Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
765 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 57.75 | 0.001 | 0.001 | 0.0005 | 0 | 57.75 | 104.789 | 36% |
36% September - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1) Package-1
2) Package-2
3) Package-3
4) Package-4 | |||||||||||||||||||
765 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 57.75 | 0.001 | 0.001 | 0.0005 | 0 | 57.75 | 104.789 | 36% |
36% July - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1) Package-1
2) Package-2
3) Package-3
4) Package-4 | |||||||||||||||||||
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 986 | 0 | 20 | 20 | 0 | 0 | 0 | 966 | 2% |
- December - 2020 |
Approved. AA Awqaited . |
No Image |
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 986 | 0 | 20 | 20 | 0 | 0 | 0 | 966 | 2% |
- December - 2020 |
Approved. AA Awqaited . |
No Image |
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 280 | 7% |
- October - 2020 |
LOA issued to Consultant. Drawing awaited. |
No Image |
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 280 | 7% |
- September - 2020 |
LOA issued to Consultant. Drawing awaited. |
No Image |
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 280 | 7% |
- August - 2020 |
LOA issued to Consultant. Drawing awaited. |
No Image |
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
PC-II approved for Rs. 12.48 m on 8/10/2019. Finna |
No Image |
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 0 | 0 | 0 | 0 | 0 |
- May - 2021 |
Approved. AA Awqaited . |
No Image | |
Head Quarter Hospital at Ghazi Abad, | |||||||||||||||||||
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 0 | 0 | 0 | 0 | 0 |
- April - 2021 |
Approved. AA Awqaited . |
No Image | |
Head Quarter Hospital at Ghazi Abad, | |||||||||||||||||||
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 0 | 0 | 0 | 0 | 0 |
- March - 2021 |
Approved. AA Awqaited . |
No Image | |
Head Quarter Hospital at Ghazi Abad, | |||||||||||||||||||
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 20 | 0 | 0 | 0 | 0 | 0 |
- February - 2021 |
Approved. AA Awqaited . |
No Image | |
Head Quarter Hospital at Ghazi Abad, | |||||||||||||||||||
765 (OG) |
151063-Establishment of District Head Quarter Hospital at Ghazi Abad, District Kolai Palas (PC-II approved on 08-10-2019) |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 986 | 0 | 20 | 20 | 0 | 0 | 0 | 966 | 2% |
- January - 2021 |
Approved. AA Awqaited . |
No Image |
Head Quarter Hospital at Ghazi Abad, | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 25 | 25 | 25 | 208.81 | 85.105 | 71% |
71% December - 2018 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 25 | 25 | 25 | 208.81 | 85.105 | 71% |
71% November - 2018 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 25 | 25 | 25 | 208.81 | 85.105 | 71% |
71% November - 2018 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 45 | 45 | 45 | 228.81 | 85.105 | 71% |
78% April - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 45 | 45 | 45 | 228.81 | 85.105 | 71% |
78% March - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 45 | 45 | 45 | 228.81 | 85.105 | 71% |
78% March - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 45 | 45 | 25 | 208.81 | 85.105 | 71% |
71% February - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability : 20 M. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 183.81 | 25 | 25 | 25 | 25 | 208.81 | 85.105 | 71% |
71% January - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% December - 2019 |
Internal roads 20 Km - structure work in progress. Rev AA issued. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% November - 2019 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% October - 2019 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 5 | 134.5 | 50.5 | 75% |
67% September - 2019 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 5 | 5 | 134.5 | 50.5 | 75% |
67% August - 2019 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% May - 2020 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% April - 2020 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% March - 2020 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% February - 2020 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
765 (OG) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 129.5 | 20 | 20 | 20 | 20 | 149.5 | 50.5 | 75% |
75% January - 2020 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
Pages : 1 |