Progressive Review for the month(s) of : January - 2019, January - 2020, February - 2020, February - 2019, March - 2020, March - 2019, April - 2020, April - 2019, May - 2020, July - 2018, August - 2019, September - 2018, September - 2019, October - 2019, November - 2018, November - 2019, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
608
(OG)
140985-F/S, Design and Construction / Rehabilitation of Roads (a) Awan Road (b) Loke Road (c) Jabal Wala Road (d) Nadeem Shah Road (e) Kurar Shedi (8 Kms), DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 79.96 45.441 34.519 34.519 17.26 17.26 62.701 0 100% 78%
September - 2018
Length 8 Km (width 12 ft) - 8 Km completed, structure work in progress.
No Image
1) Awan road 2 Km
2) Loak road 2 Km
3) Bali Shumali road 1 Km shifted to Jabbar Wala
4) Nadeem Shah road 1 Km
5) Kurrar Shiddi road PK-65 2 Km
608
(OG)
140985-F/S, Design and Construction / Rehabilitation of Roads (a) Awan Road (b) Loke Road (c) Jabal Wala Road (d) Nadeem Shah Road (e) Kurar Shedi (8 Kms), DI.Khan.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 79.96 45.441 34.519 34.519 17.26 0 45.441 0 100% 57%
July - 2018
Length 8 Km (width 12 ft) - 8 Km completed, structure work in progress.
No Image
1) Awan road 2 Km
2) Loak road 2 Km
3) Bali Shumali road 1 Km shifted to Jabbar Wala
4) Nadeem Shah road 1 Km
5) Kurrar Shiddi road PK-65 2 Km
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
December - 2019
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
November - 2019
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
October - 2019
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
September - 2019
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
August - 2019
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
May - 2020
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
April - 2020
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
March - 2020
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
February - 2020
No Image
608
(OG)
170269-Sewerage System & Treatment Plant at Kalabat Township (PC-II Approved)
Haripur
30-11--1 30-11--1 - 30-11--1 - 200 5 20 20 0 0 5 0 - -
January - 2020
No Image
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 7.5 7.5 38.4 292.53 14% 11%
December - 2018
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 0 0 30.9 292.53 14% 9%
November - 2018
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 0 0 30.9 292.53 14% 9%
November - 2018
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 15 11.25 42.15 292.53 14% 12%
April - 2019
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 11.25 11.25 42.15 292.53 14% 12%
March - 2019
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 11.25 11.25 42.15 292.53 14% 12%
March - 2019
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 11.25 11.25 42.15 292.53 14% 12%
February - 2019
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat
608
(OG)
160445-Construction of Judicial Complex, Kohat at KDA Phase-I.
Kohat
30-11--1 30-11--1 - 30-11--1 - 338.43 30.9 15 15 11.25 7.5 38.4 292.53 14% 11%
January - 2019
MAK consultant for Phase-I. Work started. Land payment made.
No Image
KDA, Kohat