Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 37.321803 | 361.129803 | 16.41 | 96% |
93% December - 2019 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 35.539 | 359.347 | 16.41 | 96% |
92% November - 2019 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed.
P-II |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 27.616 | 351.424 | 16.41 | 96% |
90% October - 2019 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed.
P-II |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 12.5 | 12.5 | 336.308 | 16.41 | 96% |
86% September - 2019 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 12.5 | 12.5 | 336.308 | 16.41 | 96% |
86% August - 2019 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 44.292 | 368.1 | 16.41 | 96% |
94% May - 2020 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 44.292 | 368.1 | 16.41 | 96% |
94% April - 2020 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 44.292 | 368.1 | 16.41 | 96% |
94% March - 2020 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 44.292 | 368.1 | 16.41 | 96% |
94% February - 2020 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 323.808 | 50 | 50 | 50 | 37.321803 | 361.129803 | 16.41 | 96% |
93% January - 2020 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. |
No Image |
Karak | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 0.001 | 0 | 0 | 485.317 | 459.319 | 51% |
51% December - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress.
MB plastering in progress. C/Block S/Stucture in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 0.001 | 0 | 0 | 485.317 | 459.319 | 51% |
51% December - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress.
MB plastering in progress. C/Block S/Stucture in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 0.001 | 0 | 0 | 485.317 | 459.319 | 51% |
51% October - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress.
MB plastering in progress. C/Block S/Stucture in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 507.896 | 0.001 | 0.001 | 0 | 0 | 507.896 | 0 | 100% |
100% September - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress.
MB plastering in progress. C/Block S/Stucture in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 507.896 | 0.001 | 0.001 | 0 | 0 | 507.896 | 0 | 100% |
100% August - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 507.896 | 0.001 | 0 | 0 | 0 | 507.896 | 0 | 100% |
100% July - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 10.001 | 10.001 | 0 | 485.317 | 459.319 | 51% |
51% May - 2021 |
1. G/Floor A+B+D+E Blocks =Finishing in progress
2. F/Floor A+B+D+E Blocker = Plastering in progress.
3. S/Floor= B-Block = Plastering in progress.
4. Main building = Plastering in progress.
5. C=Block S/Structure in progress.
6. VRF L/C opened Manufacturing started |
No Image |
DHQ Hospital Swabi
Scope of work:
| |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 100 | 100 | 0 | 485.317 | 459.319 | 51% |
51% April - 2021 |
1. G/Floor A+B+D+E Blocks =Finishing in progress
2. F/Floor A+B+D+E Blocker = Plastering in progress.
3. S/Floor= B-Block = Plastering in progress.
4. Main building = Plastering in progress.
5. C=Block S/Structure in progress.
6. VRF L/C opened Manufacturing started |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 100 | 100 | 0 | 485.317 | 459.319 | 51% |
51% March - 2021 |
1. G/Floor A+B+D+E Blocks =Finishing in progress
2. F/Floor A+B+D+E Blocker = Plastering in progress.
3. S/Floor= B-Block = Plastering in progress.
4. Main building = Plastering in progress.
5. C=Block S/Structure in progress.
6. VRF L/C opened Manufacturing started |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 100 | 100 | 0 | 485.317 | 459.319 | 51% |
51% February - 2021 |
1. G/Floor A+B+D+E Blocks =Finishing in progress
2. F/Floor A+B+D+E Blocker = Plastering in progress.
3. S/Floor= B-Block = Plastering in progress.
4. Main building = Plastering in progress.
5. C=Block S/Structure in progress.
6. VRF L/C opened Manufacturing started |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 944.637 | 485.317 | 0.001 | 0.001 | 0 | 0 | 485.317 | 459.319 | 51% |
51% January - 2021 |
GF/FF - A, B, D, E blocks - finishing in progress.
MB plastering in progress. C/Block S/Stucture in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
753 (OG) |
150812-Construction of road from Nusrat Chowk to Langarr Chowk, Shamozai Jabbagai road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 74.348 | 5 | 5 | 2.5 | 1.824 | 76.172 | 120.652 | 40% |
38% September - 2018 |
Length 9 Km - 4.7 Km BT completed. WBM, structure work in progress in remaining road. |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
753 (OG) |
150812-Construction of road from Nusrat Chowk to Langarr Chowk, Shamozai Jabbagai road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 74.348 | 5 | 5 | 2.5 | 0 | 74.348 | 120.652 | 40% |
37% July - 2018 |
Length 9 Km - 4.7 Km BT completed. WBM, structure work in progress in remaining road. |
No Image |
1) Nusrat Chowk to Langar Chowk (7.37 Km)
2) Shamozai Jabbagai road (1.86 Km) | |||||||||||||||||||
Pages : 1 |