Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, February - 2019, February - 2020, February - 2021, March - 2019, March - 2020, March - 2021, April - 2019, April - 2020, April - 2021, May - 2020, May - 2021, July - 2020, July - 2018, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, November - 2018, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 4

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 5 5 5 0.494 34.858 2.649 94% 83%
December - 2020
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 5 5 5 0.494 34.858 2.649 94% 83%
December - 2020
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 0 5 5 5 0 0 37.013 12% -
October - 2020
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 0 5 5 5 0 0 37.013 12% -
September - 2020
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 0 0 0 0 0 0 42.013 - -
August - 2020
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 0 0 0 0 0 0 42.013 - -
July - 2020
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 6.743 6.743 6.743 1.459 35.823 0.906 98% 85%
May - 2021
05- Units 1. Completed & handed over 2. Completed & handed over 3. Completed & handed over 4. B/wall completed. Main building Block-A completed Block-B not yet started 5. Completed
No Image
1) Civil Hospital Sherwan PK-46
2 BHU Ghori
3 BHU Langrial
4 BHU Nagri Totial
5 CD Leeran
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 5 5 5 1.459 35.823 2.649 94% 85%
April - 2021
5 Units - 04 units- H/O 01 unit - in progress 1. Completed & handed over 2. Completed & handed over 3. Completed & handed over 4. B/wall completed. Main building Block-A completed Block-B not yet started 5. Completed
No Image
1) Civil Hospital Sherwan PK-46
2 BHU Ghori
3 BHU Langrial
4 BHU Nagri Totial
5 CD Leeran
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 5 5 5 1.459 35.823 2.649 94% 85%
March - 2021
5 Units - 04 units- H/O 01 unit - in progress 1. Completed & handed over 2. Completed & handed over 3. Completed & handed over 4. B/wall completed. Main building Block-A completed Block-B not yet started 5. Completed
No Image
1) Civil Hospital Sherwan PK-46
2 BHU Ghori
3 BHU Langrial
4 BHU Nagri Totial
5 CD Leeran
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 5 5 5 1.459 35.823 2.649 94% 85%
February - 2021
5 Units - 04 units- H/O 01 unit - in progress 1. Completed & handed over 2. Completed & handed over 3. Completed & handed over 4. B/wall completed. Main building Block-A completed Block-B not yet started 5. Completed
No Image
1) Civil Hospital Sherwan PK-46
2 BHU Ghori
3 BHU Langrial
4 BHU Nagri Totial
5 CD Leeran
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 42.013 34.364 5 5 5 0.714 35.078 2.649 94% 83%
January - 2021
5 Units - Repair nature of work. Work in progress.
No Image
1) Civil Hospital Sherwan PK-46
2 BHU Ghori
3 BHU Langrial
4 BHU Nagri Totial
5 CD Leeran
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 12.5 5 65.0637 1.452 98% 85%
December - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
Bannu
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 1.365 1.365 1.365 0.748 11.287 0 100% 95%
December - 2020
completed
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 1.365 1.365 1.365 0.748 11.287 0 100% 95%
December - 2020
completed
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 12.5 5 65.0637 1.452 98% 85%
November - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
Bannu
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 12.5 5 65.0637 1.452 98% 85%
November - 2018
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed.
No Image
Bannu
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 0 1.365 1.365 1.365 0 0 10.539 11% -
October - 2020
Out of 9 units, 8 completed, 1 dropped.
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 0 1.365 1.365 1.365 0 0 10.539 11% -
September - 2020
Out of 9 units, 8 completed, 1 dropped.
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 0 1.365 1.365 1.365 0 0 10.539 11% -
August - 2020
Out of 9 units, 8 completed, 1 dropped. Deamnd R
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 0 0 0 0 0 0 11.904 - -
July - 2020
Out of 9 units, 8 completed, 1 dropped. Deamnd R
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 0.827 0.827 0.827 0.827 11.366 0.538 95% 95%
May - 2021
01-Unit Completed & H/O
No Image
1) DHO Office Bannu
2) DHO residence Bannu
3 Type D Hospital Jani Khel
4 CD Kalan Tughal Khel
5 CD Zalim Mandan
6 CD Khan Suba Mitha Khel
7 BHU Seru Bada Khel
8 BHU Biland Fatma Khel
9 CD Lawat Landidak
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 15 5 65.0637 1.452 98% 85%
April - 2019
Length 8 Km - road work 5 Km ready for asphalt. ). Remaining (1.5 Km) earth work completed.
No Image
Bannu
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 1.365 1.365 1.365 0.824 11.363 0 100% 95%
April - 2021
completed & H/O
No Image
1) DHO Office Bannu
2) DHO residence Bannu
3 Type D Hospital Jani Khel
4 CD Kalan Tughal Khel
5 CD Zalim Mandan
6 CD Khan Suba Mitha Khel
7 BHU Seru Bada Khel
8 BHU Biland Fatma Khel
9 CD Lawat Landidak
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 15 5 65.0637 1.452 98% 85%
March - 2019
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Stay order issued.
No Image
Bannu
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 15 5 65.0637 1.452 98% 85%
March - 2019
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Stay order issued.
No Image
Bannu
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 1.365 1.365 1.365 0.824 11.363 0 100% 95%
March - 2021
completed & H/O
No Image
1) DHO Office Bannu
2) DHO residence Bannu
3 Type D Hospital Jani Khel
4 CD Kalan Tughal Khel
5 CD Zalim Mandan
6 CD Khan Suba Mitha Khel
7 BHU Seru Bada Khel
8 BHU Biland Fatma Khel
9 CD Lawat Landidak
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 15 5 65.0637 1.452 98% 85%
February - 2019
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Stay order issued.
No Image
Bannu
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 1.365 1.365 1.365 0.824 11.363 0 100% 95%
February - 2021
completed & H/O
No Image
1) DHO Office Bannu
2) DHO residence Bannu
3 Type D Hospital Jani Khel
4 CD Kalan Tughal Khel
5 CD Zalim Mandan
6 CD Khan Suba Mitha Khel
7 BHU Seru Bada Khel
8 BHU Biland Fatma Khel
9 CD Lawat Landidak
771
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 76.516 60.0637 15 15 12.5 5 65.0637 1.452 98% 85%
January - 2019
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Stay order issued.
No Image
Bannu
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Bannu
30-11--1 30-11--1 - 30-11--1 - 11.904 10.539 1.365 1.365 1.365 0.748 11.287 0 100% 95%
January - 2021
completed
No Image
1) DHO Office Bannu
2) DHO resi
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 23.40625 23.40625 23.406 151.39 172.016 47% 47%
December - 2019
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress.
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 25 6.25 6.25 134.234 172.016 47% 41%
November - 2019
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress.
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 25 6.25 6.25 134.234 172.016 47% 41%
October - 2019
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress.
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 25 6.25 6.25 134.234 172.016 47% 41%
September - 2019
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress.
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 25 6.25 3.15 131.134 172.016 47% 40%
August - 2019
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress.
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 23.40625 23.40625 23.406 151.39 172.016 47% 47%
May - 2020
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress. Demand Rs. 20 m
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 23.40625 23.40625 23.406 151.39 172.016 47% 47%
April - 2020
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress. Demand Rs. 20 m
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 23.40625 23.40625 23.406 151.39 172.016 47% 47%
March - 2020
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress. Demand Rs. 20 m
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 23.40625 23.40625 23.406 151.39 172.016 47% 47%
February - 2020
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress. Demand Rs. 20 m
No Image
Charsadda
771
(OG)
150954-Construction and BT of road a) Peshawar road to Kodai UC Agra b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 325 127.984 25 23.40625 23.40625 23.406 151.39 172.016 47% 47%
January - 2020
8.5 Km (original scope) - 8.5 Km asphalt completed. Revised scope (15.8 Km)- work in progress. Demand Rs. 20 m
No Image
Charsadda
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
December - 2020
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
December - 2020
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
October - 2020
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
September - 2020
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
August - 2020
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
July - 2020
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
May - 2021
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
April - 2021
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
March - 2021
Work in progress.
No Image
(reconstruction)
771
(OG)
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 168.471 0 0 0 0 0 0 168.471 - -
February - 2021
Work in progress.
No Image
(reconstruction)