Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2020, February - 2020, February - 2021, February - 2018, March - 2020, March - 2021, March - 2018, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2018, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2019, December - 2020, December - 2017, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
24-06-09 - - 16-11-17 - 330.06 222.275 0 0 0 0 222.275 107.785 - 67%
December - 2017
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
24-06-09 - - 18-05-11 - 264.391 222.275 0 0 0 0 222.275 42.116 - 84%
September - 2017
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress. Revised DCE including damage portion submitted for Rs.339 m to P&D.
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
24-06-09 - - 18-05-11 - 264.391 222.275 0 0 0 0 222.275 42.116 - 84%
August - 2017
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress. Revised DCE including damage portion submitted for Rs.339 m to P&D.
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
24-06-09 - - 18-05-11 - 264.391 222.275 0 0 0 0 222.275 42.116 - 84%
July - 2017
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress. Revised DCE including damage portion submitted for Rs.339 m to Home Deptt.
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 222.275 0 0 0 0 222.275 107.785 - 67%
November - 2017
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 264.391 222.275 0 0 0 0 222.275 42.116 - 84%
October - 2017
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress. Revised DCE including damage portion submitted for Rs.339 m to P&D. observation attended.
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 220.663 0 0 0 0 220.663 109.397 - 67%
June - 2018
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
Hangu
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 220.663 0 0 0 0 220.663 109.397 - 67%
May - 2018
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
Hangu
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 220.663 0 0 0 0 220.663 109.397 - 67%
April - 2018
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
Hangu
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 220.663 0 0 0 0 220.663 109.397 - 67%
March - 2018
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
Hangu
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 220.663 0 0 0 0 220.663 109.397 - 67%
February - 2018
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
Hangu
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (Provincial Funds Exhausted, remaining funds released by FATA).
Hangu
30-11--1 30-11--1 - 30-11--1 - 330.06 222.275 0 0 0 0 222.275 107.785 - 67%
January - 2018
Barraks finishing stage. Admin block damaged due to bomb blast. Mosque finishing stage laid. Dev work in progress.
No Image
Hangu
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
December - 2019
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
December - 2019
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
November - 2019
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 69.625 121.951 40 40 0 0 121.951 0 100% 100%
October - 2019
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 69.625 121.951 40 40 0 0 121.951 0 100% 100%
September - 2019
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 69.625 121.951 40 40 0 0 121.951 0 100% 100%
August - 2019
Steel Fabrication GF in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
May - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
May - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
April - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
April - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
March - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
March - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
February - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
February - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
January - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur
Haripur
30-11--1 30-11--1 - 30-11--1 - 38.46 121.951 40 40 30 0 121.951 0 100% 100%
January - 2020
GF/FF - roofing in progress.
No Image
Haripur
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
December - 2020
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
December - 2020
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
October - 2020
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
September - 2020
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
August - 2020
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 -
July - 2020
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
May - 2021
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
April - 2021
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
March - 2021
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
February - 2021
No Image
717
(OG)
191420-180578 - Development of NTFP activities in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 20 3.088 0 0 0 0 3.088 0 - -
January - 2021
No Image
717
(OG)
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 75 55.5 19.5 19.5 9.75 3.518 59.018 0 100% 79%
September - 2018
2/2 units in progress.
No Image
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft
717
(OG)
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 75 55.5 19.5 19.5 9.75 0 55.5 0 100% 74%
July - 2018
2/2 units in progress.
ADP's Images
1) Qutab Garhi to Latif Khan Killi 2.5 Km (construction/rehabilitation/BT) width 18ft
2) Village Jalala to Pir Saddu via Ghano Shah road 4 Km (construction/rehabilitation/BT) width 18ft
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
24-06-09 - - 16-11-17 - 330.06 222.275 0.001 0.001 0 0 222.275 107.784 67% 67%
December - 2017
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
24-06-09 - - 18-05-11 - 264.391 222.275 0.001 0.001 0 0 222.275 42.115 84% 84%
September - 2017
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
24-06-09 - - 18-05-11 - 264.391 222.275 0.001 0.001 0 0 222.275 42.115 84% 84%
August - 2017
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
24-06-09 - - 18-05-11 - 264.391 222.275 0.001 0.001 0 0 222.275 42.115 84% 84%
July - 2017
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
30-11--1 30-11--1 - 30-11--1 - 330.06 222.275 0.001 0.001 0 0 222.275 107.784 67% 67%
November - 2017
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
30-11--1 30-11--1 - 30-11--1 - 264.391 222.275 0.001 0.001 0 0 222.275 42.115 84% 84%
October - 2017
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
30-11--1 30-11--1 - 30-11--1 - 330.06 222.275 0.001 0.001 0 0 222.275 107.784 67% 67%
June - 2018
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
30-11--1 30-11--1 - 30-11--1 - 330.06 222.275 0.001 0.001 0 0 222.275 107.784 67% 67%
May - 2018
No Image
717
(OG)
80466-Construction of District Jail Hangu (Phase-I) 50/50 cost sharing basis with FATA (provincial funds exhausted, remaining funds released by FATA).
Provincial
30-11--1 30-11--1 - 30-11--1 - 330.06 222.275 0.001 0.001 0 0 222.275 107.784 67% 67%
April - 2018
No Image