Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2018, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
December - 2018
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
November - 2018
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
November - 2018
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
April - 2019
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
March - 2019
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
March - 2019
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
February - 2019
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
January - 2019
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-09-17 - - 23-12-16 - 104.382 0 20 35 24 16 16 84.382 19% 15%
December - 2017
Foundation and plinth in progress.
No Image
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
- - - 23-12-16 - 104.382 0 20 20 9 0 0 84.382 19% -
September - 2017
Work started. Site recently handed over.
No Image
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
- - - 23-12-16 - 104.382 0 20 20 9 0 0 84.382 19% -
August - 2017
Work started.
No Image
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
- - - 23-12-16 - 104.382 0 20 20 9 0 0 84.382 19% -
July - 2017
Work started.
No Image
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 20 9 9 9 84.382 19% 9%
November - 2017
Foundation and plinth in progress.
No Image
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 20 9 9 9 84.382 19% 9%
October - 2017
Work started.
No Image
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 35 35 35 35 84.382 19% 34%
June - 2018
GF - roof laid, plastering in progress. FF - roofing in progress.
No Image
Battagram
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 35 35 35 35 84.382 19% 34%
May - 2018
GF - roof laid. FF - roofing in progress. Rs.20 m demanded.
No Image
Battagram
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 35 35 33.997 33.997 84.382 19% 33%
April - 2018
GF - roof laid. FF - roofing in progress. Rs.50 m demanded.
No Image
Battagram
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 35 35 24 24 84.382 19% 23%
March - 2018
Basement - roofing in progress.
No Image
Battagram
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 35 24 24 24 84.382 19% 23%
February - 2018
Basement - roofing in progress.
ADP's Images
Battagram
77
(OG)
150484-Construction of Deputy Commissioner Office cum Residence, Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 0 20 35 24 16.501 16.501 84.382 19% 16%
January - 2018
Basement upto lintel in progress.
No Image
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
December - 2018
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
November - 2018
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
November - 2018
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
April - 2019
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
March - 2019
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
March - 2019
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
February - 2019
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
January - 2019
Completed & H/O.
No Image
PHED Office Chitral
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
December - 2020
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
December - 2020
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
October - 2020
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
September - 2020
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
August - 2020
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 182.108 0 0 0 0 182.108 0 -
July - 2020
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
May - 2021
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
April - 2021
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
March - 2021
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
February - 2021
No Image
77
(OG)
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 196.108 0 0 0 0 0 0 0 - -
January - 2021
No Image
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 0 0 0 2.813 0 100% 11%
December - 2019
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 21.873 5.468 0 2.813 0 100% 11%
November - 2019
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 21.873 5.468 0 2.813 0 100% 11%
October - 2019
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 21.873 5.468 0 2.813 0 100% 11%
September - 2019
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 21.873 5.468 0 2.813 0 100% 11%
August - 2019
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 0 0 0 2.813 0 100% 11%
May - 2020
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 0 0 0 2.813 0 100% 11%
April - 2020
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 0 0 0 2.813 0 100% 11%
March - 2020
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 0 0 0 2.813 0 100% 11%
February - 2020
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 24.686 2.813 21.873 0 0 0 2.813 0 100% 11%
January - 2020
Dismantling of old building involved. Site not handed over by client deptt.
No Image
Malakand (DC office/hall)
77
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Mardan
30-11--1 30-11--1 - 30-11--1 - 58.805 46.308 8.681 8.681 8.681 8.681 54.989 3.816 94% 94%
December - 2018
Completed.
No Image
1) C&W Circle and Highway Division Mardan ? AA Rs.32.508 m dated 15/03/2018
2) PHED office Mardan ? AA Rs.26.297 m dated 15/03/2018
Pages : 1 2