Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 411.788 | 0 | 80 | 80 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
Site/scope of work not identified. |
No Image |
Chitral | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.10487 | 293.91487 | 0 | 100% |
100% December - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.105 | 293.915 | 0 | 100% |
100% November - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 27.474 | 281.284 | 0 | 100% |
96% October - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 10.26 | 9.213 | 263.023 | 0 | 100% |
89% September - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 10.26 | 0 | 253.81 | 0 | 100% |
86% August - 2019 |
Length 21.5 Km - earth work, sub base completed, base course 7 Km completed, TST 4 Km completed. Liability Rs.20 m. |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.10487 | 293.91487 | 0 | 100% |
100% May - 2020 |
Length 21.5 Km - Substanially Completd
Required Rs. 22.79 M for Liability |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.10487 | 293.91487 | 0 | 100% |
100% April - 2020 |
Length 21.5 Km - Substanially Completd
Required Rs. 22.79 M for Liability |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.10487 | 293.91487 | 0 | 100% |
100% March - 2020 |
Length 21.5 Km - Substanially Completd
Required Rs. 22.79 M for Liability |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.10487 | 293.91487 | 0 | 100% |
100% February - 2020 |
Length 21.5 Km - Substanially Completd
Required Rs. 22.79 M for Liability |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (OG) |
140664-F/S, Design and Construction of Road from village Abasa to Shahab Khel, District Lakki Marwat (21.5 Kms). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 293.915 | 253.81 | 40.105 | 40.105 | 40.105 | 40.10487 | 293.91487 | 0 | 100% |
100% January - 2020 |
Length 21.5 Km - Substanially Completd
Required Rs. 22.79 M for Liability |
No Image |
Lakki Marwat (21.50 Km) | |||||||||||||||||||
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
740 (New) |
200159-Khyber Pakhtunkhwa Human Capital Investment Project. (IDA Credit of US$ 49.6 million and IDA grant US$ 35.4 million). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
740 (OG) |
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms). |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 188.14 | 61.221 | 0.001 | 0.001 | 0.0005 | 0 | 61.221 | 126.918 | 33% |
33% September - 2018 |
Length 12 Km (4 units) - earth work, SW in progress. |
No Image |
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km) | |||||||||||||||||||
740 (OG) |
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms). |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 188.14 | 61.221 | 0.001 | 0.001 | 0.0005 | 0 | 61.221 | 126.918 | 33% |
33% July - 2018 |
Length 12 Km (4 units) - earth work, SW in progress. |
No Image |
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km) | |||||||||||||||||||
Pages : 1 |