Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 3 0 86.2 86.2 0 0 0 0 100% -
December - 2018
LOA issued to consultant on 03/03/2015. PC-I/DCE for Rs.57.999 m re-submitted to Secretary R&R on 28/01/2016. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 3 0 86.2 86.2 0 0 0 0 100% -
November - 2018
LOA issued to consultant on 03/03/2015. PC-I/DCE for Rs.57.999 m re-submitted to Secretary R&R on 28/01/2016. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 3 0 86.2 86.2 0 0 0 0 100% -
November - 2018
LOA issued to consultant on 03/03/2015. PC-I/DCE for Rs.57.999 m re-submitted to Secretary R&R on 28/01/2016. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 44.355 0 86.2 86.2 0 0 0 0 100% -
April - 2019
Approved. LOA issued to consultant on 03/03/2015. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 44.355 0 86.2 86.2 0 0 0 0 100% -
March - 2019
Approved. LOA issued to consultant on 03/03/2015. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 44.355 0 86.2 86.2 0 0 0 0 100% -
March - 2019
Approved. LOA issued to consultant on 03/03/2015. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 44.355 0 86.2 86.2 0 0 0 0 100% -
February - 2019
Approved. LOA issued to consultant on 03/03/2015. Land not available.
No Image
Abbottabad
742
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 44.355 0 86.2 86.2 0 0 0 0 100% -
January - 2019
Approved. LOA issued to consultant on 03/03/2015. Land not available.
No Image
Abbottabad
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 8.145014 49.194014 98.951 34% 33%
December - 2019
Length 6 Km - earth work, sub base in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 55 55 55 50.489 65.059 301.293 19% 18%
December - 2020
Reaft founation completed. Column in progresss
No Image
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 55 55 55 50.489 65.059 301.293 19% 18%
December - 2020
Reaft founation completed. Column in progresss
No Image
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 2.5 43.549 98.951 34% 29%
November - 2019
Length 6 Km - earth work, sub base in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 2.5 43.549 98.951 34% 29%
October - 2019
Length 6 Km - earth work, sub base in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 55 55 55 20 34.57 301.293 19% 9%
October - 2020
Reaft founation completed. Column in progresss
No Image
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 2.5 0.433 41.482 98.951 34% 28%
September - 2019
Length 6 Km - earth work, sub base in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 0 0 20 14 28.57 356.293 - 8%
September - 2020
PC-II for Rs.12.500 m approved. LOA issued to Lalazar Consultants.
No Image
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 2.5 0 41.049 98.951 34% 27%
August - 2019
Length 6 Km - earth work, sub base in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 0 0 20 0 14.57 356.293 - 4%
August - 2020
PC-II for Rs.12.500 m approved. LOA issued to Lalazar Consultants.
No Image
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 365 0 140 0 0 0 0 225 38% -
July - 2020
PC-II for Rs.12.500 m approved. LOA issued Lalazar
No Image
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 10 51.049 98.951 34% 34%
May - 2020
Length 6 Km - earth work, sub base 80% completed.Base course & structure work in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 140 90 90 86.234 100.804 216.293 42% 27%
May - 2021
01- Unit Portion one roof laid Column completed
No Image
Trauma Centre in DHQ Hospital Lakki Marwat.
 
Scope of work:
  • 02 Nos O.T with scrub room and sterilization roomalong with 04 rooms for storageof article and medicines 
  • 02 Nos Recovery rooms 
  • 02 No Resuscitationrooms 
  • Plaster Room 
  • 03 M/Ward each 10 beds 
  • 03 F/Ward each 10 beds 
  • 10 bedsI.C.U 
  • Patient reciving Hall 02 for Male/Female 
  • X-Ray Block 
  • Pathology/Lab Block 
  • Office setup 
  • Dislysis Block 
  • Office setup for specialists 
  • Waiting area/ Halls for Patients  
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 10 51.049 98.951 34% 34%
April - 2020
Length 6 Km - earth work, sub base 80% completed.Base course & structure work in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 140 90 90 85.944 100.514 216.293 42% 27%
April - 2021
Plainth beam completed column in progress
No Image
Trauma Centre in DHQ Hospital Lakki Marwat.
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 10 51.049 98.951 34% 34%
March - 2020
Length 6 Km - earth work, sub base 80% completed.Base course & structure work in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 140 90 90 66.008 80.578 216.293 42% 22%
March - 2021
Plainth beam completed column in progress
No Image
Trauma Centre in DHQ Hospital Lakki Marwat.
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 10 51.049 98.951 34% 34%
February - 2020
Length 6 Km - earth work, sub base 80% completed.Base course & structure work in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 140 90 90 66.008 80.578 216.293 42% 22%
February - 2021
Plainth beam completed column in progress
No Image
Trauma Centre in DHQ Hospital Lakki Marwat.
742
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 41.049 10 10 10 10 51.049 98.951 34% 34%
January - 2020
Length 6 Km - earth work, sub base in progress.
No Image
PK-76, Lakki Marwat
742
(OG)
180467-Establishment of Trauma Centre in DHQ Hospital Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 370.863 14.57 55 90 90 63.766 78.336 301.293 19% 21%
January - 2021
Reaft founation completed. Column in progresss
No Image
Trauma Centre in DHQ Hospital Lakki Marwat.
742
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 66.852 0.001 0.001 0.0005 0 66.852 81.908 45% 45%
September - 2018
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress.
No Image
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km)
742
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 66.852 0.001 0.001 0.0005 0 66.852 81.908 45% 45%
July - 2018
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress.
No Image
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km)
Pages : 1