Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2021, January - 2018, February - 2019, February - 2021, February - 2018, March - 2019, March - 2021, March - 2018, April - 2019, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, September - 2018, September - 2020, September - 2017, October - 2020, October - 2017, November - 2017, November - 2018, December - 2018, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 11.022 11.022 78.916 9.961 90% 79%
December - 2018
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 11.022 2.5 70.394 9.961 90% 70%
November - 2018
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 11.022 2.5 70.394 9.961 90% 70%
November - 2018
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 22.044 17.483 85.377 9.961 90% 85%
April - 2019
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 22.044 11.022 78.916 9.961 90% 79%
March - 2019
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 22.044 11.022 78.916 9.961 90% 79%
March - 2019
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 22.044 11.022 78.916 9.961 90% 79%
February - 2019
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
150759-F/S, Design and Construction of Building for Tehsil Gagra, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 99.899 67.894 22.044 22.044 11.022 11.022 78.916 9.961 90% 79%
January - 2019
Main building - plastering/flooring in progress.
No Image
PK-78 District Buner
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
05-12-16 30-06-18 - 26-11-15 - 98.586 34.835 67.751 67.751 30.488 27.541 62.376 0 100% 63%
December - 2017
Main building - GF roof laid. BW 80%, tube well completed.
No Image
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
05-12-16 30-06-18 - 26-11-15 - 98.586 34.835 67.751 67.751 30.488 13.945 48.78 0 100% 49%
September - 2017
Main building - plinth level. BW - SS in progress. Tube well - completed.
No Image
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
05-12-16 30-06-18 - 26-11-15 - 98.586 34.835 67.751 67.751 30.488 0 34.835 0 100% 35%
August - 2017
Main building - plinth level. BW - SS in progress. Tube well - completed.
No Image
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
05-12-16 30-06-18 - 26-11-15 - 98.586 34.835 67.751 67.751 30.488 0 34.835 0 100% 35%
July - 2017
Main building - plinth level. BW - SS in progress. Tube well - completed.
No Image
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 30.488 27.541 62.376 0 100% 63%
November - 2017
Main building - GF roof laid. BW 80%, tube well completed.
No Image
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 30.488 25.644 60.479 0 100% 61%
October - 2017
Main building - GF roof laid. BW 80%, tube well completed.
No Image
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 49.38 49.38 49.38 84.215 0 100% 85%
June - 2018
Consultant Design: Allied. Main building - finishing in progress. BW 95%, tube well completed.
No Image
Offices and residences for Tehsildar at Rustam Mardan
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 67.751 43.921 78.756 0 100% 80%
May - 2018
Consultant Design: Allied. Main building - finishing in progress. BW 95%, tube well completed.
No Image
Offices and residences for Tehsildar at Rustam Mardan
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 64.364 43.921 78.756 0 100% 80%
April - 2018
Consultant Design: Allied. Main building - finishing in progress. BW 95%, tube well completed.
No Image
Offices and residences for Tehsildar at Rustam Mardan
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 47.426 38.824 73.659 0 100% 75%
March - 2018
Consultant Design: Allied. Main building - finishing in progress. BW 95%, tube well completed.
No Image
Offices and residences for Tehsildar at Rustam Mardan
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 47.426 38.824 73.659 0 100% 75%
February - 2018
(Consultant Design: Allied) Main building - finishing in progress. BW 95%, tube well completed.
No Image
Mardan
71
(OG)
140976-F/S, Design and Construction of Offices and Residence for Tehsildar at Rustam, Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 98.586 34.835 67.751 67.751 30.488 30.488 65.323 0 100% 66%
January - 2018
Main building - FF roof laid. BW 90%, tube well completed.
No Image
Mardan
71
(OG)
150214-Construction of Cafeteria/Car Parking/Masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290.907 276.423 60.86 60.86 30.43 5.786 282.209 0 100% 97%
September - 2018
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
No Image
Peshawar
71
(OG)
150214-Construction of Cafeteria/Car Parking/Masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290.907 276.423 60.86 60.86 30.43 0 276.423 0 100% 95%
July - 2018
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress. 2nd Revised PC-I/DCE for Rs.400.760 m submitted to SOR on 26/04/2018.
No Image
Peshawar
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 20.216 1.789 1.789 1.789 0 20.216 0 100% 92%
December - 2020
Completed & H/O.
No Image
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 20.216 1.789 1.789 1.789 0 20.216 0 100% 92%
December - 2020
Completed & H/O.
No Image
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 20.216 1.789 1.789 1.789 0 20.216 0 100% 92%
October - 2020
Completed & H/O.
No Image
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 20.216 1.789 1.789 1.789 0 20.216 0 100% 92%
September - 2020
Completed & H/O.
No Image
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 20.216 1.789 1.789 1.789 0 20.216 0 100% 92%
August - 2020
Completed & H/O.
No Image
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 19.775 1.789 1.789 1.789 0 19.775 0.441 98% 90%
May - 2021
06- Units All Completed & H/O.
No Image
1 CVD Malik Khanzada Yargul Khel Kot
2 CVD Kot Remal Jan Baddar Giga Khel
3 CVD at Rehman Gul Kot Nano Sarwaki
4 CVC Malik Pir Ghulam Kot Bazai Makeen
5 CVC Kotkai Saraogha
6 CVD Akbar Jan Kot Shabi Khel Woucha Wam Shawal
 
Scope of work:
  • Maing Building
  • Int: Elect:
  • Int: W/S & Sanitary Installation
  • Dev: work
  • C/Wall
  • Store room
 
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 19.775 1.789 1.789 1.789 0 19.775 0.441 98% 90%
April - 2021
Completed & H/O.
No Image
1 CVD Malik Khanzada Yargul Khel Kot
2 CVD Kot Remal Jan Baddar Giga Khel
3 CVD at Rehman Gul Kot Nano Sarwaki
4 CVC Malik Pir Ghulam Kot Bazai Makeen
5 CVC Kotkai Saraogha
6 CVD Akbar Jan Kot Shabi Khel Woucha Wam Shawal
 
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 19.775 1.789 1.789 1.789 0 19.775 0.441 98% 90%
March - 2021
Completed & H/O.
No Image
1 CVD Malik Khanzada Yargul Khel Kot
2 CVD Kot Remal Jan Baddar Giga Khel
3 CVD at Rehman Gul Kot Nano Sarwaki
4 CVC Malik Pir Ghulam Kot Bazai Makeen
5 CVC Kotkai Saraogha
6 CVD Akbar Jan Kot Shabi Khel Woucha Wam Shawal
 
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 19.775 1.789 1.789 1.789 0 19.775 0.441 98% 90%
February - 2021
Completed & H/O.
No Image
1 CVD Malik Khanzada Yargul Khel Kot
2 CVD Kot Remal Jan Baddar Giga Khel
3 CVD at Rehman Gul Kot Nano Sarwaki
4 CVC Malik Pir Ghulam Kot Bazai Makeen
5 CVC Kotkai Saraogha
6 CVD Akbar Jan Kot Shabi Khel Woucha Wam Shawal
 
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 22.005 19.775 1.789 1.789 1.789 0 19.775 0.441 98% 90%
January - 2021
Completed & H/O.
No Image
1 CVD Malik Khanzada Yargul Khel Kot
2 CVD Kot Remal Jan Baddar Giga Khel
3 CVD at Rehman Gul Kot Nano Sarwaki
4 CVC Malik Pir Ghulam Kot Bazai Makeen
5 CVC Kotkai Saraogha
6 CVD Akbar Jan Kot Shabi Khel Woucha Wam Shawal
 
71
(OG)
191076-070082-Construction of building for 06 existing CVDs in SWA. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 22.005 20.216 1.789 0 0 0 20.216 0
July - 2020
No Image