Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
15-04-16 | 30-06-18 | - | 04-06-15 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 14.083 | 68.583 | 0 | 100% |
69% December - 2017 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
15-04-16 | 30-06-18 | - | 04-06-15 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 0 | 54.5 | 0 | 100% |
55% September - 2017 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
15-04-16 | 30-06-18 | - | 04-06-15 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 0 | 54.5 | 0 | 100% |
55% August - 2017 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
15-04-16 | 30-06-18 | - | 04-06-15 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 0 | 54.5 | 0 | 100% |
55% July - 2017 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 4.083 | 58.583 | 0 | 100% |
59% November - 2017 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 4.083 | 58.583 | 0 | 100% |
59% October - 2017 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 13.394 | 13.394 | 13.394 | 67.894 | 0 | 100% |
68% June - 2018 |
Main building - plastering/flooring in progress. Cannot be completed as balance allocation is required for completion. |
No Image |
PK-78 District Buner | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 13.394 | 67.894 | 0 | 100% |
68% May - 2018 |
Main building - plastering/flooring in progress. Cannot be complted as balance allocation is required for completion. |
No Image |
PK-78 District Buner | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 14.083 | 68.583 | 0 | 100% |
69% April - 2018 |
Main building - plastering/flooring in progress. . |
No Image |
PK-78 District Buner | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 14.083 | 68.583 | 0 | 100% |
69% March - 2018 |
Main building - plastering/flooring in progress. Balance funds Rs. 26.145 for completion |
No Image |
PK-78 District Buner | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 14.083 | 68.583 | 0 | 100% |
69% February - 2018 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 District Buner | |||||||||||||||||||
73 (OG) |
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.899 | 54.5 | 51.899 | 51.899 | 23.355 | 14.083 | 68.583 | 0 | 100% |
69% January - 2018 |
Main building - plastering/flooring in progress. |
No Image |
PK-78 | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5.0005 | 0 | 0 | 339.501 | 3% |
- December - 2018 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5.0005 | 0 | 0 | 339.501 | 3% |
- November - 2018 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5.0005 | 0 | 0 | 339.501 | 3% |
- November - 2018 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 15.602 | 15.602 | 5 | 5 | 339.501 | 3% |
1% April - 2019 |
Land payment of Rs.50 m involved. Work order issued.
Demand Rs. 60 M |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5.0005 | 4.5 | 4.5 | 339.501 | 3% |
1% March - 2019 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5.0005 | 4.5 | 4.5 | 339.501 | 3% |
1% March - 2019 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5.0005 | 4.5 | 4.5 | 339.501 | 3% |
1% February - 2019 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
170642-Establishment of District Secretariate for Lower Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.501 | 0 | 10 | 10 | 5 | 0 | 0 | 339.501 | 3% |
- January - 2019 |
Land payment of Rs.70 m involved. Work order issued. |
No Image |
Lower Kohistan | |||||||||||||||||||
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- December - 2020 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- December - 2020 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- October - 2020 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- September - 2020 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- August - 2020 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- May - 2021 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- April - 2021 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- March - 2021 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- February - 2021 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
- January - 2021 |
No Image | |
73 (OG) |
191047-070181 - Provision of AI Facilities in Existing 11 Vety: Institutions, NWA. [MA] |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 72.73 | 68.73 | 0 | 0 | 0 | 0 | 68.73 | 0 | - |
July - 2020 |
No Image | |
73 (OG) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 20 | 10 | 0 | 0 | 59.84 | - |
- September - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
73 (OG) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 20 | 10 | 0 | 0 | 59.84 | - |
- July - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 5 | 0 | 0 | 46.604 | 30% |
- December - 2019 |
Work on BW and Overhand Tank Started. |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 5 | 0 | 0 | 46.604 | 30% |
- November - 2019 |
Work on BW and Overhand Tank Started. |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 5 | 0 | 0 | 46.604 | 30% |
- October - 2019 |
Work on BW and Overhand Tank Started. |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 5 | 0 | 0 | 46.604 | 30% |
- September - 2019 |
Work order issued. |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 5 | 0 | 0 | 46.604 | 30% |
- August - 2019 |
Financial bid submitted to CE. |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 20 | 13.993 | 13.993 | 46.604 | 30% |
21% May - 2020 |
MB- G.F upto Roof leve.
BW- 40 %
Overhead Tank 60 %
Guard Room - Lintel Level |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 20 | 8.77 | 8.77 | 46.604 | 30% |
13% April - 2020 |
MB- G.F upto Roof leve.
BW- 40 %
Overhead Tank 60 %
Guard Room - Lintel Level |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 20 | 8.77 | 8.77 | 46.604 | 30% |
13% March - 2020 |
MB- G.F upto Roof leve.
BW- 40 %
Overhead Tank 60 %
Guard Room - Lintel Level |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 20 | 8.77 | 8.77 | 46.604 | 30% |
13% February - 2020 |
MB- G.F upto Roof leve.
BW- 40 %
Overhead Tank 60 %
Guard Room - Lintel Level |
No Image |
Tank | |||||||||||||||||||
73 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 20 | 20 | 20 | 5 | 5 | 46.604 | 30% |
8% January - 2020 |
MB- Plintgh Level
BW- 40 %
Overhand Tank Started. |
No Image |
Tank | |||||||||||||||||||
Pages : 1 |