Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% December - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% November - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% November - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% April - 2019 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% March - 2019 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% March - 2019 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% February - 2019 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% January - 2019 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-09-17 | - | - | 23-12-16 | - | 104.382 | 0 | 20 | 35 | 24 | 16 | 16 | 84.382 | 19% |
15% December - 2017 |
Foundation and plinth in progress. |
No Image |
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
- | - | - | 23-12-16 | - | 104.382 | 0 | 20 | 20 | 9 | 0 | 0 | 84.382 | 19% |
- September - 2017 |
Work started. Site recently handed over. |
No Image |
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
- | - | - | 23-12-16 | - | 104.382 | 0 | 20 | 20 | 9 | 0 | 0 | 84.382 | 19% |
- August - 2017 |
Work started. |
No Image |
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
- | - | - | 23-12-16 | - | 104.382 | 0 | 20 | 20 | 9 | 0 | 0 | 84.382 | 19% |
- July - 2017 |
Work started. |
No Image |
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 20 | 9 | 9 | 9 | 84.382 | 19% |
9% November - 2017 |
Foundation and plinth in progress. |
No Image |
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 20 | 9 | 9 | 9 | 84.382 | 19% |
9% October - 2017 |
Work started. |
No Image |
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 35 | 35 | 35 | 35 | 84.382 | 19% |
34% June - 2018 |
GF - roof laid, plastering in progress. FF - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 35 | 35 | 35 | 35 | 84.382 | 19% |
34% May - 2018 |
GF - roof laid. FF - roofing in progress. Rs.20 m demanded. |
No Image |
Battagram | |||||||||||||||||||
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 35 | 35 | 33.997 | 33.997 | 84.382 | 19% |
33% April - 2018 |
GF - roof laid. FF - roofing in progress. Rs.50 m demanded. |
No Image |
Battagram | |||||||||||||||||||
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 35 | 35 | 24 | 24 | 84.382 | 19% |
23% March - 2018 |
Basement - roofing in progress. |
No Image |
Battagram | |||||||||||||||||||
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 35 | 24 | 24 | 24 | 84.382 | 19% |
23% February - 2018 |
Basement - roofing in progress. |
ADP's Images |
Battagram | |||||||||||||||||||
77 (OG) |
150484-Construction of Deputy Commissioner Office cum Residence, Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.382 | 0 | 20 | 35 | 24 | 16.501 | 16.501 | 84.382 | 19% |
16% January - 2018 |
Basement upto lintel in progress. |
No Image |
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% December - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% November - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% November - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% April - 2019 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% March - 2019 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% March - 2019 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% February - 2019 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% January - 2019 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 182.108 | 0 | 0 | 0 | 0 | 182.108 | 0 | - |
July - 2020 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
77 (OG) |
191054-050011-Opening of 05 CVCs and 08 CVDs, 22 AICs and Diagonostic Laboratory in Kurram Agency. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 196.108 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 0 | 0 | 0 | 2.813 | 0 | 100% |
11% December - 2019 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 21.873 | 5.468 | 0 | 2.813 | 0 | 100% |
11% November - 2019 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 21.873 | 5.468 | 0 | 2.813 | 0 | 100% |
11% October - 2019 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 21.873 | 5.468 | 0 | 2.813 | 0 | 100% |
11% September - 2019 |
Dismantling of old building involved. Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 21.873 | 5.468 | 0 | 2.813 | 0 | 100% |
11% August - 2019 |
Dismantling of old building involved. Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 0 | 0 | 0 | 2.813 | 0 | 100% |
11% May - 2020 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 0 | 0 | 0 | 2.813 | 0 | 100% |
11% April - 2020 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 0 | 0 | 0 | 2.813 | 0 | 100% |
11% March - 2020 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 0 | 0 | 0 | 2.813 | 0 | 100% |
11% February - 2020 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
160613-Construction of Deputy Commissioner Office i/c Hall in District Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.686 | 2.813 | 21.873 | 0 | 0 | 0 | 2.813 | 0 | 100% |
11% January - 2020 |
Dismantling of old building involved.
Site not handed over by client deptt. |
No Image |
Malakand (DC office/hall) | |||||||||||||||||||
77 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.805 | 46.308 | 8.681 | 8.681 | 8.681 | 8.681 | 54.989 | 3.816 | 94% |
94% December - 2018 |
Completed. |
No Image |
1) C&W Circle and Highway Division Mardan ? AA Rs.32.508 m dated 15/03/2018
2) PHED office Mardan ? AA Rs.26.297 m dated 15/03/2018 | |||||||||||||||||||
Pages : 1 2 |