Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 2.909 | 1.7 | 7.734 | 4.699 | 72% |
47% December - 2018 |
85% work completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 2.909 | 1.7 | 7.734 | 4.699 | 72% |
47% November - 2018 |
85% work completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 2.909 | 1.7 | 7.734 | 4.699 | 72% |
47% November - 2018 |
85% work completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 5.818 | 1.7 | 7.734 | 4.699 | 72% |
47% April - 2019 |
Roof treatment, flooring completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 5.818 | 1.7 | 7.734 | 4.699 | 72% |
47% March - 2019 |
Roof treatment, flooring completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 5.818 | 1.7 | 7.734 | 4.699 | 72% |
47% March - 2019 |
Roof treatment, flooring completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 5.818 | 1.7 | 7.734 | 4.699 | 72% |
47% February - 2019 |
85% work completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
160612-Renovation work of Tehsil Office, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.551 | 6.034 | 5.818 | 5.818 | 2.909 | 1.7 | 7.734 | 4.699 | 72% |
47% January - 2019 |
85% work completed. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
07-05-15 | - | - | 24-01-17 | - | 200.251 | 136.934 | 15 | 5 | 0 | 0 | 136.934 | 48.317 | 76% |
68% December - 2017 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Summary submitted to CA for handing over of laboratories to PKHA. |
No Image |
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 15 | 0 | 0 | 136.934 | 48.317 | 76% |
68% November - 2017 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Bid evaluation under process. |
No Image |
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 15 | 6.75 | 0 | 136.934 | 48.317 | 76% |
68% October - 2017 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Bid evaluation under process. |
No Image |
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
07-05-15 | - | - | 24-01-17 | - | 200.251 | 136.934 | 15 | 15 | 6.75 | 0 | 136.934 | 48.317 | 76% |
68% September - 2017 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Bid evaluation under process. |
No Image |
69 (OG) |
140837-Construction of Hanger for MI-17 at Peshawar Airport. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 351.183 | 27.925 | 0.001 | 0.001 | 0.0005 | 0 | 27.925 | 323.257 | 8% |
8% September - 2018 |
New site and scope NOC issued by Base Commander. Work in progress. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
07-05-15 | - | - | 24-01-17 | - | 200.251 | 136.934 | 15 | 15 | 6.75 | 0 | 136.934 | 48.317 | 76% |
68% August - 2017 |
8 Nos vehicles, 7 lab equipments - procured. Civil work in main lab completed. Bid evaluation under process. |
No Image |
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
07-05-15 | - | - | 24-01-17 | - | 200.251 | 136.934 | 15 | 15 | 6.75 | 0 | 136.934 | 48.317 | 76% |
68% July - 2017 |
8 Nos vehicles, 7 lab equipments - procured. Civil work in main lab completed. Bid evaluation under process. |
No Image |
69 (OG) |
140837-Construction of Hanger for MI-17 at Peshawar Airport. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 351.183 | 27.925 | 0.001 | 0.001 | 0.0005 | 0 | 27.925 | 323.257 | 8% |
8% July - 2018 |
New site and scope NOC issued by Base Commander. Work in progress. |
No Image |
Peshawar | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 0 | 0 | 0 | 136.934 | 48.317 | 76% |
68% June - 2018 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification in progress. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 5 | 5 | 0 | 136.934 | 48.317 | 76% |
68% May - 2018 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre qualification in progress. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 8.25 | 8.25 | 0 | 136.934 | 48.317 | 76% |
68% April - 2018 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Summary submitted to CA for handing over of laboratories to PKHA. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 18.25 | 18.25 | 0 | 136.934 | 48.317 | 76% |
68% March - 2018 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Summary submitted to CA for handing over of laboratories to PKHA. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 10 | 10 | 0 | 136.934 | 48.317 | 76% |
68% February - 2018 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Summary submitted to CA for handing over of laboratories to PKHA. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
69 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 136.934 | 15 | 5 | 0 | 0 | 136.934 | 48.317 | 76% |
68% January - 2018 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Summary submitted to CA for handing over of laboratories to PKHA. |
No Image |
1) Lab Equipments (7 Nos) 2) Main Lab (civil work) | |||||||||||||||||||
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 4.97 | 0 | 20.134 | 0 | 100% |
80% December - 2020 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 4.97 | 0 | 20.134 | 0 | 100% |
80% December - 2020 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 2.5 | 0 | 20.134 | 0 | 100% |
80% October - 2020 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 2.5 | 0 | 20.134 | 0 | 100% |
80% September - 2020 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 2.5 | 0 | 20.134 | 0 | 100% |
80% August - 2020 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 15.446 | 4.97 | 4.97 | 4.97 | 2.97 | 18.416 | 4.688 | 81% |
73% May - 2021 |
07- Units
1. Completed & H/O
2. Work yet not started
3. Completed & H/O
4. Completed & H/O
5. Completed & H/O
6. Finshing stage
7. Work yet not started |
No Image |
1 CVC Malik Mira Jan Sarwaki
2 CVC Darak Khan Kot Ladha
3 CVC Dramoon Kone Ladha
4 CVC Gul Muhammad Kot Laya Khel Makin
5 CVC, Falaz Jan Kot Patella Ladha
6 CVC, Peshawar Khan Kot Ladha
7 CVC, Bashir Khan Kot Ghundakai Jalal Khel Sarwakai
Scope of work:
| |||||||||||||||||||
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 4.97 | 0.957 | 21.091 | 0 | 100% |
84% April - 2021 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
1 CVC Malik Mira Jan Sarwaki
2 CVC Darak Khan Kot Ladha
3 CVC Dramoon Kone Ladha
4 CVC Gul Muhammad Kot Laya Khel Makin
5 CVC, Falaz Jan Kot Patella Ladha
6 CVC, Peshawar Khan Kot Ladha
7 CVC, Bashir Khan Kot Ghundakai Jalal Khel Sarwakai | |||||||||||||||||||
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 4.97 | 0.957 | 21.091 | 0 | 100% |
84% March - 2021 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
1 CVC Malik Mira Jan Sarwaki
2 CVC Darak Khan Kot Ladha
3 CVC Dramoon Kone Ladha
4 CVC Gul Muhammad Kot Laya Khel Makin
5 CVC, Falaz Jan Kot Patella Ladha
6 CVC, Peshawar Khan Kot Ladha
7 CVC, Bashir Khan Kot Ghundakai Jalal Khel Sarwakai | |||||||||||||||||||
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 4.97 | 0.957 | 21.091 | 0 | 100% |
84% February - 2021 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
1 CVC Malik Mira Jan Sarwaki
2 CVC Darak Khan Kot Ladha
3 CVC Dramoon Kone Ladha
4 CVC Gul Muhammad Kot Laya Khel Makin
5 CVC, Falaz Jan Kot Patella Ladha
6 CVC, Peshawar Khan Kot Ladha
7 CVC, Bashir Khan Kot Ghundakai Jalal Khel Sarwakai | |||||||||||||||||||
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 4.97 | 4.97 | 0 | 20.134 | 0 | 100% |
80% January - 2021 |
07- Units
Completed & H/O =04
Work not yet started =03 |
No Image |
1 CVC Malik Mira Jan Sarwaki
2 CVC Darak Khan Kot Ladha
3 CVC Dramoon Kone Ladha
4 CVC Gul Muhammad Kot Laya Khel Makin
5 CVC, Falaz Jan Kot Patella Ladha
6 CVC, Peshawar Khan Kot Ladha
7 CVC, Bashir Khan Kot Ghundakai Jalal Khel Sarwakai | |||||||||||||||||||
69 (OG) |
191071-140293-Construction of Buildings for 07 Existing CVCs and CVDs in Closed Area, SWA. [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.104 | 20.134 | 4.97 | 0 | 0 | 0 | 20.134 | 0 |
July - 2020 |
No Image | ||
Pages : 1 |