Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- December - 2019 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- November - 2019 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- October - 2019 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- September - 2019 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- August - 2019 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- May - 2020 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- April - 2020 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- March - 2020 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- February - 2020 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
160447-Establishment of Emergency Rescue Services (Rescue 1122) in District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 240.989 | 136.587 | 30 | 20 | 0 | 0 | 136.587 | 0 | - |
- January - 2020 |
Approved in PDWP on 23/12/2016. AA awaited. |
No Image |
1) Main Station
2) Sub Station | |||||||||||||||||||
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
Scope of work not identified. |
No Image |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Scope of work not identified. |
No Image |
707 (OG) |
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.614 | 85.573 | 13.11 | 13.11 | 13.11 | 6.555 | 92.128 | 0 | 100% |
100% September - 2018 |
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress. |
No Image |
1) Bridge i/c Bridge approaches (4 span n length 24 m each)
2) 5 Km road on both sides | |||||||||||||||||||
707 (OG) |
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.614 | 85.573 | 13.11 | 13.11 | 6.555 | 0 | 85.573 | 0 | 100% |
100% July - 2018 |
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress. |
ADP's Images |
1) Bridge i/c Bridge approaches (4 span n length 24 m each)
2) 5 Km road on both sides | |||||||||||||||||||
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
- | - | - | 11-03-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
- | - | - | 11-03-16 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
- | - | - | 11-03-16 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
- | - | - | 11-03-16 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
- | - | - | 11-03-16 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
No Image | |
707 (OG) |
191486-190273 -Biodiversity Research Initiatives in Merged Areas of Khyber Pakhtunkhwa . [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | - |
- December - 2020 |
No Image | |
707 (OG) |
191486-190273 -Biodiversity Research Initiatives in Merged Areas of Khyber Pakhtunkhwa . [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | - |
- December - 2020 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
No Image | |
707 (OG) |
191486-190273 -Biodiversity Research Initiatives in Merged Areas of Khyber Pakhtunkhwa . [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | - |
- October - 2020 |
No Image | |
707 (OG) |
191486-190273 -Biodiversity Research Initiatives in Merged Areas of Khyber Pakhtunkhwa . [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | - |
- September - 2020 |
No Image | |
707 (OG) |
191486-190273 -Biodiversity Research Initiatives in Merged Areas of Khyber Pakhtunkhwa . [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | - |
- August - 2020 |
No Image | |
707 (OG) |
191486-190273 -Biodiversity Research Initiatives in Merged Areas of Khyber Pakhtunkhwa . [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44 | 4 | 0 | 0 | 0 | 0 | 4 | 0 | - |
July - 2020 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
No Image | |
707 (OG) |
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 185.18 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
No Image | |