Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2020, January - 2021, February - 2018, February - 2020, February - 2021, March - 2018, March - 2020, March - 2021, April - 2018, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2018, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 4

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2017
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2017
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
August - 2017
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
July - 2017
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
November - 2017
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
October - 2017
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
June - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
March - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
January - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2017
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2017
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
August - 2017
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
July - 2017
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
November - 2017
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
October - 2017
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
June - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
March - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
January - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
- 30-06-18 - 16-12-16 - 50 0 20 20 10 0 0 30 40% -
December - 2017
Work order issued. Site disputed. Jail Superindent not allowing to start work on site.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
- 30-06-18 - 16-12-16 - 50 0 20 20 20 0 0 30 40% -
September - 2017
Work order issued. Site disputed. Jail superindent not allowing to start work on site.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
- 30-06-18 - 16-12-16 - 50 0 10 10 10 0 0 40 20% -
August - 2017
Work order issued. Site disputed. Jail superindent not allowing to start work on site.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
- 30-06-18 - 16-12-16 - 50 0 0 0 0 0 0 50 - -
July - 2017
Work order issued.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 10 0 0 30 40% -
November - 2017
Work order issued. Site disputed. Jail Superindent not allowing to start work on site.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 20 0 0 30 40% -
October - 2017
Work order issued. Site disputed. Jail superindent not allowing to start work on site.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 3.977 3.977 3.977 3.977 3.977 46.023 8% 8%
June - 2018
DPC plinth beam on half due to space problem. Cannot be complted in CFY due to late handing taking of site by Jail Admin.
No Image
District Jail Buner
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 20 3.977 3.977 30 40% 8%
May - 2018
DPC plinth beam on half due to space problem. Cannot be complted in CFY due to late handing taking of site by Jail Admin.
No Image
District Jail Buner
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 10 3.925 3.925 30 40% 8%
April - 2018
DPC plinth beam on half due to space problem. Cannot be complted in CFY due to late handing taking of site by Jail Admin.
No Image
District Jail Buner
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 10 3.925 3.925 30 40% 8%
March - 2018
DPC plinth beam on half due to space problem. Cannot be complted in CFY due to late handing taking of site by Jail Admin.
No Image
District Jail Buner
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 10 0 0 30 40% -
February - 2018
Raft in progress.
No Image
District Jail Buner
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 10 0 0 30 40% -
January - 2018
Work order issued. Site disputed. Jail Superindent not allowing to start work on site.
No Image
Sub Jail Daggar
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2017
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2017
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
August - 2017
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
July - 2017
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
November - 2017
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
October - 2017
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
June - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
March - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
January - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Chitral
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2017
PC-I/DCE under preparation.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Chitral
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2017
PC-I/DCE under preparation.