Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, February - 2020, February - 2021, March - 2020, March - 2021, April - 2020, April - 2021, May - 2020, May - 2021, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 14.04375 14.04375 3.299484 53.703484 84.696 44% 36%
December - 2019
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 15 3.75 2.572 52.976 84.696 44% 35%
November - 2019
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 15 3.75 2.157 52.561 84.696 44% 35%
October - 2019
Delay due to stay order by court (vacated). Work in progress on 21 units. Revised DCE suibmitted to P&D. Pre PDWP held.
No Image
Bannu
748
(OG)
151077-Construction/ Rehabilitation of road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 15 3.75 0.32 50.724 84.696 44% 34%
September - 2019
Delay due to stay order by court (vacated). Work in progress on 21 units. Revised DCE suibmitted to P&D. Pre PDWp held.
No Image
Bannu
748
(OG)
151077-Construction/ Rehabilitation of road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 15 3.75 0 50.404 84.696 44% 34%
August - 2019
Delay due to stay order by court (vacated). Work in progress on 21 units.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 33.379 33.379 7.714 58.118 84.696 44% 39%
May - 2020
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 19.748 14.44 6.405 56.809 84.696 44% 38%
April - 2020
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 19.748 14.44 6.405 56.809 84.696 44% 38%
March - 2020
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 19.748 14.44 6.405 56.809 84.696 44% 38%
February - 2020
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 150.1 50.404 15 14.04375 14.04375 3.594 53.998 84.696 44% 36%
January - 2020
6/15 KM GSB completed. 7/21 work in progress.
No Image
Bannu
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
MPD-2
30-11--1 30-11--1 - 30-11--1 - 175.53 144.344 34.185 27.389 27.389 19.925 164.269 0 100% 94%
May - 2021
02 Blocks Block 1 Completed & H/O Block 2 93% Completed
No Image
Block 1  Hayatabad Peshawar
Block 2  Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
 
Scope of work:
  • Block- I
  • Basement + 3 story Building
  • 2-Nos Gyms wards
  • Staff room
  • OTS = 03 Nos
  • Laboratory Library
  • Class room = 04 Nos
  • Tennis Court
  • Block- II
  • Orthopedic
  • Wards 12 Nos
  • Lavatory & Laundary
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
MPD-2
30-11--1 30-11--1 - 30-11--1 - 175.53 0 34.185 31.203 31.203 19.925 0 0
April - 2021
02 Blocks Block 1 Completed & H/O Block 2 Finishing stage
No Image
Block 1  Hayatabad Peshawar
Block 2  Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
 
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 34.185 31.203 14.75 156.095 0 100% 89%
December - 2020
Finishing in progress. Revised TS submitted
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 34.185 31.203 14.75 156.095 0 100% 89%
December - 2020
Finishing in progress. Revised TS submitted
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 34.185 17 14.751 156.096 0 100% 89%
October - 2020
finishing in progress.
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 34.185 17 8.84 150.185 0 100% 86%
September - 2020
Block-1 completed & H/O Block-2 Structure work completed fair facing in progress. Lift L.C opened. HVAc in progress.
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 34.185 17 0 141.345 0 100% 81%
August - 2020
Block-1 completed & H/O Block-2 Structure work completed fair facing in progress. Lift L.C opened.
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 0 0 0 141.345 0 100% 81%
July - 2020
Block-1 completed, Block-2 Plastering work under progress.
No Image
Hayatabad Peshawar
Main Buildin
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 0 34.185 31.203 31.203 19.925 0 0
March - 2021
02 Blocks Block 1 Completed & H/O Block 2 Finishing stage
No Image
Block 1  Hayatabad Peshawar
Block 2  Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
 
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 0 34.185 31.203 31.203 19.925 0 0
February - 2021
02 Blocks Block 1 Completed & H/O Block 2 Finishing stage
No Image
Block 1  Hayatabad Peshawar
Block 2  Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
 
748
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 141.345 34.185 34.185 31.203 14.75 156.095 0 100% 89%
January - 2021
Finishing in progress. Revised TS submitted
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
748
(OG)
140965-F/S, Design & improvement, Widening & BT of Mangwaltan to Toha Road (6.5 Km), District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 135.93 78.302 0.001 0.001 0.0005 0.0005 78.3025 57.627 58% 58%
September - 2018
Length 6.5 Km - earth work 100% completed, structure work, RW, in progress, sub base 2 Km completed.
No Image
PK-86, Swat
748
(OG)
140965-F/S, Design & improvement, Widening & BT of Mangwaltan to Toha Road (6.5 Km), District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 135.93 78.302 0.001 0.001 0.0005 0 78.302 57.627 58% 58%
July - 2018
Length 6.5 Km - earth work 100% completed, structure work, RW, in progress, sub base 2 Km completed.
No Image
PK-86, Swat