Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.798 | 41.273 | 6.048 | 50.458 | 0.72 | 99% |
41% December - 2018 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit.Stay order issued |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.798 | 41.273 | 6 | 50.41 | 0.72 | 99% |
41% November - 2018 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.798 | 41.273 | 6 | 50.41 | 0.72 | 99% |
41% November - 2018 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.7984 | 73.7984 | 31.209 | 75.619 | 0.72 | 99% |
62% April - 2019 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.7984 | 73.7984 | 19.863 | 64.273 | 0.72 | 99% |
53% March - 2019 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.7984 | 73.7984 | 19.863 | 64.273 | 0.72 | 99% |
53% March - 2019 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.7984 | 73.7984 | 13.045 | 57.455 | 0.72 | 99% |
47% February - 2019 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 122.181 | 44.41 | 77.051 | 73.798 | 41.273 | 8.271 | 52.681 | 0.72 | 99% |
43% January - 2019 |
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur). Work in progress on 3 unit.Stay order vacated. |
No Image |
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
5) Restoration work Right Guide Bank (washed away) from RD-1350 to 1900 i/c cost factor (additional work) | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 4.68125 | 4.68125 | 1.25 | 25.751 | 87.918 | 25% |
22% December - 2019 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -tender approval process. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 5 | 1.25 | 1.25 | 25.751 | 87.918 | 25% |
22% November - 2019 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -tender approval process. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 5 | 1.25 | 1.25 | 25.751 | 87.918 | 25% |
22% October - 2019 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -tender approval process. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 5 | 1.25 | 1.25 | 25.751 | 87.918 | 25% |
22% September - 2019 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -tender approva in progress. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 5 | 1.25 | 0 | 24.501 | 87.918 | 25% |
21% August - 2019 |
Length 5 Km- embankment and sub base in progress. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 4.68125 | 4.68125 | 1.25 | 25.751 | 87.918 | 25% |
22% May - 2020 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -Work Order issued.
Consultant Hiring in progress. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 4.68125 | 4.68125 | 1.25 | 25.751 | 87.918 | 25% |
22% April - 2020 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -Work Order issued.
Consultant Hiring in progress. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 4.68125 | 4.68125 | 1.25 | 25.751 | 87.918 | 25% |
22% March - 2020 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -Work Order issued.
Consultant Hiring in progress. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 4.68125 | 4.68125 | 1.25 | 25.751 | 87.918 | 25% |
22% February - 2020 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -Work Order issued.
Consultant Hiring in progress. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 117.419 | 24.501 | 5 | 4.68125 | 4.68125 | 1.25 | 25.751 | 87.918 | 25% |
22% January - 2020 |
Length 5 Km- KM 5 WBM in progress.
KM 1-4 -tender approval process. |
No Image |
Karak | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 50 | 23 | 21.12 | 761.168 | 908.237 | 47% |
45% December - 2020 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 50 | 23 | 21.12 | 761.168 | 908.237 | 47% |
45% December - 2020 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 50 | 13 | 0 | 740.048 | 908.237 | 47% |
44% October - 2020 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 50 | 13 | 0 | 740.048 | 908.237 | 47% |
44% September - 2020 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 50 | 0 | 0 | 740.048 | 908.237 | 47% |
44% August - 2020 |
Main building, - In progress
nurses hostel & doc |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 0 | 0 | 0 | 740.048 | 908.237 | 47% |
44% July - 2020 |
Main building, - In progress
nurses hostel & doc |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 703.699 | 50 | 270 | 270 | 193.341 | 897.04 | 944.586 | 44% |
53% May - 2021 |
01- Unit
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan
Scope of work:
| |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 703.699 | 50 | 243 | 243 | 187.964 | 891.663 | 944.586 | 44% |
53% April - 2021 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 703.699 | 50 | 243 | 243 | 163.884 | 867.583 | 944.586 | 44% |
51% March - 2021 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 703.699 | 50 | 243 | 243 | 163.884 | 867.583 | 944.586 | 44% |
51% February - 2021 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
100183-Establishment of Shaheed Mohtarma Benazir Bhutto Children Hospital in Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1698.285 | 740.048 | 50 | 243 | 243 | 23 | 763.048 | 908.237 | 47% |
45% January - 2021 |
Main building, - In progress on all units.
VRF & lift Work work order issued.
2 Nos Hostel h/o, |
No Image |
PK-24 Mardan | |||||||||||||||||||
756 (OG) |
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 231.52 | 117.677 | 0.001 | 0.001 | 0.0005 | 0.0005 | 117.6775 | 113.842 | 51% |
51% September - 2018 |
Length 16.2 Km (5 units) - Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed. |
No Image |
PK 86, Swat | |||||||||||||||||||
756 (OG) |
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 231.52 | 117.677 | 0.001 | 0.001 | 0.0005 | 0 | 117.677 | 113.842 | 51% |
51% July - 2018 |
Length 16.2 Km (5 units) - Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed. |
No Image |
PK 86, Swat | |||||||||||||||||||