Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 4.501 | 4.5 | 80.868 | 111.755 | 44% |
41% December - 2018 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 4.501 | 3.175 | 79.543 | 111.755 | 44% |
40% November - 2018 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 4.501 | 3.175 | 79.543 | 111.755 | 44% |
40% November - 2018 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 9.5 | 9.5 | 85.868 | 111.755 | 44% |
43% April - 2019 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 7.0005 | 4.5 | 80.868 | 111.755 | 44% |
41% March - 2019 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 7.0005 | 4.5 | 80.868 | 111.755 | 44% |
41% March - 2019 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 7.0005 | 4.5 | 80.868 | 111.755 | 44% |
41% February - 2019 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
150780-(a) Construciton / Rehabilitation of road (a) Tank Adda - Zafar Abad Colony and Daraban Chungi (b) Circular Road - Muryali Mor, Shah Alam Abad, Eye Hospital road, Chashma road - Village Singar, Sheikh Yousaf DI.Khan (10.24 Kms) (i) Circular Road - Multan Road (ii) Diyal Road balance length 0.88 Km (iii) Bannu Road - Kotli (0.31 Km) (iv) TB Hospital Chowk to Circular House Road (0.78 Km) (v) Drain from Kotli to Shobra Hotel. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.123 | 76.368 | 10 | 9.5 | 4.501 | 4.5 | 80.868 | 111.755 | 44% |
41% January - 2019 |
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6 units sub base in progress.
Additional work - work order issued. |
No Image |
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 20 | 8.905925 | 39.627925 | 133.4 | 28% |
22% December - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 5 | 5 | 35.722 | 133.4 | 28% |
19% November - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 5 | 5 | 35.722 | 133.4 | 28% |
19% October - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 5 | 5 | 35.722 | 133.4 | 28% |
19% September - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 5 | 0 | 30.722 | 133.4 | 28% |
17% August - 2019 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 20 | 16.789 | 47.511 | 133.4 | 28% |
26% May - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 20 | 8.905925 | 39.627925 | 133.4 | 28% |
22% April - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 20 | 8.905925 | 39.627925 | 133.4 | 28% |
22% March - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 20 | 8.905925 | 39.627925 | 133.4 | 28% |
22% February - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 30.722 | 20 | 20 | 20 | 8.905925 | 39.627925 | 133.4 | 28% |
22% January - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 118 | 88.5 | 88.079 | 148.879 | 168.2 | 52% |
43% December - 2020 |
Work in progress.
MB- Ist Floor roof laid, Plater in progress, Doctor Flates roof in progress. Supper staff roof laid plaster work in progrees.
Gyanee Block S/S completed. Wards foundation work in progress.
Mature Liabilities 80 M |
No Image |
Kabal, Swat | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 118 | 88.5 | 88.079 | 148.879 | 168.2 | 52% |
43% December - 2020 |
Work in progress.
MB- Ist Floor roof laid, Plater in progress, Doctor Flates roof in progress. Supper staff roof laid plaster work in progrees.
Gyanee Block S/S completed. Wards foundation work in progress.
Mature Liabilities 80 M |
No Image |
Kabal, Swat | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 118 | 24 | 24 | 84.8 | 168.2 | 52% |
24% October - 2020 |
Work in progress.
MB- Ist Floor roof laid, Plater in progress, Doctor Flates roof in progress. Supper staff roof laid plaster work in progrees.
Gyanee Block S/S completed. Wards foundation work in progress.
Mature Liabilities 80 M |
No Image |
Kabal, Swat | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 118 | 24 | 24 | 84.8 | 168.2 | 52% |
24% September - 2020 |
Work in progress.
MB- Ist Floor roof laid, Plater in progress, Doctor Flates roof in progress. Supper staff roof laid plaster work in progrees.
Gyanee Block S/S completed. Wards foundation work in progress.
Mature Liabilities 80 M |
No Image |
Kabal, Swat | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 118 | 24 | 23.5 | 84.3 | 168.2 | 52% |
24% August - 2020 |
Work in progress.
MB- Ist Floor roof laid, Plater in progress, Doctor Flates roof in progress. Supper staff roof laid plaster work in progrees.
Gyanee Block S/S completed. Wards foundation work in progress.
Mature Liabilities 25 M |
No Image |
Kabal, Swat | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 0 | 0 | 0 | 60.8 | 168.2 | 52% |
18% July - 2020 |
Work started. |
No Image |
Kabal, Swat | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 336.4 | 336.4 | 162.974 | 223.774 | 168.2 | 52% |
64% May - 2021 |
Main Building - F/F Roof laid
Doctor Flates 06 Nos - roof laid
Supports staff Block - roof laid
Mortury Block - roof liad
Gynaee Block - Super structure in progress
Ward Building - Foundation in progress |
No Image |
THQ Hospital Kabal to Cat-C, District Swat. | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 336.4 | 336.4 | 162.974 | 223.774 | 168.2 | 52% |
64% April - 2021 |
Main Building - F/F Roof laid
Doctor Flates 06 Nos - roof laid
Supports staff Block - roof laid
Mortury Block - roof liad
Gynaee Block - Super structure in progress
Ward Building - Foundation in progress |
No Image |
THQ Hospital Kabal to Cat-C, District Swat. | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 336.4 | 336.4 | 162.974 | 223.774 | 168.2 | 52% |
64% March - 2021 |
Main Building - F/F Roof laid
Doctor Flates 06 Nos - roof laid
Supports staff Block - roof laid
Mortury Block - roof liad
Gynaee Block - Super structure in progress
Ward Building - Foundation in progress |
No Image |
THQ Hospital Kabal to Cat-C, District Swat. | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 286.4 | 286.4 | 286.4 | 118 | 178.8 | 0 | 100% |
52% February - 2021 |
Main Building - F/F Roof laid
Doctor Flates 06 Nos - roof laid
Supports staff Block - roof laid
Mortury Block - roof liad
Gynaee Block - Super structure in progress
Ward Building - Foundation in progress |
No Image |
THQ Hospital Kabal to Cat-C, District Swat. | |||||||||||||||||||
760 (OG) |
170651-Upgradation of THQ Hospital Kabal to Cat-C, District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 347 | 60.8 | 118 | 118 | 118 | 118 | 178.8 | 168.2 | 52% |
52% January - 2021 |
Work in progress.
MB- Ist Floor roof laid, Plater in progress, Doctor Flates roof in progress. Supper staff roof laid plaster work in progrees.
Gyanee Block S/S completed. Wards foundation work in progress.
Mature Liabilities 80 M |
No Image |
THQ Hospital Kabal to Cat-C, District Swat. | |||||||||||||||||||
760 (OG) |
170568-Construction of 2 Km Bypass Road in Barikot District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.9 | 0.097 | 0.001 | 0.001 | 0.0005 | 0.0005 | 0.0975 | 112.802 | 0% |
0% September - 2018 |
Land acquisition under process by district administration. Work order issued. Survey in progress. |
No Image |
PK-82, Swat | |||||||||||||||||||
760 (OG) |
170568-Construction of 2 Km Bypass Road in Barikot District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.9 | 0.097 | 0.001 | 0.001 | 0.0005 | 0 | 0.097 | 112.802 | 0% |
0% July - 2018 |
Land acquisition under process by district administration. Work order issued. |
No Image |
PK-82, Swat | |||||||||||||||||||
Pages : 1 |