Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2019, February - 2019, February - 2020, February - 2021, March - 2019, March - 2020, March - 2021, April - 2019, April - 2020, April - 2021, May - 2020, May - 2021, July - 2020, July - 2018, August - 2019, August - 2020, September - 2019, September - 2020, September - 2018, October - 2019, October - 2020, November - 2019, November - 2018, December - 2018, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 9.3625 9.3625 0 40.85 169.15 23% 19%
December - 2019
Structure work 600 rft completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 90 0 0 0 0 100% -
December - 2020
Tendering in progress.
No Image
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 90 0 0 0 0 100% -
December - 2020
Tendering in progress.
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 10 2.5 0 40.85 169.15 23% 19%
November - 2019
Structure work 600 rft completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 10 2.5 0 40.85 169.15 23% 19%
October - 2019
Structure work 600 rft completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 90 0 0 0 0 100% -
October - 2020
Procuremnet in progress.
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 10 2.5 0 40.85 169.15 23% 19%
September - 2019
Structure work 600 rft completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 90 0 0 0 0 100% -
September - 2020
Procuremnet in progress.
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 10 2.5 0 40.85 169.15 23% 19%
August - 2019
Structure work 600 rft completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 90 0 0 0 0 100% -
August - 2020
Procuremnet in progress.
No Image
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 0 0 0 0 0 100% -
July - 2020
Approved.
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 9.101 9.101 8.839 49.689 169.15 23% 23%
May - 2020
Length 05 KM - 02 KM Sub Base complted . 5500/6000 m retaining wall completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 61.094 61.094 36.294 36.294 0 100% 40%
May - 2021
01-Unit Main Building Roof laid.
No Image
Scope of work:
 
  • Main Building
  • 1st Floor
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 9.3625 9.3625 7.7 48.55 169.15 23% 22%
April - 2020
Length 05 KM - 02 KM Sub Base complted . 5500/6000 m retaining wall completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 75 75 27.2 27.2 0 100% 30%
April - 2021
M/B Excavatin is in progress
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 9.3625 9.3625 7.7 48.55 169.15 23% 22%
March - 2020
Length 05 KM - 02 KM Sub Base complted . 5500/6000 m retaining wall completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 45 45 14.782 14.782 0 100% 16%
March - 2021
M/B Excavatin is in progress
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 9.3625 9.3625 7.7 48.55 169.15 23% 22%
February - 2020
Length 05 KM - 02 KM Sub Base complted . 5500/6000 m retaining wall completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 45 45 14.782 14.782 0 100% 16%
February - 2021
M/B Excavatin is in progress
No Image
744
(OG)
140886-F/S, Design & Construction of 05 Km road from Bannu City to Kakki via Mundan, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 220 40.85 10 9.3625 9.3625 3 43.85 169.15 23% 20%
January - 2020
Length 05 KM - 02 KM Sub Base complted . 5500/6000 m retaining wall completed. Removal of encroachment in progress.
No Image
5 Km Bannu
744
(OG)
180618-Improvement and rehabilitation of Women & Children Hospital, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 90 0 90 45 45 0 0 0 100% -
January - 2021
work order issued
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
December - 2018
Completed (5 units).
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
November - 2018
Out of 5 unit, 1 completed, 3 in progress, 1 court case.
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
November - 2018
Out of 5 unit, 1 completed, 3 in progress, 1 court case.
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
April - 2019
Completed (5 units).
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
March - 2019
Completed (5 units).
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
March - 2019
Completed (5 units).
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
February - 2019
Completed (5 units).
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
30-11--1 30-11--1 - 30-11--1 - 140.049 129.388 0 0 0 0 129.388 10.661 - 92%
January - 2019
Completed (5 units).
No Image
1) Station No.11 Mardan Medical Complex Mardan
2) Station No.22 Town Hall Mardan
3) Station No.33 Malakand Bypass Road Mardan
4) Station No.44 Swabi Road Mardan
5) Station No.55 Tehsil Building at Takhat Bhai
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 268.214 192.916 0 0 0 0 192.916 75.298 - 72%
December - 2018
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years. Client deptt has requested to cap the project on 04/01/2017.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 268.214 192.916 0 0 0 0 192.916 75.298 - 72%
November - 2018
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years. Client deptt has requested to cap the project on 04/01/2017.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 268.214 192.916 0 0 0 0 192.916 75.298 - 72%
November - 2018
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years. Client deptt has requested to cap the project on 04/01/2017.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 307.565 192.916 39.351 39.351 39.351 0.09 193.006 75.298 76% 63%
April - 2019
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 307.565 192.916 0 0 0 0 192.916 114.649 - 63%
March - 2019
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 307.565 192.916 0 0 0 0 192.916 114.649 - 63%
March - 2019
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 307.565 192.916 0 0 0 0 192.916 114.649 - 63%
February - 2019
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 307.565 192.916 0 0 0 0 192.916 114.649 - 63%
January - 2019
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years. Client deptt has requested to cap the project on 04/01/2017.
No Image
1) No.1 Tariq Road Cantt PK-04
2) Civil Defence office GT road PK-01 (near Lahore Bus Terminal)
3) Kohati Gate PK-03
4) Setalite Hospital Kohat road
5) Unversity Town shifted to KTH PK-05
6) Hayatbad Medical Complex PK-05
7) Eid Gah Charsadda road PK-01
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
December - 2018
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
November - 2018
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
November - 2018
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
April - 2019
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
March - 2019
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
March - 2019
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
February - 2019
No Image
744
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
January - 2019
No Image
744
(OG)
170627-Rehabilitation of Karora to Ajmir Road (12Km) District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 150 5.311 0.001 0.001 0.0005 0 5.311 144.688 4% 4%
September - 2018
Earth work, structure work in progress.
No Image
Karora to Ajmir road (12 Km) Shangla
744
(OG)
170627-Rehabilitation of Karora to Ajmir Road (12Km) District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 150 5.311 0.001 0.001 0.0005 0 5.311 144.688 4% 4%
July - 2018
Earth work, structure work in progress.
No Image
Karora to Ajmir road (12 Km) Shangla
Pages : 1