Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 13.881536 | 161.146536 | 82.735 | 67% |
64% December - 2019 |
12 Km length - 7 Km completed. |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 13.881 | 161.146 | 82.735 | 67% |
64% November - 2019 |
12 Km length - 7 Km completed. |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 5 | 152.265 | 82.735 | 67% |
61% October - 2019 |
12 Km length - 7 Km completed. |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 5 | 5 | 152.265 | 82.735 | 67% |
61% September - 2019 |
12 Km length - 7 Km completed. |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 5 | 0 | 147.265 | 82.735 | 67% |
59% August - 2019 |
12 Km length - 7 Km completed. |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 20 | 167.265 | 82.735 | 67% |
67% May - 2020 |
12 Km length - 7 Km completed.
Demand Rs. 20 m |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 20 | 167.265 | 82.735 | 67% |
67% April - 2020 |
12 Km length - 7 Km completed.
Demand Rs. 20 m |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 20 | 167.265 | 82.735 | 67% |
67% March - 2020 |
12 Km length - 7 Km completed.
Demand Rs. 20 m |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 20 | 167.265 | 82.735 | 67% |
67% February - 2020 |
12 Km length - 7 Km completed.
Demand Rs. 20 m |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140890-F/S, Design, Reconst: & Reh: of Roads a) Alladad Khel-Village Kani b) Ziam Rest House-Salgaray via Gud Killi Chowk c) Village Cheena-Dildar Ghari (12 Km), 2) Main Tangi Rd Rehmat Killi-Sarfaraz Killi Shakh No. 03, 3) Charai rd-Gujar Killi....Chars |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 147.265 | 20 | 20 | 20 | 20 | 167.265 | 82.735 | 67% |
67% January - 2020 |
12 Km length - 7 Km completed.
Demand Rs. 20 m |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft )
New Scope :
(2) Construction & rehabilitation of road from Main Shakoor Madhand road to Lalma Islamabad and link road to Muslim Abad Shakoor (3) construction and rehabilitation of Main road from Yar Jan Killi Sewan Chowk to Khanjari (4) Reconstruction and rehabilitation of road from Main Shodag Shakoor road to Mulagori and link road in UC Shodag (5) construction and rehabilitation of road in Harichand (6) construction and rehabilitation of road from Sherpao Chowk to Jindi via Durrankheil i/c link roads 1.40 Km. | |||||||||||||||||||
767 (OG) |
140989-F/S, Design and Construction of 4 Nos of RCC Bridges (a) Aghiraly and Arif (b) Darangal Khwar (c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 136.483 | 0.001 | 0.001 | 0.0005 | 0 | 136.483 | 38.342 | 78% |
78% September - 2018 |
Out of 4 bridges, all in progress (Agharily, Arif Killi, Darangal Khwar, Markhani Maidan bridges). |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
767 (OG) |
140989-F/S, Design and Construction of 4 Nos of RCC Bridges (a) Aghiraly and Arif (b) Darangal Khwar (c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 136.483 | 0.001 | 0.001 | 0.0005 | 0 | 136.483 | 38.342 | 78% |
78% July - 2018 |
Out of 4 bridges, all in progress (Agharily, Arif Killi, Darangal Khwar, Markhani Maidan bridges). |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 4.5005 | 1.433 | 12.982 | 128.451 | 14% |
9% December - 2018 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 4.501 | 1.433 | 12.982 | 128.451 | 14% |
9% November - 2018 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 4.501 | 1.433 | 12.982 | 128.451 | 14% |
9% November - 2018 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 9.5005 | 9.0935 | 20.6425 | 128.451 | 14% |
14% April - 2019 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 9.5005 | 4.5005 | 16.0495 | 128.451 | 14% |
11% March - 2019 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 9.5005 | 4.5005 | 16.0495 | 128.451 | 14% |
11% March - 2019 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 9.5005 | 4.5005 | 16.0495 | 128.451 | 14% |
11% February - 2019 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 11.549 | 10 | 9.5 | 4.5005 | 4.5005 | 16.0495 | 128.451 | 14% |
11% January - 2019 |
Length 6 Km - earth work, sub base in progress. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 15 | 15 | 69.322 | 180.03 | 29% |
27% December - 2020 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 15 | 15 | 69.322 | 180.03 | 29% |
27% December - 2020 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 4 | 4 | 58.322 | 180.03 | 29% |
23% October - 2020 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 4 | 4 | 58.322 | 180.03 | 29% |
23% September - 2020 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 0 | 0 | 54.322 | 180.03 | 29% |
21% August - 2020 |
Main building finishing in progress. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 0 | 0 | 0 | 54.322 | 180.03 | 29% |
21% July - 2020 |
A) Main building finishing in progress.
Paint wor |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 45 | 45 | 45 | 99.322 | 180.03 | 29% |
39% May - 2021 |
01-Unit
Main building finishing in progress.
Main Building basement roof laid.
Demand Rs. 30 M |
No Image |
PK-33, Mansehra
Scope of work:
| |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 45 | 45 | 45 | 99.322 | 180.03 | 29% |
39% April - 2021 |
Main building finishing in progress?
2- main building basement roof laid.
Demand Rs. 30 M |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 45 | 45 | 45 | 99.322 | 180.03 | 29% |
39% March - 2021 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 20 | 19.902 | 74.224 | 180.03 | 29% |
29% February - 2021 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
767 (OG) |
150007-Upgradation of RHC Oghi to Cat-D Hospital, District Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 254.352 | 54.322 | 20 | 20 | 20 | 19.902 | 74.224 | 180.03 | 29% |
29% January - 2021 |
Main building finishing in progress?
2- main building basement roof laid. |
No Image |
PK-33, Mansehra | |||||||||||||||||||
Pages : 1 |