% |
30% March - 2019 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 7.0005 | 7 | 30.166 | 26.934 | 73% |
30% March - 2019 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 7.0005 | 3.391 | 26.557 | 26.934 | 73% |
27% February - 2019 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.1 | 23.166 | 50 | 49.5 | 4.5005 | 0 | 23.166 | 26.934 | 73% |
23% January - 2019 |
Length 10 Km (15 units) - structure work, sub base in progress. |
No Image |
1) Fatima Khel to Piran road Bazar Ahmad Khan
2) Hassani Kala to Talab Shah
3) Amandi Kala to Kot Barara road
4) Danday Kala to Mandati Ketkai
5) Lalozai to Mir Aslam Surrani
6) Bangi Khel Sabir Khan Surrani
7) Master Abad and Shahji Abad Bazar Ahmad Khan
8) Shahbaz Azmat Khel road to Kotka Pakistan Gandali
9) Anwar Kamal Daud Shah
10) Sher Ali Baz Daud Shah
11) Power House No.2 to Umerdin Koroona
12) Police Canttto Army Gate
13) Khan Koroona Surrani
14) Ali Koroona Surrani
15) Kotka Feroz Oabaz Koroona | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 41.993 | 41.993 | 0.817912 | 110.916912 | 36.851 | 82% |
54% December - 2019 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 60 | 15 | 0.818 | 110.917 | 36.851 | 82% |
54% November - 2019 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 60 | 15 | 0.818 | 110.917 | 36.851 | 82% |
54% October - 2019 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 60 | 15 | 0.818 | 110.917 | 36.851 | 82% |
54% September - 2019 |
Length 2.4 Km (width 24 ft) - in progress. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 60 | 15 | 0 | 110.099 | 36.851 | 82% |
53% August - 2019 |
Length 2.4 Km (width 24 ft) - in progress. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 0.818 | 0.818 | 0.818 | 110.917 | 36.851 | 82% |
54% May - 2020 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 0.818 | 0.818 | 0.818 | 110.917 | 36.851 | 82% |
54% April - 2020 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 0.818 | 0.818 | 0.818 | 110.917 | 36.851 | 82% |
54% March - 2020 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 0.818 | 0.818 | 0.818 | 110.917 | 36.851 | 82% |
54% February - 2020 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 110.099 | 60 | 0.818 | 0.818 | 0.818 | 110.917 | 36.851 | 82% |
54% January - 2020 |
Length 2.4 Km (width 24 ft) - in progress.
Alignemnt disputed. |
No Image |
Charsadda | |||||||||||||||||||
773 (New) |
200189-F/S for Construction of Mother & Child Care Hospital at D.I.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 5 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-II has been submitted to Health Deptt Deffered in pre- PDWP for want of the social feasibility by the health deptt . |
No Image |
773 (New) |
200189-F/S for Construction of Mother & Child Care Hospital at D.I.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 5 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-II has been submitted to Health Deptt Deffered in pre- PDWP for want of the social feasibility by the health deptt . |
No Image |
773 (New) |
200189-F/S for Construction of Mother & Child Care Hospital at D.I.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 5 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
773 (New) |
200189-F/S for Construction of Mother & Child Care Hospital at D.I.Khan. |
DI.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 5 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-II has been submitted to Health Deptt |
No Image |
773 (OG) |
150964-Construction / Rehabiliation of roads Shaneey, Masho-Chinaroona, Banda Khonko Cheeno Dherey, Chinar Tangay, Ahmad Gali, Macho, Katon, Gumbat Amlok Dara, Chaman Abad, Seyar Gay, Yar Khan Banda & Nagri-Gumbat Kay, Anangro Khwar & Hajiabad Distt Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 367.574 | 234.121 | 0.001 | 0.001 | 0 | 0 | 234.121 | 133.452 | 64% |
64% September - 2018 |
Length 31 Km (20 units) - 12 Km BT completed, 19 Km in progress. |
No Image |
1) Shaneey road
2) Mashoo road
3) Chinarono road
4) Banda road
5) Chinoo road
6) Dehrai road
7) Chinar Tangai road
8) Machoo road
9) Gumbat road
10) Katan road
11) Khonako road
12) Ahmad Galai road
13) Amlook Dara road
14) Siar Gatt road
15) Chaman Abad road
16) Yar Khan Banda road
17) Nagrai road
18) Gumbat Gai road
19) Anangoro road
20) Haji Abad road | |||||||||||||||||||
773 (OG) |
150964-Construction / Rehabiliation of roads Shaneey, Masho-Chinaroona, Banda Khonko Cheeno Dherey, Chinar Tangay, Ahmad Gali, Macho, Katon, Gumbat Amlok Dara, Chaman Abad, Seyar Gay, Yar Khan Banda & Nagri-Gumbat Kay, Anangro Khwar & Hajiabad Distt Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 367.574 | 234.121 | 0.001 | 0.001 | 0 | 0 | 234.121 | 133.452 | 64% |
64% July - 2018 |
Length 31 Km (20 units) - 12 Km BT completed, 19 Km in progress. |
No Image |
1) Shaneey road
2) Mashoo road
3) Chinarono road
4) Banda road
5) Chinoo road
6) Dehrai road
7) Chinar Tangai road
8) Machoo road
9) Gumbat road
10) Katan road
11) Khonako road
12) Ahmad Galai road
13) Amlook Dara road
14) Siar Gatt road
15) Chaman Abad road
16) Yar Khan Banda road
17) Nagrai road
18) Gumbat Gai road
19) Anangoro road
20) Haji Abad road | |||||||||||||||||||
Pages : 1 |