Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2018, September - 2019, October - 2020, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 4

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
- 30-06-18 - 12-04-16 - 250 4.5 19.243 19.243 19.243 8.659 13.159 226.257 9% 5%
December - 2017
4 units - 1 completed, 2 finishing in progress, 1 structure work completed.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
- 30-06-18 - 12-04-16 - 250 4.5 19.243 19.243 19.243 4.021 8.521 226.257 9% 3%
September - 2017
4 units - 1 completed, 3 in progress.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
- 30-06-18 - 12-04-16 - 250 4.5 19.243 19.243 19.243 0 4.5 226.257 9% 2%
August - 2017
4 units - 1 completed, 3 in progress.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
- 30-06-18 - 12-04-16 - 250 4.5 19.243 19.243 19.243 0 4.5 226.257 9% 2%
July - 2017
4 units - 1 completed, 3 in progress.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 4.5 19.243 19.243 19.243 4.021 8.521 226.257 9% 3%
November - 2017
4 units - 1 completed, 3 in progress.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 4.5 19.243 19.243 19.243 4.021 8.521 226.257 9% 3%
October - 2017
4 units - 1 completed, 3 in progress.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 23.418 28.955 28.955 28.955 28.955 52.373 197.627 21% 21%
June - 2018
4 units - 1 completed, 3 in progress.
No Image
1) Lavatory Block at GPGC, Abbottabad
2) Hostel at GGDC Nawanshehr Abbottabad
3) 04-Nos Class Rooms in GGDC Havelian Abbottabad
4) Bus Shed in GGDC Qalandarabad, Abbottabad
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 23.418 34.243 34.243 34.243 18.147 41.565 192.339 23% 17%
May - 2018
4 units - 1 completed, 3 in progress.
No Image
1) Lavatory Block at GPGC, Abbottabad
2) Hostel at GGDC Nawanshehr Abbottabad
3) 04-Nos Class Rooms in GGDC Havelian Abbottabad
4) Bus Shed in GGDC Qalandarabad, Abbottabad
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 23.418 34.243 34.243 34.243 18.147 41.565 192.339 23% 17%
April - 2018
4 units - 1 completed, 3 in progress.
No Image
1) Lavatory Block at GPGC, Abbottabad
2) Hostel at GGDC Nawanshehr Abbottabad
3) 04-Nos Class Rooms in GGDC Havelian Abbottabad
4) Bus Shed in GGDC Qalandarabad, Abbottabad
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 23.418 34.243 34.243 34.243 18.147 41.565 192.339 23% 17%
March - 2018
4 units - 1 completed, 3 in progress.
No Image
1) Lavatory Block at GPGC, Abbottabad
2) Hostel at GGDC Nawanshehr Abbottabad
3) 04-Nos Class Rooms in GGDC Havelian Abbottabad
4) Bus Shed in GGDC Qalandarabad, Abbottabad
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 23.418 19.243 19.243 19.243 12.772 36.19 207.339 17% 14%
February - 2018
4 units - 1 completed, 3 in progress.
No Image
1) Lavatory Block at GPGC, Abbottabad
2) Hostel at GGDC Nawanshehr Abbottabad
3) 04-Nos Class Rooms in GGDC Havelian Abbottabad
4) Bus Shed in GGDC Qalandarabad, Abbottabad
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 4.5 19.243 19.243 19.243 8.659 13.159 226.257 9% 5%
January - 2018
4 units - 1 completed, 2 finishing in progress, 1 structure work completed.
No Image
1) Lavatory Block at GPGC, Abbottabad 2) Hostel at GGDC Nawanshehr A?Abad   3) 04-Nos Class Rooms in GGDC Havelian Abbottabad 4) Bus Shed in GGDC Qalandarabad, Abbottabad
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-08-16 30-06-18 - 12-04-16 - 16.93 0 0.4 0.4 0.4 0.363 0.363 16.53 2% 2%
December - 2017
Completed & H/O.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
- 30-06-18 - 12-04-16 - 16.93 0 0 0 0 0 0 16.93 - -
September - 2017
Completed.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
- 30-06-18 - 12-04-16 - 16.93 0 0 0 0 0 0 16.93 - -
August - 2017
Completed.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
- 30-06-18 - 12-04-16 - 16.93 0 0 0 0 0 0 16.93 - -
July - 2017
Completed.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 0 0.4 0.4 0.4 0.363 0.363 16.53 2% 2%
November - 2017
Completed & H/O.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 0 0.4 0.4 0.4 0.263 0.263 16.53 2% 2%
October - 2017
Completed.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 16.53 0.4 0.4 0.4 0.363 16.893 0 100% 100%
June - 2018
Completed & H/O.
No Image
GDC No.2 Bannu (4 class rooms and library block)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 16.53 0.4 0.4 0.4 0.363 16.893 0 100% 100%
May - 2018
Completed & H/O.
No Image
GDC No.2 Bannu (4 class rooms and library block)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 16.53 0.4 0.4 0.4 0.363 16.893 0 100% 100%
April - 2018
Completed & H/O.
No Image
GDC No.2 Bannu (4 class rooms and library block)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 16.53 0.4 0.4 0.4 0.363 16.893 0 100% 100%
March - 2018
Completed & H/O.
No Image
GDC No.2 Bannu (4 class rooms and library block)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 16.53 0.4 0.4 0.4 0.363 16.893 0 100% 100%
February - 2018
Completed & H/O.
No Image
GDC No.2 Bannu (4 class rooms and library block)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
30-11--1 30-11--1 - 30-11--1 - 16.93 0 0.4 0.4 0.4 0.363 0.363 16.53 2% 2%
January - 2018
Completed & H/O.
No Image
GDC No.2 Bannu (4 class rooms and library block)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
06-05-16 30-06-18 - 12-04-16 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
December - 2017
Completed (2 units).
No Image
1) GPGC Charsadda (group latrin)
2) GEC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
06-05-16 30-06-18 - 12-04-16 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
September - 2017
Completed (2 units).
No Image
1) GPGC Charsadda (group latrin)
2) GEC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
06-05-16 30-06-18 - 12-04-16 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
August - 2017
Completed (2 units).
No Image
1) GPGC Charsadda (group latrin)
2) GEC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
06-05-16 30-06-18 - 12-04-16 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
July - 2017
Completed (2 units).
No Image
1) GPGC Charsadda (group latrin)
2) GEC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
November - 2017
Completed (2 units).
No Image
1) GPGC Charsadda (group latrin)
2) GEC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
October - 2017
Completed (2 units).
No Image
1) GPGC Charsadda (group latrin)
2) GEC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
June - 2018
Completed (2 units).
No Image
1) GPGC Charsadda (group latrine)
2) GDC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
May - 2018
Completed (2 units).
No Image
1) GPGC Charsadda (group latrine)
2) GDC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
April - 2018
Completed (2 units).
No Image
1) GPGC Charsadda (group latrine)
2) GDC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
March - 2018
Completed (2 units).
No Image
1) GPGC Charsadda (group latrine)
2) GDC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
February - 2018
Completed (2 units).
No Image
1) GPGC Charsadda (group latrine)
2) GDC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 4.057 3.106 0 0 0 0 3.106 0.951 - 77%
January - 2018
Completed (2 units).
No Image
1) GPGC Charsadda (group latrine)
2) GDC Tangi (bus shed)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
- 30-06-18 - 12-04-16 - 14.057 0 7 7 7 0 0 7.057 50% -
December - 2017
Excavation in progress.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
- 30-06-18 - 12-04-16 - 14.057 0 7 7 7 0 0 7.057 50% -
September - 2017
Work order issued. Demolition estimate submitted for approval. Site not available.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
- 30-06-18 - 12-04-16 - 14.057 0 7 7 7 0 0 7.057 50% -
August - 2017
Work order issued. Demolition estimate submitted for approval.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
- 30-06-18 - 12-04-16 - 14.057 0 0 0 0 0 0 14.057 - -
July - 2017
Work order issued. Demolition estimate submitted for approval.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 7 7 7 0 0 7.057 50% -
November - 2017
Work order issued. Demolition estimate submitted for approval. Site not available.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 7 7 7 0 0 7.057 50% -
October - 2017
Work order issued. Demolition estimate submitted for approval. Site not available.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 10.787 10.787 10.787 10.787 10.787 3.27 77% 77%
June - 2018
Completed.
No Image
GGDC Kulachi DI.Khan (5 Nos class rooms)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 12 12 12 9.095 9.095 2.057 85% 65%
May - 2018
GF plastering in progress. FF roof laid.
No Image
GGDC Kulachi DI.Khan (5 Nos class rooms)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 12 12 12 7 7 2.057 85% 50%
April - 2018
GF plastering in progress. FF roof laid.
No Image
GGDC Kulachi DI.Khan (5 Nos class rooms)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 12 12 12 7 7 2.057 85% 50%
March - 2018
GF roof laid. FF upto roof level.
No Image
GGDC Kulachi DI.Khan (5 Nos class rooms)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 7 7 7 2.482 2.482 7.057 50% 18%
February - 2018
GF roof shuttering in progress.
ADP's Images
GGDC Kulachi DI.Khan (5 Nos class rooms)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 14.057 0 7 7 7 2.482 2.482 7.057 50% 18%
January - 2018
Excavation in progress.
No Image
GGDC Kulachi DI.Khan (5 Nos class rooms)
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Dir Lower
16-07-16 30-06-18 - 12-04-16 - 14.4 7.319 4.35 4.35 4.35 4.35 11.669 2.731 81% 81%
December - 2017
Completed.
No Image
633
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Dir Lower
- 30-06-18 - 12-04-16 - 14.4 7.319 4.35 4.35 4.35 3.754 11.073 2.731 81% 77%
September - 2017
Block - finishing in progress.
No Image
Pages : 1 2 3 4