Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 0 | 0 | 278.386 | 1% |
- December - 2018 |
Work order issued. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 0 | 0 | 278.386 | 1% |
- November - 2018 |
Work order issued. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 0 | 0 | 278.386 | 1% |
- November - 2018 |
Work order issued. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 3 | 3 | 278.386 | 1% |
1% April - 2019 |
Layout given. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 3 | 3 | 278.386 | 1% |
1% March - 2019 |
Layout given. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 3 | 3 | 278.386 | 1% |
1% March - 2019 |
Layout given. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 3 | 3 | 278.386 | 1% |
1% February - 2019 |
Layout given. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 3 | 3 | 278.386 | 1% |
1% January - 2019 |
Layout given. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
621 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 60.0637 | 10 | 10 | 5 | 5 | 65.0637 | 6.452 | 92% |
85% September - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
Bannu | |||||||||||||||||||
621 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 60.0637 | 10 | 10 | 5 | 0 | 60.0637 | 6.452 | 92% |
78% July - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Cannot be completed to court case. |
No Image |
Bannu | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 6 | 6.3 | 96.982 | 6% |
6% December - 2018 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 3 | 3.3 | 96.982 | 6% |
3% November - 2018 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 3 | 3.3 | 96.982 | 6% |
3% November - 2018 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 6 | 6.3 | 96.982 | 6% |
6% April - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 6 | 6.3 | 96.982 | 6% |
6% March - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 6 | 6.3 | 96.982 | 6% |
6% March - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 6 | 6.3 | 96.982 | 6% |
6% February - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 6 | 6 | 6 | 6 | 6.3 | 96.982 | 6% |
6% January - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- December - 2018 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- November - 2018 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- November - 2018 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- April - 2019 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- March - 2019 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- March - 2019 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- February - 2019 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- January - 2019 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
02-10-12 | 30-06-18 | - | 12-04-12 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% December - 2017 |
Main building, cafetaria, guard room - completed, 50-student hostel, mosque - finishing in progress. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
02-10-12 | 30-06-18 | - | 12-04-12 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% September - 2017 |
Main building, cafetaria, guard room - completed, 50-student hostel, mosque - finishing in progress. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
02-10-12 | 30-06-18 | - | 12-04-12 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% August - 2017 |
Main building, cafetaria, guard room - completed, 50-student hostel, mosque - finishing in progress. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
02-10-12 | 30-06-18 | - | 12-04-12 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% July - 2017 |
Main building, cafetaria, guard room - completed, 50-student hostel, mosque - finishing in progress. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% November - 2017 |
Main building, cafetaria, guard room - completed, 50-student hostel, mosque - finishing in progress. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% October - 2017 |
Main building, cafetaria, guard room - completed, 50-student hostel, mosque - finishing in progress. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% June - 2018 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos students hostel/cafeteria/mosque/guard room/development/protection works) | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% May - 2018 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos students hostel/cafeteria/mosque/guard room/development/protection works) | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% April - 2018 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos students hostel/cafeteria/mosque/guard room/development/protection works) | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% March - 2018 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos students hostel/cafeteria/mosque/guard room/development/protection works) | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% February - 2018 |
Completed. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% January - 2018 |
Completed. |
No Image |
1) DBC Lal Qilla Maidan | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
02-11-12 | 30-06-18 | - | 12-04-12 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% December - 2017 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
02-11-12 | 30-06-18 | - | 12-04-12 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% September - 2017 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
02-11-12 | 30-06-18 | - | 12-04-12 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% August - 2017 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
02-11-12 | 30-06-18 | - | 12-04-12 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% July - 2017 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% November - 2017 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% October - 2017 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% June - 2018 |
All buildings completed. Developmental works in progress. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% May - 2018 |
All buildings completed. Developmental works in progress. Demand Rs.12.864 m. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% April - 2018 |
All buildings completed. Developmental works in progress. Demand Rs.12.864 m. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% March - 2018 |
All buildings completed. Developmental works in progress. Demand Rs. 12.864 M |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% February - 2018 |
All buildings completed. Developmental works in progress. |
ADP's Images |
1) GDC Barawal PK-91 | |||||||||||||||||||
621 (OG) |
50179-Establishment of Govt Colleges in Khyber Pakhtunkhwa (Phase-II). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 161.952 | 0 | 0 | 0 | 0 | 161.952 | 0 | - |
100% January - 2018 |
All buildings completed. Developmental works in progress. |
No Image |
1) GDC Barawal PK-91 | |||||||||||||||||||
Pages : 1 2 3 4 |