Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2020, July - 2018, August - 2020, August - 2019, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 5.154 173.491 3.869 98% 88%
December - 2018
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 5.084 173.421 3.869 98% 88%
November - 2018
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 5.084 173.421 3.869 98% 88%
November - 2018
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 9.995 178.332 3.869 98% 90%
April - 2019
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 8.896 177.233 3.869 98% 90%
March - 2019
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 8.896 177.233 3.869 98% 90%
March - 2019
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 8.896 177.233 3.869 98% 90%
February - 2019
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 197.162 168.337 24.956 13.978 13.978 5.247 173.584 3.869 98% 88%
January - 2019
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress.
No Image
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 7.44695 227.58395 67.999 79% 72%
December - 2019
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 7.447 227.584 67.999 79% 72%
November - 2019
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 7.447 227.584 67.999 79% 72%
October - 2019
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 7.447 7.447 227.584 67.999 79% 72%
September - 2019
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 249.927 220.137 29.79 29.79 7.447 0 220.137 0 100% 88%
August - 2019
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 29.79 249.927 67.999 79% 79%
May - 2020
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. Demand as per revised DCE. Cannot be complted due to revision in spet 2019.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 29.79 249.927 67.999 79% 79%
April - 2020
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. Demand as per revised DCE. Cannot be complted due to revision in spet 2019.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 29.79 249.927 67.999 79% 79%
March - 2020
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. Demand as per revised DCE. Cannot be complted due to revision in spet 2019.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 29.79 249.927 67.999 79% 79%
February - 2020
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. Demand as per revised DCE. Cannot be complted due to revision in spet 2019.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat.
Kohat
30-11--1 30-11--1 - 30-11--1 - 317.926 220.137 29.79 29.79 29.79 22.31 242.447 67.999 79% 76%
January - 2020
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
No Image
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km)
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 100 100 75 1778.289 1136.301 61% 60%
December - 2020
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 100 100 75 1778.289 1136.301 61% 60%
December - 2020
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 100 25 24.132 1727.421 1136.301 61% 59%
October - 2020
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 100 25 24.132 1727.421 1136.301 61% 59%
September - 2020
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 100 0 0 1703.289 1136.301 61% 58%
August - 2020
OPD block, diagnastic paed wards, private wards, c
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 0 0 0 1703.289 1136.301 61% 58%
July - 2020
OPD block, diagnastic paed wards, private wards, c
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1708.22 100 187.22 187.22 127.408 1835.628 1131.37 62% 62%
May - 2021
01- Unit OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
 
Scope of work:
  • OPD/IPD
  • Admin Block
  • Doctor Hostel
  • Mosque
  • Cafeteria
  • General Store
  • Sarey
  • Elec: Sub Stataion
  • Dev: work
  • Package II Flate for Doctor 18 Nos
  • Flats for Oficer Grade 8-16
  • Flats for Grade 17
  • OPD
  • Cafeteria
  • Elect: Sub: Station
  • O.H.T
  • Road work
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1708.22 100 400 400 124.931 1833.151 1131.37 62% 62%
April - 2021
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1708.22 100 400 400 120.676 1828.896 1131.37 62% 62%
March - 2021
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1708.22 100 400 400 120.676 1828.896 1131.37 62% 62%
February - 2021
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III)
Mardan
30-11--1 30-11--1 - 30-11--1 - 2939.59 1703.289 100 400 400 84.095 1787.384 1136.301 61% 61%
January - 2021
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage. Package -II completed & Pc-iv submitted.
No Image
Mardan
757
(OG)
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 464.813 36.023 0.001 0.001 0.0005 0.0005 36.0235 428.789 8% 8%
September - 2018
Length 13.2 Km - work started. Earth work in progress. Summary approved for mutation of land measuring 81 kanals and 7 marla.
No Image
PK-84, Swat
757
(OG)
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 464.813 36.023 0.001 0.001 0.0005 0 36.023 428.789 8% 8%
July - 2018
Length 13.2 Km - work started. Earth work in progress.
No Image
PK-84, Swat
Pages : 1