Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
Tender opened on 12/07/2018. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
Tender opened on 12/07/2018. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
Tender opened on 12/07/2018. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0.987 | 0.987 | 0.987 | 0.881 | 0.881 | 0 | - |
- April - 2019 |
Work order issued. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0.987 | 0.987 | 0.987 | 0.881 | 0.881 | 0 | - |
- March - 2019 |
Work order issued. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0.987 | 0.987 | 0.987 | 0.881 | 0.881 | 0 | - |
- March - 2019 |
Work order issued. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0.987 | 0.987 | 0.987 | 0.881 | 0.881 | 0 | - |
- February - 2019 |
Work order issued. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0.987 | 0.987 | 0.987 | 0.56 | 0.56 | 0 | - |
- January - 2019 |
Work order issued. |
No Image |
Abbottabad | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.663 | 0.663 | 0 | 100% |
67% December - 2018 |
Flooring, ceiling completed, electrification in progress. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 14.185016 | 51.072016 | 33.725 | 63% |
56% December - 2019 |
Length 5 Km - TST 1.5 Km completed. TST 3.847Km completed.Tender for Rs.0.926 KM called on 10/12/2019. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0 | 0 | 0 | 0 | 0 | 0.987 | - |
- November - 2018 |
Work order issued. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0 | 0 | 0 | 0 | 0 | 0.987 | - |
- November - 2018 |
Work order issued. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 14.185 | 51.072 | 33.725 | 63% |
56% November - 2019 |
Length 5 Km - TST 1.5 Km completed. TST 3.847Km completed.Tender for Rs.0.926 KM called on 10/12/2019. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 14.185 | 51.072 | 33.725 | 63% |
56% October - 2019 |
Length 5 Km - TST 1.5 Km completed. Remaining 3.5 Km ready for TST. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 5 | 5 | 41.887 | 33.725 | 63% |
46% September - 2019 |
Length 5 Km - TST 1.5 Km completed. Remaining 3.5 Km ready for TST. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 5 | 0 | 36.887 | 33.725 | 63% |
41% August - 2019 |
Length 5 Km - TST 1.5 Km completed. Remaining 3.5 Km ready for TST. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 17.621 | 54.508 | 33.725 | 63% |
60% May - 2020 |
Length 5 Km -. TST 3.847Km completed.
\Work prder for 0.925 km issued. Work started. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.663 | 0.663 | 0 | 100% |
67% April - 2019 |
Work in progress. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 17.621 | 54.508 | 33.725 | 63% |
60% April - 2020 |
Length 5 Km -. TST 3.847Km completed.
\Work prder for 0.925 km issued. Work started. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.663 | 0.663 | 0 | 100% |
67% March - 2019 |
Work in progress. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.663 | 0.663 | 0 | 100% |
67% March - 2019 |
Work in progress. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 17.621 | 54.508 | 33.725 | 63% |
60% March - 2020 |
Length 5 Km -. TST 3.847Km completed.
\Work prder for 0.925 km issued. Work started. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.663 | 0.663 | 0 | 100% |
67% February - 2019 |
Work in progress. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 17.621 | 54.508 | 33.725 | 63% |
60% February - 2020 |
Length 5 Km -. TST 3.847Km completed.
\Work prder for 0.925 km issued. Work started. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.663 | 0.663 | 0 | 100% |
67% January - 2019 |
Work in progress. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
141018-F/S,design and Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.612 | 36.887 | 20 | 20 | 20 | 14.185016 | 51.072016 | 33.725 | 63% |
56% January - 2020 |
Length 5 Km -. TST 3.847Km completed.
\Work prder for 0.925 km issued. Work started. |
No Image |
Bannu | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0 | 0 | 0 | 100% |
- December - 2018 |
Finishing in progress. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 1 | 1 | 47.326 | 177.493 | 21% |
21% December - 2020 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed.
Demand Rs. 80 M
TS under preparation |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 1 | 1 | 47.326 | 177.493 | 21% |
21% December - 2020 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed.
Demand Rs. 80 M
TS under preparation |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0 | 0 | 0 | 0 | 0 | 0.987 | - |
- November - 2018 |
Work started. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0 | 0 | 0 | 0 | 0 | 0.987 | - |
- November - 2018 |
Work started. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 1 | 0.324 | 46.65 | 177.493 | 21% |
21% October - 2020 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 0 | 0 | 46.326 | 177.493 | 21% |
21% September - 2020 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 0 | 0 | 46.326 | 177.493 | 21% |
21% August - 2020 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 0 | 0 | 0 | 46.326 | 177.493 | 21% |
21% July - 2020 |
Type -IV qtr G/F column in progress.
Doctor Host |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 26 | 31 | 31 | 23.176 | 69.502 | 152.493 | 32% |
31% May - 2021 |
01- Unit
PC-II: 12.500, dt: 07-10-16
1. MB Raft Completed
2. Type - IV & VI roof laid
3. Doctor Hostel roofing in progress
Demand Rs. 80 M
TS under preparation |
No Image |
| |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.522 | 0.522 | 0 | 100% |
53% April - 2019 |
Completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 26 | 31 | 31 | 23.176 | 69.502 | 152.493 | 32% |
31% April - 2021 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed.
Demand Rs. 80 M
TS under preparation |
No Image |
Civil Hospital Shakardara to Cat-D Hospital, Kohat. | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.522 | 0.522 | 0 | 100% |
53% March - 2019 |
Completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.522 | 0.522 | 0 | 100% |
53% March - 2019 |
Completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 1 | 1 | 47.326 | 177.493 | 21% |
21% March - 2021 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed.
Demand Rs. 80 M
TS under preparation |
No Image |
Civil Hospital Shakardara to Cat-D Hospital, Kohat. | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.522 | 0.522 | 0 | 100% |
53% February - 2019 |
Completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 1 | 1 | 47.326 | 177.493 | 21% |
21% February - 2021 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed.
Demand Rs. 80 M
TS under preparation |
No Image |
Civil Hospital Shakardara to Cat-D Hospital, Kohat. | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.987 | 0 | 0.987 | 0.987 | 0.987 | 0.522 | 0.522 | 0 | 100% |
53% January - 2019 |
Completed. |
No Image |
Kohat | |||||||||||||||||||
745 (OG) |
160233-Upgradation of Civil Hospital Shakardara to Cat-D Hospital, Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.819 | 46.326 | 1 | 1 | 1 | 1 | 47.326 | 177.493 | 21% |
21% January - 2021 |
Type -IV qtr G/F column in progress.
Doctor Hostel plinth beam completed.
Demand Rs. 80 M
TS under preparation |
No Image |
Civil Hospital Shakardara to Cat-D Hospital, Kohat. | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.018 | 10.95 | 0 | 0 | 0 | 0 | 10.95 | 14.068 | - |
44% December - 2018 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.018 | 10.95 | 0 | 0 | 0 | 0 | 10.95 | 14.068 | - |
44% November - 2018 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.018 | 10.95 | 0 | 0 | 0 | 0 | 10.95 | 14.068 | - |
44% November - 2018 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.018 | 10.95 | 0 | 0 | 0 | 0 | 10.95 | 14.068 | - |
44% April - 2019 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
745 (OG) |
140306-Revamping of PEOC & MIS Section and Development of MIS for PDMA. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.018 | 10.95 | 0 | 0 | 0 | 0 | 10.95 | 14.068 | - |
44% March - 2019 |
Completed. |
No Image |
Peshawar | |||||||||||||||||||
Pages : 1 2 |