Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- December - 2020 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- December - 2020 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- October - 2020 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- September - 2020 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- August - 2020 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
July - 2020 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- May - 2021 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- April - 2021 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- March - 2021 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- February - 2021 |
No Image | |
692 (OG) |
191452-170090 - Afforestation Over Denuded/ Barren Community Land in Khyber Agency. [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 38.819 | 0 | 0 | 0 | 0 | 38.819 | 0 | - |
- January - 2021 |
No Image | |
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
25-05-11 | - | - | 23-12-16 | - | 658.831 | 394.78 | 25 | 25 | 18.75 | 18.747 | 413.527 | 239.051 | 64% |
63% December - 2017 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 394.78 | 25 | 25 | 18.75 | 18.747 | 413.527 | 239.051 | 64% |
63% November - 2017 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 394.78 | 25 | 25 | 12.5 | 12.5 | 407.28 | 239.051 | 64% |
62% October - 2017 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
25-05-11 | - | - | 23-12-16 | - | 658.831 | 394.78 | 25 | 25 | 12.5 | 0 | 394.78 | 239.051 | 64% |
60% September - 2017 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
25-05-11 | - | - | 23-12-16 | - | 658.831 | 394.78 | 25 | 25 | 12.5 | 0 | 394.78 | 239.051 | 64% |
60% August - 2017 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
25-05-11 | - | - | 23-12-16 | - | 658.831 | 394.78 | 25 | 25 | 12.5 | 0 | 394.78 | 239.051 | 64% |
60% July - 2017 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 393.79 | 25 | 25 | 25 | 25 | 418.79 | 240.041 | 64% |
64% June - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 393.79 | 25 | 25 | 25 | 25 | 418.79 | 240.041 | 64% |
64% May - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. Demand Rs.100 m. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 393.79 | 25 | 25 | 25 | 25 | 418.79 | 240.041 | 64% |
64% April - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. Demand Rs.100 m. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 393.79 | 25 | 25 | 25 | 25 | 418.79 | 240.041 | 64% |
64% March - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. Demand Rs.100 m. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 394.78 | 25 | 25 | 25 | 18.747 | 413.527 | 239.051 | 64% |
63% February - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. Demand Rs.100 m. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
692 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 394.78 | 25 | 25 | 18.75 | 18.747 | 413.527 | 239.051 | 64% |
63% January - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. Demand Rs,.100 m. |
No Image |
Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy | |||||||||||||||||||
692 (OG) |
150849-Const / Reh / widening of road from (a) Shahmansoor Town to Sikandari (b) Govt Girls High School Manari Bala to Saleem Khan Chowk (c) Panjpir main road to Shaga Bridge (d) Qazi Abad to Aboo Banda, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 71.673 | 28.327 | 28.327 | 28.327 | 14.164 | 85.837 | 0 | 100% |
86% September - 2018 |
Length 8 Km - embankment, WBM completed. |
No Image |
1) Shah Mansoor Town to Sikandariroad (0.88 Km) width 18ft
2) GGHS Maneri Bala to Saleem Khan Chowk road (3.500 Km) width 18ft
3) Panjpir main road to Shaga Bridge (2.20 Km) width 18ft
4) Qazi Abad to Aboo Banda raod (1.800 Km) width 18ft | |||||||||||||||||||
692 (OG) |
150849-Const / Reh / widening of road from (a) Shahmansoor Town to Sikandari (b) Govt Girls High School Manari Bala to Saleem Khan Chowk (c) Panjpir main road to Shaga Bridge (d) Qazi Abad to Aboo Banda, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 71.673 | 28.327 | 28.327 | 14.164 | 0 | 71.673 | 0 | 100% |
72% July - 2018 |
Length 8 Km - embankment, WBM completed. |
No Image |
1) Shah Mansoor Town to Sikandariroad (0.88 Km) width 18ft
2) GGHS Maneri Bala to Saleem Khan Chowk road (3.500 Km) width 18ft
3) Panjpir main road to Shaga Bridge (2.20 Km) width 18ft
4) Qazi Abad to Aboo Banda raod (1.800 Km) width 18ft | |||||||||||||||||||
Pages : 1 |