Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 5.154 | 173.491 | 3.869 | 98% |
88% December - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 5.084 | 173.421 | 3.869 | 98% |
88% November - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 5.084 | 173.421 | 3.869 | 98% |
88% November - 2018 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 9.995 | 178.332 | 3.869 | 98% |
90% April - 2019 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 8.896 | 177.233 | 3.869 | 98% |
90% March - 2019 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 8.896 | 177.233 | 3.869 | 98% |
90% March - 2019 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 8.896 | 177.233 | 3.869 | 98% |
90% February - 2019 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.162 | 168.337 | 24.956 | 13.978 | 13.978 | 5.247 | 173.584 | 3.869 | 98% |
88% January - 2019 |
Phase-1 (9 Km) Original Scope - 9 Km completed. Finishing in progress. |
No Image |
1) Circular road 5.60 Km
2) Bannu road 1.46 Km
3) Diyal road 1.76 Km
4) Circular road to old Prova Chungi infront of Bahu Petroleum 0.17 Km | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 7.44695 | 227.58395 | 67.999 | 79% |
72% December - 2019 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 7.447 | 227.584 | 67.999 | 79% |
72% November - 2019 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 7.447 | 227.584 | 67.999 | 79% |
72% October - 2019 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 7.447 | 7.447 | 227.584 | 67.999 | 79% |
72% September - 2019 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.927 | 220.137 | 29.79 | 29.79 | 7.447 | 0 | 220.137 | 0 | 100% |
88% August - 2019 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 29.79 | 249.927 | 67.999 | 79% |
79% May - 2020 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
Demand as per revised DCE.
Cannot be complted due to revision in spet 2019. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 29.79 | 249.927 | 67.999 | 79% |
79% April - 2020 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
Demand as per revised DCE.
Cannot be complted due to revision in spet 2019. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 29.79 | 249.927 | 67.999 | 79% |
79% March - 2020 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
Demand as per revised DCE.
Cannot be complted due to revision in spet 2019. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 29.79 | 249.927 | 67.999 | 79% |
79% February - 2020 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued.
Demand as per revised DCE.
Cannot be complted due to revision in spet 2019. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 317.926 | 220.137 | 29.79 | 29.79 | 29.79 | 22.31 | 242.447 | 67.999 | 79% |
76% January - 2020 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Balance work - work order issued. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 100 | 100 | 75 | 1778.289 | 1136.301 | 61% |
60% December - 2020 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 100 | 100 | 75 | 1778.289 | 1136.301 | 61% |
60% December - 2020 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 100 | 25 | 24.132 | 1727.421 | 1136.301 | 61% |
59% October - 2020 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 100 | 25 | 24.132 | 1727.421 | 1136.301 | 61% |
59% September - 2020 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 100 | 0 | 0 | 1703.289 | 1136.301 | 61% |
58% August - 2020 |
OPD block, diagnastic paed wards, private wards, c |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 0 | 0 | 0 | 1703.289 | 1136.301 | 61% |
58% July - 2020 |
OPD block, diagnastic paed wards, private wards, c |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1708.22 | 100 | 187.22 | 187.22 | 127.408 | 1835.628 | 1131.37 | 62% |
62% May - 2021 |
01- Unit
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan
Scope of work:
| |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1708.22 | 100 | 400 | 400 | 124.931 | 1833.151 | 1131.37 | 62% |
62% April - 2021 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1708.22 | 100 | 400 | 400 | 120.676 | 1828.896 | 1131.37 | 62% |
62% March - 2021 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1708.22 | 100 | 400 | 400 | 120.676 | 1828.896 | 1131.37 | 62% |
62% February - 2021 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
120333-Improvement & Standardization of DHQ Hospital, Mardan. (Phase-III) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2939.59 | 1703.289 | 100 | 400 | 400 | 84.095 | 1787.384 | 1136.301 | 61% |
61% January - 2021 |
OPD block, Admn Block, Doctors Hostel, Mosque, Cafeteria, General Store diagnastic paed wards private wards, in finishing stage.
Package -II completed & Pc-iv submitted. |
No Image |
Mardan | |||||||||||||||||||
757 (OG) |
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 464.813 | 36.023 | 0.001 | 0.001 | 0.0005 | 0.0005 | 36.0235 | 428.789 | 8% |
8% September - 2018 |
Length 13.2 Km - work started. Earth work in progress. Summary approved for mutation of land measuring 81 kanals and 7 marla. |
No Image |
PK-84, Swat | |||||||||||||||||||
757 (OG) |
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 464.813 | 36.023 | 0.001 | 0.001 | 0.0005 | 0 | 36.023 | 428.789 | 8% |
8% July - 2018 |
Length 13.2 Km - work started. Earth work in progress. |
No Image |
PK-84, Swat | |||||||||||||||||||
Pages : 1 |