Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
12-09-16 | 30-06-18 | - | - | - | 190 | 27.5 | 60.395 | 60.395 | 60.395 | 37.86 | 65.36 | 102.105 | 46% |
34% December - 2017 |
Work on SS level in progress on 3/6 units. 3 units not yet cleared by Supdt Jail. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
12-09-16 | 30-06-18 | - | - | - | 190 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 162.5 | - |
14% September - 2017 |
Work in progress on 6 units. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
12-09-16 | 30-06-18 | - | - | - | 190 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 162.5 | - |
14% August - 2017 |
Work in progress on 6 units. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
12-09-16 | 30-06-18 | - | - | - | 190 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 162.5 | - |
14% July - 2017 |
Work in progress on 6 units. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 190 | 27.5 | 60.395 | 60.395 | 60.395 | 37.86 | 65.36 | 102.105 | 46% |
34% November - 2017 |
Work in progress on 3/6 units. 3 units not yet cleared by Supdt Jail. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 190 | 27.5 | 60.395 | 60.395 | 60.395 | 6.205 | 33.705 | 102.105 | 46% |
18% October - 2017 |
Work in progress on 3/6 units. 3 units not yet cleared by Supdt Jail. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 27.5 | 46.658 | 46.658 | 46.658 | 46.657 | 74.157 | 33.277 | 69% |
69% June - 2018 |
Work in progress on 6/6 units. |
No Image |
Central Prison Haripur (remaining BW/interview shed with allied facility/watch tower on P/Wall/warden barrack/kitchen/second armor block/water reservoir/drain) | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 27.5 | 60.395 | 60.395 | 60.395 | 46.657 | 74.157 | 19.54 | 82% |
69% May - 2018 |
Work in progress on 6/6 units. |
No Image |
Central Prison Haripur (remaining BW/interview shed with allied facility/watch tower on P/Wall/warden barrack/kitchen/second armor block/water reservoir/drain) | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 27.5 | 60.395 | 60.395 | 60.395 | 44.541 | 72.041 | 19.54 | 82% |
67% April - 2018 |
Work in progress on 6/6 units. |
No Image |
Central Prison Haripur (remaining BW/interview shed with allied facility/watch tower on P/Wall/warden barrack/kitchen/second armor block/water reservoir/drain) | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 27.5 | 60.395 | 60.395 | 60.395 | 38.439 | 65.939 | 19.54 | 82% |
61% March - 2018 |
Work in progress on 6/6 units. |
No Image |
Central Prison Haripur (remaining BW/interview shed with allied facility/watch tower on P/Wall/warden barrack/kitchen/second armor block/water reservoir/drain) | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 27.5 | 60.395 | 60.395 | 60.395 | 37.017 | 64.517 | 19.54 | 82% |
60% February - 2018 |
Work on SS level in progress on 6/6 units. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 190 | 27.5 | 60.395 | 60.395 | 60.395 | 22.351 | 49.851 | 102.105 | 46% |
26% January - 2018 |
Work on SS level in progress on 6/6 units. |
No Image |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
14-01-16 | 30-06-18 | - | - | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% December - 2017 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
14-01-16 | 30-06-18 | - | - | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% September - 2017 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
14-01-16 | 30-06-18 | - | - | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% August - 2017 |
Completed. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
14-01-16 | 30-06-18 | - | - | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% July - 2017 |
Completed. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% November - 2017 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% October - 2017 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% June - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% May - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% April - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% March - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% February - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% January - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% December - 2019 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% November - 2019 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% October - 2019 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% September - 2019 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% August - 2019 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% May - 2020 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% April - 2020 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% March - 2020 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% February - 2020 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.967 | 0.12 | 0 | 0 | 0 | 0 | 0.12 | 87.847 | - |
0% January - 2020 |
Tender under process.
Site disputed b/w DC office and PDMA. |
No Image |
Pattan Lower Kohistan | |||||||||||||||||||
723 (OG) |
170661-Rehabilitation of Road from Kandaro Kalay to Asif Kalay (2 Km), Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 15.251 | 4.749 | 4.749 | 2.375 | 1.439 | 16.69 | 0 | 100% |
83% September - 2018 |
RW, pipe culverts, sub base in trench both side, WBM 100% completed. |
No Image |
Kandaro Kalay to Asif Kalay (2 Km) Mardan | |||||||||||||||||||
723 (OG) |
170661-Rehabilitation of Road from Kandaro Kalay to Asif Kalay (2 Km), Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 15.251 | 4.749 | 4.749 | 2.375 | 0 | 15.251 | 0 | 100% |
76% July - 2018 |
RW, pipe culverts, sub base in trench both side, WBM 100% completed. |
ADP's Images |
Kandaro Kalay to Asif Kalay (2 Km) Mardan | |||||||||||||||||||
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
- | 30-06-18 | - | 08-10-15 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% December - 2017 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
- | 30-06-18 | - | 08-10-15 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% September - 2017 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
- | 30-06-18 | - | 08-10-15 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% August - 2017 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
- | 30-06-18 | - | 08-10-15 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% July - 2017 |
No Image | |
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% November - 2017 |
No Image | |
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% October - 2017 |
No Image | |
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% June - 2018 |
No Image | |
723 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 143 | 71.777 | 120.79 | 120.79 | 0 | 0 | 71.777 | 0 | 100% |
50% May - 2018 |
No Image | |
723 (OG) |
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
Pages : 1 2 |