Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, February - 2019, February - 2020, February - 2021, March - 2019, March - 2020, March - 2021, April - 2019, April - 2020, April - 2021, May - 2020, May - 2021, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2018, November - 2019, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 10 2 0 1.98 211.094 5% 1%
December - 2020
Technical bids opened on 24/08/2020. Technical evaluation in process.
No Image
Abbottabad
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 10 2 0 1.98 211.094 5% 1%
December - 2020
Technical bids opened on 24/08/2020. Technical evaluation in process.
No Image
Abbottabad
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 10 2 0 1.98 211.094 5% 1%
October - 2020
Technical bids opened on 24/08/2020. Technical evaluation in process.
No Image
Abbottabad
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 10 2 0 1.98 211.094 5% 1%
September - 2020
Technical bids opened on 24/08/2020. Technical evaluation in process.
No Image
Abbottabad
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 10 0 0 1.98 211.094 5% 1%
August - 2020
DCE for Rs. 1000 M submitted to MS DHQ
No Image
Abbottabad
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 0 0 0 1.98 211.094 5% 1%
July - 2020
DCE for Rs. 1000 M submitted to MS DHQ
No Image
Abbottabad
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 0 0 0 1.98 211.094 5% 1%
May - 2021
01- Unit Auction in progress
No Image
 DHQ Hospital,  Abbottabad to Category-A.
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 2 2 0 1.98 211.094 5% 1%
April - 2021
NOC not yet recived form Auction of Exiting building from Health Deptt.
No Image
 DHQ Hospital,  Abbottabad to Category-A.
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 2 2 0 1.98 211.094 5% 1%
March - 2021
NOC not yet recived form Auction of Exiting building
No Image
 DHQ Hospital,  Abbottabad to Category-A.
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 2 2 0 1.98 211.094 5% 1%
February - 2021
NOC not yet recived form Auction of Exiting building
No Image
 DHQ Hospital,  Abbottabad to Category-A.
768
(OG)
130674-Upgrdadation of DHQ Hospital, Abbottabad to Category-A.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 223.074 1.98 10 10 2 0 1.98 211.094 5% 1%
January - 2021
Technical bids opened on 24/08/2020. Technical evaluation in process.
No Image
 DHQ Hospital,  Abbottabad to Category-A.
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
December - 2019
Length 7 Km - 3 Km completed. Demand Rs. 20 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
November - 2019
Length 7 Km - 3 Km completed. Demand Rs. 20 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
October - 2019
Length 7 Km - 3 Km completed. Demand Rs. 20 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
September - 2019
Length 7 Km - 3 Km completed.
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 7.5 7.5 139.945 68.472 70% 61%
August - 2019
Length 7 Km - 3 Km completed.
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
May - 2020
Length 7 Km - 3 Km completed. Demand Rs. 50 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
April - 2020
Length 7 Km - 3 Km completed. Demand Rs. 50 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
March - 2020
Length 7 Km - 3 Km completed. Demand Rs. 50 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
February - 2020
Length 7 Km - 3 Km completed. Demand Rs. 50 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 230.917 132.445 30 30 30 30 162.445 68.472 70% 70%
January - 2020
Length 7 Km - 3 Km completed. Demand Rs. 50 m
No Image
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft )  
768
(OG)
150835-Construction of RCC Bridges at Hajiabad, Munjai & Nasafa, Kano, Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 450.485 42.237 10 10 10 5 47.237 398.248 12% 10%
September - 2018
Munjai Bridge - working pile in progress. Casting of girders in progress. 3 units tender in progress.
No Image
1) RCC Bridges in Dir Lower (4 Nos)
2) RCC Bridge at Munjai (210 mtr)
3) Haji Abad (210 mtr)
4) Nasafa (140 mtr)
5) Kano (70 mtr)
768
(OG)
150835-Construction of RCC Bridges at Hajiabad, Munjai & Nasafa, Kano, Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 450.485 42.237 10 10 5 0 42.237 398.248 12% 9%
July - 2018
Munjai Bridge - working pile in progress. Casting of girders in progress. 3 units tender in progress.
No Image
1) RCC Bridges in Dir Lower (4 Nos)
2) RCC Bridge at Munjai (210 mtr)
3) Haji Abad (210 mtr)
4) Nasafa (140 mtr)
5) Kano (70 mtr)
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 3.707 2.308 32.058 0 100% 100%
December - 2018
Length 3 Km - earth work, road work completed, structure work 30% completed. Court case.
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 3.707 2.308 32.058 0 100% 100%
November - 2018
Length 3 Km - earth work, road work completed, structure work 30% completed. Court case.
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 3.707 2.308 32.058 0 100% 100%
November - 2018
Length 3 Km - earth work, road work completed, structure work 30% completed. Court case.
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 4.942 4.576 34.326 0 100% 100%
April - 2019
Length 3 Km - completed. (physiaclly + financailly).
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 4.942 3.707 33.457 0 100% 100%
March - 2019
Length 3 Km - completed. (physiaclly + financailly).
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 4.942 3.707 33.457 0 100% 100%
March - 2019
Length 3 Km - completed. (physiaclly + financailly).
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 4.942 3.707 33.457 0 100% 100%
February - 2019
Length 3 Km - completed. (physiaclly + financailly).
No Image
PK-74, Lakki Marwat
768
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 30 29.75 4.942 4.942 3.707 3.707 33.457 0 100% 100%
January - 2019
Length 3 Km - Complted. (physiaclly + financailly )
No Image
PK-74, Lakki Marwat