Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- December - 2019 |
1 unit,
Havellian - Rs.4 m required. |
No Image |
1) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- November - 2019 |
1 unit,
Havellian - Rs.4 m required. |
No Image |
1) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- October - 2019 |
1 unit,
Havellian - Rs.4 m required. |
No Image |
1) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- September - 2019 |
1 unit,
Havellian - Rs.4 m required. |
No Image |
1) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- August - 2019 |
1 unit,
Havellian - Rs.4 m required. |
No Image |
1) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 24.686 | 9% |
9% May - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Paymnet made , Site not yet handed over |
No Image |
1) SDC abbottabad
2) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 24.686 | 9% |
9% April - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Paymnet made , Site not yet handed over |
No Image |
1) SDC abbottabad
2) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 24.686 | 9% |
9% March - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Paymnet made , Site not yet handed over |
No Image |
1) SDC abbottabad
2) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 24.686 | 9% |
9% February - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Paymnet made , Site not yet handed over |
No Image |
1) SDC abbottabad
2) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 24.686 | 9% |
9% January - 2020 |
SDC Abbottabad- Complted
SDC Havelian - land Paymnet made , Site bnot yet handed over |
No Image |
1) SDC abbottabad
2) SDC Havelian | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- December - 2019 |
1 units, Bannu - demolition in progress. Site plan approved & work order issued. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- November - 2019 |
1 units, Bannu - demolition in progress. Site plan approved & work order issued. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- October - 2019 |
1 units, Bannu - demolition in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- September - 2019 |
1 units, Bannu - demolition in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- August - 2019 |
1 units, Bannu - demolition in progress. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 4.801 | 4.801 | 4.801 | 2.115 | 2.115 | 31.876 | 13% |
6% May - 2020 |
1 units, Bannu - demolition icompleted . Work started. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 10 | 10 | 10 | 0 | 0 | 26.677 | 27% |
- April - 2020 |
1 units, Bannu - demolition icompleted . Work started. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 10 | 10 | 10 | 0 | 0 | 26.677 | 27% |
- March - 2020 |
1 units, Bannu - demolition icompleted . Work started. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 10 | 10 | 10 | 0 | 0 | 26.677 | 27% |
- February - 2020 |
1 units, Bannu - demolition icompleted . Work started. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- January - 2020 |
1 units, Bannu - demolition icompleted . Work started. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 3 | 2.591 | 2.591 | 1.131 | 96% |
8% December - 2019 |
2 units,
Battagram - Deffered
Allai - Tendering approval in progress. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 3 | 2.591 | 2.591 | 1.131 | 96% |
8% November - 2019 |
2 units,
Battagram - Deffered
Allai - Tendering approval in progress. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 30 | 2.591 | 2.591 | 1.131 | 96% |
8% October - 2019 |
2 units,
Battagram - Deffered
Allai - Tendering approval in progress. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 30 | 0 | 0 | 1.131 | 96% |
- September - 2019 |
2 units,
Battagram - Deffered
Allai - Tendering approval in progress. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 0 | 0 | 0 | 0 | 0 | 31.131 | - |
- August - 2019 |
2 units,
Battagram - Deffered
Allai - Tendering approval in progress. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 5.295 | 5.295 | 2.591 | 2.591 | 1.131 | 96% |
8% May - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued(Land Award Awaited) |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 3 | 2.591 | 2.591 | 1.131 | 96% |
8% April - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued(Land Award Awaited) |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 3 | 2.591 | 2.591 | 1.131 | 96% |
8% March - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued(Land Award Awaited) |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 3 | 2.591 | 2.591 | 1.131 | 96% |
8% February - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued(Land Award Awaited) |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.131 | 0 | 30 | 30 | 3 | 2.591 | 2.591 | 1.131 | 96% |
8% January - 2020 |
2 units,
Battagram - Deffered
Allai - Work order issued(Land Award Awaited) |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 1 | 21.788 | 21.788 | 2 | 51.592 | 21.167 | 71% |
72% December - 2019 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 1 | 1 | 1 | 0 | 49.592 | 21.167 | 71% |
69% November - 2019 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 1 | 1 | 1 | 0 | 49.592 | 21.167 | 71% |
69% October - 2019 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 0 | 0 | 0 | 0 | 49.592 | 22.167 | - |
69% September - 2019 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 0 | 0 | 0 | 0 | 49.592 | 22.167 | - |
69% August - 2019 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 21.788 | 21.788 | 21.788 | 2 | 51.592 | 0.379 | 99% |
72% May - 2020 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 21.788 | 21.788 | 21.788 | 2 | 51.592 | 0.379 | 99% |
72% April - 2020 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 21.788 | 21.788 | 21.788 | 2 | 51.592 | 0.379 | 99% |
72% March - 2020 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 21.788 | 21.788 | 21.788 | 2 | 51.592 | 0.379 | 99% |
72% February - 2020 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 49.592 | 1 | 21.788 | 21.788 | 2 | 51.592 | 21.167 | 71% |
72% January - 2020 |
3 units -
Khadukhail - 90% completed.
Gagra - finishing in progress.
Mandar - 50% completed. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% December - 2019 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% November - 2019 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% October - 2019 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 0 | 0 | 0 | 0 | 35.755 | 13.025 | - |
73% September - 2019 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 0 | 0 | 0 | 0 | 35.755 | 13.025 | - |
73% August - 2019 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 2 | 37.755 | 11.025 | 77% |
77% May - 2020 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar -Site Stay order - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% April - 2020 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar -Site Stay order - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% March - 2020 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar -Site Stay order - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% February - 2020 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar -Site Stay order - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
70 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 35.755 | 2 | 2 | 2 | 0 | 35.755 | 11.025 | 77% |
73% January - 2020 |
3 units,
Charsadda - completed.
Tangi - finishing in progress.
Shabqadar -Site Stay order - NIT floated. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
Pages : 1 2 3 4 5 |