Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 5 | 0 | 0 | 52.013 | 16% |
- December - 2018 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 5 | 0 | 0 | 52.013 | 16% |
- November - 2018 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 5 | 0 | 0 | 52.013 | 16% |
- November - 2018 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 4.5 | 0.102 | 0.102 | 52.013 | 16% |
0% April - 2019 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 4.5 | 0.102 | 0.102 | 52.013 | 16% |
0% March - 2019 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 4.5 | 0.102 | 0.102 | 52.013 | 16% |
0% March - 2019 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 4.5 | 0.102 | 0.102 | 52.013 | 16% |
0% February - 2019 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 10 | 10 | 4.5 | 0.102 | 0.102 | 52.013 | 16% |
0% January - 2019 |
Work in progress. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
- | - | - | 23-12-16 | - | 283.622 | 68.51 | 20 | 40 | 40 | 40 | 108.51 | 195.112 | 31% |
38% December - 2017 |
Main building - foundation, BW, developmental work in progress. |
No Image |
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
- | - | - | 23-12-16 | - | 283.622 | 68.51 | 20 | 20 | 0 | 0 | 68.51 | 195.112 | 31% |
24% September - 2017 |
Main building - foundation, BW, developmental work in progress. |
No Image |
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
- | - | - | 23-12-16 | - | 283.622 | 68.51 | 20 | 20 | 0 | 0 | 68.51 | 195.112 | 31% |
24% August - 2017 |
Main building - foundation, BW, developmental work in progress. |
No Image |
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
- | - | - | 23-12-16 | - | 283.622 | 68.51 | 20 | 20 | 0 | 0 | 68.51 | 195.112 | 31% |
24% July - 2017 |
Main building - foundation, BW, developmental work in progress. |
No Image |
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 20 | 10 | 10 | 78.51 | 195.112 | 31% |
28% November - 2017 |
Main building - foundation, BW, developmental work in progress. |
No Image |
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 20 | 0 | 0 | 68.51 | 195.112 | 31% |
24% October - 2017 |
Main building - foundation, BW, developmental work in progress. |
No Image |
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 50 | 50 | 50 | 118.51 | 195.112 | 31% |
42% June - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 50 | 50 | 49.247 | 117.757 | 195.112 | 31% |
42% May - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 50 | 50 | 49.247 | 117.757 | 195.112 | 31% |
42% April - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 45 | 45 | 45 | 113.51 | 195.112 | 31% |
40% March - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 45 | 45 | 44.948 | 113.458 | 195.112 | 31% |
40% February - 2018 |
Main building - foundation, BW, developmental work in progress. |
ADP's Images |
PK-21 Charsadda | |||||||||||||||||||
618 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 68.51 | 20 | 45 | 45 | 44.324 | 112.834 | 195.112 | 31% |
40% January - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- December - 2019 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- November - 2019 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- October - 2019 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- September - 2019 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- August - 2019 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- May - 2020 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- April - 2020 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- March - 2020 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- February - 2020 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.05 | 0 | 0 | 0 | 0 | 0 | 0 | 40.05 | - |
- January - 2020 |
Work order issued to contractor on 08/12/2017. Site selected, mutation awaited. |
No Image |
Hangu | |||||||||||||||||||
618 (OG) |
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 29.75 | 4.942 | 4.942 | 2.471 | 0 | 29.75 | 0 | 100% |
99% September - 2018 |
Length 3 Km - earth work, road work completed, structure work 30% completed. Court Case. |
No Image |
PK-74, Lakki Marwat | |||||||||||||||||||
618 (OG) |
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 29.75 | 4.942 | 4.942 | 2.471 | 0 | 29.75 | 0 | 100% |
99% July - 2018 |
Length 3 Km - earth work, road work completed, structure work 30% completed. |
No Image |
PK-74, Lakki Marwat | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- December - 2019 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- November - 2019 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- October - 2019 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- September - 2019 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- August - 2019 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- May - 2020 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- April - 2020 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- March - 2020 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- February - 2020 |
No Image | |
Hangu | |||||||||||||||||||
618 (OG) |
150726-Establishment of public parks in Havelian-Abbottabad, Thana-Malakand and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 82.17 | 10 | 10 | 0 | 0 | 82.17 | 0 | - |
- January - 2020 |
No Image | |
Hangu | |||||||||||||||||||
Pages : 1 |