Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 14.04375 | 14.04375 | 3.299484 | 53.703484 | 84.696 | 44% |
36% December - 2019 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 15 | 3.75 | 2.572 | 52.976 | 84.696 | 44% |
35% November - 2019 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 15 | 3.75 | 2.157 | 52.561 | 84.696 | 44% |
35% October - 2019 |
Delay due to stay order by court (vacated). Work in progress on 21 units. Revised DCE suibmitted to P&D. Pre PDWP held. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction/ Rehabilitation of road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 15 | 3.75 | 0.32 | 50.724 | 84.696 | 44% |
34% September - 2019 |
Delay due to stay order by court (vacated). Work in progress on 21 units. Revised DCE suibmitted to P&D. Pre PDWp held. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction/ Rehabilitation of road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 15 | 3.75 | 0 | 50.404 | 84.696 | 44% |
34% August - 2019 |
Delay due to stay order by court (vacated). Work in progress on 21 units. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 33.379 | 33.379 | 7.714 | 58.118 | 84.696 | 44% |
39% May - 2020 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 19.748 | 14.44 | 6.405 | 56.809 | 84.696 | 44% |
38% April - 2020 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 19.748 | 14.44 | 6.405 | 56.809 | 84.696 | 44% |
38% March - 2020 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 19.748 | 14.44 | 6.405 | 56.809 | 84.696 | 44% |
38% February - 2020 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
151077-Construction / BT / Reconstruction / Rehabilitation of Road UC Nar Jaffar, UC Kakki-I, UC Bharat, UC Koser Fath Khel, UC Mandan, UC Shamshi Khel and UC Mira Khel, District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150.1 | 50.404 | 15 | 14.04375 | 14.04375 | 3.594 | 53.998 | 84.696 | 44% |
36% January - 2020 |
6/15 KM GSB completed. 7/21 work in progress. |
No Image |
Bannu | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 144.344 | 34.185 | 27.389 | 27.389 | 19.925 | 164.269 | 0 | 100% |
94% May - 2021 |
02 Blocks
Block 1 Completed & H/O
Block 2 93% Completed |
No Image |
Block 1 Hayatabad Peshawar
Block 2 Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Scope of work:
| |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 0 | 34.185 | 31.203 | 31.203 | 19.925 | 0 | 0 |
April - 2021 |
02 Blocks
Block 1 Completed & H/O
Block 2 Finishing stage |
No Image | |
Block 1 Hayatabad Peshawar
Block 2 Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
| |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 34.185 | 31.203 | 14.75 | 156.095 | 0 | 100% |
89% December - 2020 |
Finishing in progress.
Revised TS submitted |
No Image |
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope) | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 34.185 | 31.203 | 14.75 | 156.095 | 0 | 100% |
89% December - 2020 |
Finishing in progress.
Revised TS submitted |
No Image |
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope) | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 34.185 | 17 | 14.751 | 156.096 | 0 | 100% |
89% October - 2020 |
finishing in progress. |
No Image |
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope) | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 34.185 | 17 | 8.84 | 150.185 | 0 | 100% |
86% September - 2020 |
Block-1 completed & H/O
Block-2 Structure work completed fair facing in progress.
Lift L.C opened.
HVAc in progress. |
No Image |
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope) | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 34.185 | 17 | 0 | 141.345 | 0 | 100% |
81% August - 2020 |
Block-1 completed & H/O
Block-2 Structure work completed fair facing in progress.
Lift L.C opened. |
No Image |
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope) | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 0 | 0 | 0 | 141.345 | 0 | 100% |
81% July - 2020 |
Block-1 completed,
Block-2 Plastering work under progress. |
No Image |
Hayatabad Peshawar
Main Buildin | |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 0 | 34.185 | 31.203 | 31.203 | 19.925 | 0 | 0 |
March - 2021 |
02 Blocks
Block 1 Completed & H/O
Block 2 Finishing stage |
No Image | |
Block 1 Hayatabad Peshawar
Block 2 Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
| |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 0 | 34.185 | 31.203 | 31.203 | 19.925 | 0 | 0 |
February - 2021 |
02 Blocks
Block 1 Completed & H/O
Block 2 Finishing stage |
No Image | |
Block 1 Hayatabad Peshawar
Block 2 Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
| |||||||||||||||||||
748 (OG) |
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.53 | 141.345 | 34.185 | 34.185 | 31.203 | 14.75 | 156.095 | 0 | 100% |
89% January - 2021 |
Finishing in progress.
Revised TS submitted |
No Image |
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope) | |||||||||||||||||||
748 (OG) |
140965-F/S, Design & improvement, Widening & BT of Mangwaltan to Toha Road (6.5 Km), District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 135.93 | 78.302 | 0.001 | 0.001 | 0.0005 | 0.0005 | 78.3025 | 57.627 | 58% |
58% September - 2018 |
Length 6.5 Km - earth work 100% completed, structure work, RW, in progress, sub base 2 Km completed. |
No Image |
PK-86, Swat | |||||||||||||||||||
748 (OG) |
140965-F/S, Design & improvement, Widening & BT of Mangwaltan to Toha Road (6.5 Km), District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 135.93 | 78.302 | 0.001 | 0.001 | 0.0005 | 0 | 78.302 | 57.627 | 58% |
58% July - 2018 |
Length 6.5 Km - earth work 100% completed, structure work, RW, in progress, sub base 2 Km completed. |
No Image |
PK-86, Swat | |||||||||||||||||||
Pages : 1 |